| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Apr 23, 2021 | 60V39 | LakeDistrict 1 | This traffic signal installation and channelization project begins about 652.5 feet (0.12 miles) west of the intersection of IL 173 (FAP 303) and North Lake Avenue and proceeds in a southerly/easterly direction for 1462.3 feet (0.28 miles). This project also begins at the center of the intersection of IL 173 (FAP 303) and North Lake Avenue. | — | Executed | Dunnet Bay Construction Company $3,128,974 · | ||
| Apr 23, 2021 | 60X72 | CookDistrict 1 | The construction of a parking lot, storm sewer removal and replacement of existing frame and lid with bolted f The improvement consists of the construction of a parking lot, storm sewer removal and replacement of existing frame and lid with bolted frame and ltd. The work is located on IL 64 (North Ave.) at pump station #12 in Melrose Park. | — | Executed | Martam Construction Incorporated $361,804 · | ||
| Apr 23, 2021 | 61G09 | CookDistrict 1 | Resurfacing Park Boulevard from Irving Park Road to Schaumburg Road in Streamwood. | — | Executed | A Lamp Concrete Contractors, Inc. $1,304,037 · | ||
| Apr 23, 2021 | 61G58 | KaneDistrict 1 | Roadway reconstruction, lighting, water main, landscaping, pavement markings, on East New York Street from Farnsworth Avenue to Welsh Drive in Aurora. | — | Executed | Martam Construction Incorporated $7,777,000 · | ||
| Apr 23, 2021 | 61G91 | KaneDistrict 1 | Traffic Signal modernization at three intersections, sidewalk improvements, and pavement markings at Fabyan Parkway and IL 131, Orchard Road at Acutt Road and Rochester Drive, and Orchard Road from US 30 to Jericho Road in Batavia, Montgomery and unincorporated Kane County. | — | Executed | H & H Electric Co. $645,740 · | ||
| Apr 23, 2021 | 61G94 | McHenryDistrict 1 | Remove existing box culvert, construct single-span CIP slab bridge, and reconstruct approach pavement on Kishwaukee Valley Road over a tributary of Rush Creek, 0.2 miles east of Root Road. | — | Executed | Lorig Construction Company $1,545,703 · | ||
| Apr 23, 2021 | 61G95 | WillDistrict 1 | Resurfacing, curb and gutter, sidewalk replacement, ornamental lighting, brick paver sidewalk, landscaping and pavement markings on IL 171 from 11th Street to 10th Street and on IL 7 from IL 171 to Hamilton Street in Lockport. | — | Executed | R. W. Dunteman Company $1,793,189 · | ||
| Apr 23, 2021 | 61G96 | WillDistrict 1 | Resurfacing, curb and gutter replacement, sidewalk replacement, and pavement markings on West Street from Corning Avenue to Joliet Road in Peotone. | — | Executed | P. T. Ferro Construction Co. $321,841 · | ||
| Apr 23, 2021 | 61G97 | DuPageDistrict 1 | Resurfacing Eola Road from Oakhurst Drive to US 34 in Aurora. | — | Executed | K-Five Construction Corporation $1,046,723 · | ||
| Apr 23, 2021 | 61G99 | CookDistrict 1 | Concrete Sidewalk, curb and gutter replacement, tree removal, and landscaping on US 30 from Orchard Drive to the east village limits on Rockwell Street in Park Forest. | — | Executed | Copenhaver Construction, Inc. $243,209 · | ||
| Apr 23, 2021 | 61H00 | WillDistrict 1 | Resurfacing, curb and gutter replacement, sidewalk replacement, and pavement markings on Court Street from Elder Lane to Eastgate Avenue in Monee. | — | Executed | Iroquois Paving Corporation $256,749 · | ||
| Apr 23, 2021 | 61H01 | CookDistrict 1 | Resurfacing, HMA pavement patching, curb and gutter repairs on Old Willow Road from South Wolf Road to US 45 in Prospect Heights. | — | Executed | Arrow Road Construction Co. $510,388 · | ||
| Apr 23, 2021 | 61H02 | DuPageDistrict 1 | Resurfacing, curb and gutter, traffic signals, sidewalks and pavement markings on Grand Avenue, from US 20 to County Line Road in Elmhurst and Bensenville. | — | Executed | K-Five Construction Corporation $3,916,382 · | ||
| Apr 23, 2021 | 61H03 | McHenryDistrict 1 | Resurfacing Haligus Road from north of Ballard Road to Lakewood Road in Lakewood. | — | Executed | Geske and Sons, Inc. $510,590 · | ||
| Apr 23, 2021 | 61H04 | McHenryDistrict 1 | Resurfacing Valley View Road from Nish Road to south of IL 176 in Prairie Grove | — | Executed | Geske and Sons, Inc. $367,518 · | ||
| Apr 23, 2021 | 61H06 | CookDistrict 1 | Streetscape improvements on St. Charles Road from Mannheim Road to 25th Avenue in Bellwood. | — | Executed | Landmark Contractors, Inc. $964,551 · | ||
| Apr 23, 2021 | 61H08 | CookDistrict 1 | Resurfcing, curb and gutter, sidewalk replacement, detector loops and pavement markings on Kensington Road from Dryden Place to Regency Drive West in Arlington Heights. | — | Executed | Arrow Road Construction Co. $1,282,651 · | ||
| Apr 23, 2021 | 61H09 | CookDistrict 1 | Resurfacing Salem Drive from the village limits to Bode Road, Jones Road from Highland Boulevard to Hassel Road, and Hassell Road from Rosedale to Jones Road in Hoffman Estates. | — | Executed | Schroeder Asphalt Services, Inc. $651,585 · | ||
| Apr 23, 2021 | 62633 | CookDistrict 1 | (4,391-Ft) Intersection improvement including channelization, traffic signal modernization and resurfacing of IL 58 at Niles Center Rd. and at US 41 (Skokie Blvd.) in the Village of Skokie. | — | Executed | Alliance Contractors, Inc. $4,496,491 · | ||
| Apr 23, 2021 | 62K80 | CookWillDistrict 1 | Demolition and reconstruction of the existing bridge deck and concrete approaches, resurfacing to meet the bridge approaches, reconstruction and expansion of outside shoulders, removal and replacement of existing guar guardrail, and various drainage and grading improvements. | — | Executed | D. Construction, Inc. $2,056,069 · | ||
| Apr 23, 2021 | 62L52 | CookDistrict 1 | (1.762-Mile) Cleaning and sealing longitudinal joints in the existing HMA pavement between traffic lanes and curb and gutter, restriping pavement marking in the City of Chicago, Lake and North Chicago Townships. | — | Executed | SKC Construction, Inc. $183,344 · | ||
| Apr 23, 2021 | 62L82 | DuPageDistrict 1 | (3.9-Mile) Crack and joint sealing on US 20 (Lake Street) from I-355 to IL 83 (Kingery Highway) within the Village of Addison. | — | Executed | Freehill Asphalt, Inc. $335,213 · | ||
| Apr 23, 2021 | 62L89 | CookDistrict 1 | (1.73-Mile) SMART overlay (resurfacing) and ADA improvement project on Dempster St. from east of Skokie Blvd. to McCormick Ave. within the Village of Skokie in Cook County. | — | Executed | Builders Paving, LLC $2,092,030 · | ||
| Apr 23, 2021 | 62M04 | CookDistrict 1 | (3.553-Mile) Crack and Joint Sealing pavement preservation project. Includes renewal of pavement markings. Location: FAP 344: IL 83 from S. of Weiland Rd to Palatine Rd in the City of Prospect Heights and the Village | — | Executed | SKC Construction, Inc. $179,385 · | ||
| Apr 23, 2021 | 62M13 | CookDistrict 1 | SMART Overlay, ADA Improvements: HMA removal and replacement (single pass), pavement patching, pavement markings. Location: FAU 3520: Gross Point Road from N of Oakton St to Howard St in the Village of Morton Grove and Skokie. | — | Executed | Peter Baker & Son Co. $545,253 · | ||
| Apr 23, 2021 | 62M15 | WillDistrict 1 | (1.06-Mile) SMART Overlay, ADA Improvements: HMA removal and replacement (single pass), pavement patching, pavement markings. Location: FAP 112: IL 53 from South of I-55 to Joliet Road, in the Village of Bolingbrook and Romeoville. | — | Executed | K-Five Construction Corporation $1,563,017 · | ||
| Apr 23, 2021 | 62M16 | WillDistrict 1 | (2.78-Mile) Smart Overlay, ADA Improvements: HMA removal and replacement (single pass), pavement patching, pavement markings. Location: FAP 607: US 52/ 6/ 30 Jefferson St. from Joyce Rd.to Bluff St., within the City of Joliet. | — | Executed | D. Construction, Inc. $2,573,421 · | ||
| Apr 23, 2021 | 62M26 | CookDistrict 1 | Bridge deck overlay and joint repair The improvement of McHenry Road over Wheeling Drainage Ditch consists of bridge deck overlay and joint repair. The improvement is located in the Village of Wheeling in Cook County, IL. | — | Executed | Lorig Construction Company $446,325 · | ||
| Apr 23, 2021 | 62M27 | WillDistrict 1 | Bridge Deck and Approach repairs This improvement consists of Bridge Deck and Approach repairs. Structural repair of Concrete, deck scarification, deck latex concrete overlay, approach HMA overlay, bridge deck grooving in Green Garden Township. | — | Executed | P. T. Ferro Construction Co. $128,281 · | ||
| Apr 23, 2021 | 62M31 | CookDistrict 1 | This is a bridge repair project that includes bridge deck overlay, partial depth approach reconstruction, joint reconstruction, concrete bridge deck repair, full depth bridge deck repair. Located: IL Route 7 at 86th Ave. within within the Village of Palos Park. | — | Executed | Lorig Construction Company $298,774 · | ||
| Apr 23, 2021 | 62M36 | DuPageDistrict 1 | A full and partial depth deck and approach slab repairs, bridge deck scarification, a new latex concrete overl This project is located on IL.83 over the Salt Creek within the Village of Villa Park in DuPage County. This work consists of a full and partial depth deck and approach slab repairs, bridge deck scarification, a new latex concrete overlay, deck drain adjustments and pavement marking. | — | Executed | Martam Construction Incorporated $741,297 · | ||
| Apr 23, 2021 | 62M40 | CookDistrict 1 | Bridge Preservation Project, including bridge deck overlay (scarification and latex concrete overlay), deck repairs, reconstructing transverse joints. Location: Bridge carrying Roosevelt Rd over Des Plaines River, East of IL 171 in the Village of Forest Park in Cook County. | — | Executed | MYS, Incorporated $512,616 · | ||
| Apr 23, 2021 | 62N30 | CookDistrict 1 | A Bridge Substructure Repair in the City of Chicago, and the Village of Skokie and Wilmette in the Townships o (0.102-Mile) Improvement on I-94 at IL 50 (Cicero Ave.), II 58 (Dempster Ave.) and Lake Ave. consist of a Bridge Substructure Repair in the City of Chicago, and the Village of Skokie and Wilmette in the Townships of New Trier, Jefferson and Niles. | — | Executed | Rausch Infrastructure, LLC $830,616 · | ||
| Apr 23, 2021 | 62N92 | CookDuPageDistrict 1 | Litter/Debris removal from edge of pavement to the Pedestrian Barrier on I-55 - Stevenson expressway from IL 4 (150-Mile) Improvement consists of Litter/Debris removal from edge of pavement to the Pedestrian Barrier on I-55 - Stevenson expressway from IL 43 (Harlem Ave.) to I-355. | — | Executed | Western Remac, Inc. $207,720 · | ||
| Apr 23, 2021 | 64G99 | OgleDistrict 2 | Cold milling, Cold In-Place (CIP) Recycling, HMA resurfacing on IL Route 64 from 0.1 mile East of US 52 to 0.04 mile West of IL 26. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $1,497,763 · | ||
| Apr 23, 2021 | 64J97 | HenryDistrict 2 | 6.27 MILES, Resurfacing from Galva - Atkinson Road to West Street in Kewanee. | — | Executed | Advanced Asphalt Company $2,403,550 · | ||
| Apr 23, 2021 | 64M91 | LeeDistrict 2 | 0.80 miles, Cold milling, pavement patching, HMA resurfacing, ADA improvement and traffic signal modernization from West of Page drive to US 52/IL 26 in Dixon. | — | Executed | Martin & Company Excavating $2,016,252 · | ||
| Apr 23, 2021 | 64P29 | WinnebagoDistrict 2 | Milling, patching, and hot-mix asphalt resurfacing on IL Route 70 from Pecatonica River to 0.1 mile west of Safford Road in Rockford. | — | Executed | Rock Road Companies, Inc. $4,379,698 · | ||
| Apr 23, 2021 | 64P30 | LeeDistrict 2 | Cold milling, pavement patching and hot-mix asphalt resurfacing along US 52 from Water Street in Amboy to North of Henkle Road. | — | Executed | Advanced Asphalt Company $4,129,760 · | ||
| Apr 23, 2021 | 64P65 | WhitesideDistrict 2 | Removal and replacement of existing expansion joints on SN 098-0032 carrying US 30 over Elkhorn Creek. | — | Executed | Martin & Company Excavating $147,606 · | ||
| Apr 23, 2021 | 64P66 | CarrollDistrict 2 | Removal and replacement of existing expansion joints, along with partial replacement of the South bridge approach slab and the adjacent sidewalk on SN 008-0041 carrying IL 84 over the SOO line RR. | — | Executed | Martin & Company Excavating $187,212 · | ||
| Apr 23, 2021 | 64P68 | VariousDistrict 2 | Installing signs and posts along State maintained routes. | — | Executed | Countryman, Inc. $235,534 · | ||
| Apr 23, 2021 | 64P69 | HenryDistrict 2 | Cleaning and painting structural steel on SN's 037-0029 and 037-0030 carrying 1-80 over Mineral Creek located 0.7 mile North of US 6, and SN 037-0079 carrying US 6 over 1-80. | — | Executed | Three Star Painting, Inc. $396,650 · | ||
| Apr 23, 2021 | 64P70 | HenryDistrict 2 | Cleaning and painting structural steel on SN 037-0112 carrying TR 196-D over 1-80 located 0.9 mile southeast of IL 82, SN 037-0113 carrying TR 216 over 1-80 located 2.0 miles southeast of IL 82 and SN 037-0118 carrying TR 468 over 1-80 located 1.5 miles east of IL 78. | — | Executed | Three Star Painting, Inc. $595,000 · | ||
| Apr 23, 2021 | 64P71 | Rock IslandDistrict 2 | Cleaning and painting structural steel SN's 081-0030 and 081-0031 carrying I-280 over Case Creek located 2.0 miles west of I-74. | — | Executed | Three Star Painting, Inc. $179,995 · | ||
| Apr 23, 2021 | 64P72 | LeeDistrict 2 | Cleaning and painting structural steel on SN 052-0059 carrying Welland Road over 1-39. | — | Executed | Three Star Painting, Inc. $190,000 · | ||
| Apr 23, 2021 | 64P74 | WhitesideDistrict 2 | Milling and resurfacing on US 30 from Jackson Street to French Creek East of Morrison. | — | Executed | Martin & Company Excavating $438,325 · | ||
| Apr 23, 2021 | 64P96 | VariousDistrict 2 | Removal of dead trees along state maintained routes. | — | Executed | Endrizzi Contracting, Inc $375,100 · | ||
| Apr 23, 2021 | 66B52 | LaSalleDistrict 3 | The reconstruction of the existing intersection into a PCC roundabout The project is located in the intersection of US 6 and IL 178, north of Utica in LaSalle county and consists of the reconstruction of the existing intersection into a PCC roundabout. The project also includes earthwork, seeding, drainage improvements, permanent lighting and removal of existing traffic equipment. The project length is 0.42 miles. | — | Executed | R. W. Dunteman Company $2,442,377 · | ||
| Apr 23, 2021 | 66E14 | BureauDistrict 3 | 3P mill and resurface. | — | Executed | Advanced Asphalt Company $4,496,640 · | ||
| Apr 23, 2021 | 66K60 | BureauDistrict 3 | 7.3 miles of milling and resurfacing, ADA improvements. | — | Executed | Advanced Asphalt Company $2,816,475 · | ||
| Apr 23, 2021 | 66L01 | LaSalleDistrict 3 | 0.71 mile. Latex overlay, cleaning and painting of structural steel and expansion joint replacement. SN 050-0200 IL 251 over 1-39; 0.5 Miles north of IL 71. | — | Executed | D. Construction, Inc. $1,921,508 · | ||
| Apr 23, 2021 | 66L22 | IroquoisDistrict 3 | Bridge painting This work is located at Structure No. 038-0130, TR 95 over 1-57, approximately 3.48 miles South of IL 116 and Structure No. 038-0131 carrying TR 109 over 1-57, approximately 5.59 miles South of IL 116 in Iroquois. This work consists of bridge painting. | — | Executed | ERA-Valdivia Contractors, Inc. $384,278 · | ||
| Apr 23, 2021 | 66L28 | KankakeeDistrict 3 | Signal Mast Arm Removal and Replacement - at River St and Station St in Kankakee. | — | Executed | Van-Mack Electric Co. $210,000 · | ||
| Apr 23, 2021 | 66L30 | IroquoisKankakeeDistrict 3 | This project consists of 3.85 miles of shoulder widening and rumble strip installation on IL 1 from 150 feet west of W Circle Dr in St Anne in Kankakee County to E 3100N Rd in Iroquois County. | — | Executed | Iroquois Paving Corporation $1,088,767 · | ||
| Apr 23, 2021 | 66L32 | BureauDistrict 3 | The installation of approximately 5 This project consists of the installation of approximately 5.24 miles of high tension cable median barrier from the Henry/Bureau County Line to 0.42 miles West of 600E Rd. | — | Executed | Advanced Asphalt Company $1,112,433 · | ||
| Apr 23, 2021 | 66L33 | LaSalleDistrict 3 | The installation of approximately 5 This project consists of the installation of approximately 5.92 miles of high tension cable median barrier from 1.09 miles South of N 36th Rd to 0.88 miles South of N 42nd Rd in LaSalle County. | — | Executed | Advanced Asphalt Company $1,322,328 · | ||
| Apr 23, 2021 | 66L41 | IroquoisDistrict 3 | Removing existing HMA and aggregate subbase surfaces, repair and preparation of base course, and placing a pol This work is located at the Illinois Department of Transpiration, District 3, Buckley Maintenance Facility in Iroquois County. This work consists of removing existing HMA and aggregate subbase surfaces, repair and preparation of base course, and placing a polymer HMA asphalt binder cse. (2¼" lift) and a polymer HMA surface *See Remarks*. | — | Executed | Iroquois Paving Corporation $333,002 · | ||
| Apr 23, 2021 | 66L52 | GrundyDistrict 3 | This pollinator project is located at Three Rivers Rest Areas on I-80 west of Minooka. This work will include herbicide, seeding, planting, landscaping and maintenance. | — | Executed | Nettle Creek Nursery, Inc. $377,962 · | ||
| Apr 23, 2021 | 66L54 | DeKalbDistrict 3 | The removal and replacement of expansion joints and deck patching on SN 019-0036 This work is located at FAP 573 on US 30 on SN 019-0036 at Little Rock Creek 0.5 miles West of Hinckley in Dekalb County. This work consists of the removal and replacement of expansion joints and deck patching on SN 019-0036. | — | Executed | Martin & Company Excavating $250,265 · | ||
| Apr 23, 2021 | 66L56 | LaSalleLivingstonDistrict 3 | Placing aggregate wedge shoulder This work is located on FAP 786 (IL 170) beginning at the intersection of IL 170 and N 21st Rd in LaSalle County and ending at the intersection of IL 170 and IL 17 in Livingston County (+/- 12.0 miles). This work consists of placing aggregate wedge shoulder. | — | Executed | Phoenix Corporation of the Quad Cities $135,304 · | ||
| Apr 23, 2021 | 66L61 | KendallLaSalleDistrict 3 | The intent of this project is to repair and maintain traffic signals, flashing beacons, roadway lighting, and other electrical services that are requested by "on call" work orders in Kendall and LaSalle Counties. | — | Executed | H & H Electric Co. $49,983 · | ||
| Apr 23, 2021 | 66L62 | BureauLaSalleDistrict 3 | The intent of this project is to repair and maintain traffic signals, flashing beacons, roadway lighting, and other electrical services that are requested by "on call" work orders in Bureau and LaSalle Counties. | — | Executed | Laser Electric, Inc. $71,890 · | ||
| Apr 23, 2021 | 66L63 | GrundyDistrict 3 | The intent of this project is to repair and maintain traffic signals, flashing beacons, roadway lighting, and other electrical services that are requested by "on call" work orders in Grundy County. | — | Executed | Outsen Electric, Incorporated $51,970 · | ||
| Apr 23, 2021 | 66L64 | VariousDistrict 3 | The intent of this project is to repair and maintain traffic signals, flashing beacons, roadway lighting, and other electrical services that are requested by "on call" work orders in Livingston, Ford, Grundy, and Iroquois Counties. | — | Executed | Leo P. Kelly Electric, Incorporated $50,340 · | ||
| Apr 23, 2021 | 66L65 | IroquoisKankakeeDistrict 3 | The intent of this project is to repair and maintain traffic signals, flashing beacons, roadway lighting, and other electrical services that are requested by "on call" work orders in Kankakee and Iroquois Counties. | — | Executed | Outsen Electric, Incorporated $65,170 · | ||
| Apr 23, 2021 | 66L66 | DeKalbDistrict 3 | The intent of this project is to repair and maintain traffic signals, flashing beacons, roadway lighting, and other electrical services that are requested by "on call" work orders in DeKalb County. | — | Executed | H & H Electric Co. $54,015 · | ||
| Apr 23, 2021 | 66L70 | BureauDistrict 3 | Weed spraying to aid in weed control This project is located along FAI 80 (I-80) in Bureau county. The work consists of weed spraying to aid in weed control. | — | Executed | Endrizzi Contracting, Inc $99,891 · | ||
| Apr 23, 2021 | 68F68 | VariousDistrict 4 | Bridge deck sealing at various structures throughout District Four. | — | Executed | All States Painting, Inc. $189,900 · | ||
| Apr 23, 2021 | 68F76 | VariousDistrict 4 | Crack and joint sealing at various locations in Knox, Peoria, and Tazewell Counties. | — | Executed | Denler, Inc. $500,279 · | ||
| Apr 23, 2021 | 68F95 | VariousDistrict 4 | Pavement markings on various routes in various counties throughout District Four. | — | Executed | Varsity Striping & Construction Co. $300,626 · | ||
| Apr 23, 2021 | 68G09 | MarshallDistrict 4 | Rout and seal along Interstate 39 from 2 mile south of IL Route 17 to LaSalle County line and IL Route 18 from IL Route 29 in Henry to the Illinois River. | — | Executed | Freehill Asphalt, Inc. $239,675 · | ||
| Apr 23, 2021 | 68G18 | PeoriaDistrict 4 | Longitudinal joint repair and partial depth patching along US 150 (War Memorial Drive) from West of Brandywine Drive to IL 29 (Adams St) in Peoria. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $515,084 · | ||
| Apr 23, 2021 | 68G19 | VariousDistrict 4 | Installation of new traffic signal cabinets, traffic signal controllers, communications equipment, and video detection systems at various locations in District Four. | — | Executed | Laser Electric, Inc. $434,861 · | ||
| Apr 23, 2021 | 68G20 | MarshallMcLeanWoodfordDistrict 4 | Installation of communications duct, communications vaults, and fiber optic cable along Interstate 39 from the Interstate 55 interchange to Illinois Route 17 in District Four. | — | Executed | Gerstner Electric, Inc. $1,837,876 · | ||
| Apr 23, 2021 | 68G21 | PeoriaTazewellDistrict 4 | Installation of new traffic signal cabinets, traffic signal controllers, communications equipment, and video detection systems at various locations in District Four. | — | Executed | Laser Electric, Inc. $482,887 · | ||
| Apr 23, 2021 | 68G22 | WoodfordDistrict 4 | Removal of existing high mast towers and installation of new lighting system at Interstate 39 at the Minonk interchange and replacement of light towers at Interstate 74 Mackinaw Dells rest areas. | — | Executed | Laser Electric, Inc. $279,781 · | ||
| Apr 23, 2021 | 68G23 | TazewellDistrict 4 | Installation of overhead light poles, luminaires, flashing beacons, signs, pavement markings, rumble strips on IL Route 9 in Woodford County. | — | Executed | Laser Electric, Inc. $122,483 · | ||
| Apr 23, 2021 | 68G24 | VariousDistrict 4 | Electrical maintenance contract (maintenance and repair 04 traffic signals, overhead lighting, and ITS facilities). | — | Executed | Laser Electric, Inc. $649,929 · | ||
| Apr 23, 2021 | 70947 | VermilionDistrict 5 | 3P Policy (Standard Overlay) Resurfacing from S OF TILTON TO S OF CATLIN. | — | Executed | Open Road Paving Company LLC $1,396,862 · | ||
| Apr 23, 2021 | 70990 | DeWittDistrict 5 | 3P Resurfacing Standard overlay, ADA improvements from Logan Co. line to Van Buren St. in Clinton. Project length 9.48 miles. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $4,310,314 · | ||
| Apr 23, 2021 | 70C16 | DeWittDistrict 5 | 3P Resurfacing Standard overlay from Logan Co. line to 0.3 miles W. of US 51 at Clinton. Project length 9.91 miles. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $4,197,068 · | ||
| Apr 23, 2021 | 70D99 | ChampaignDistrict 5 | 5.3 miles of micro-surfacing joint repair of center line on us 45, from Curtis Rd in savoy to N of Tolono. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $279,272 · | ||
| Apr 23, 2021 | 70E18 | McLeanDistrict 5 | Designed Overlay on Old Rte. 66 from Logan Co. line to Shirley for a net length of 9.57 miles. | — | Executed | Rowe Construction, a div of UCM, Inc. $5,233,531 · | ||
| Apr 23, 2021 | 70E49 | McLeanDistrict 5 | Interstate Bridge Preservation/ Bridge Deck Overlay at I-39/US 51 Over Mackinaw River North of Hudson. | — | Executed | Stark Excavating, Inc. $3,710,497 · | ||
| Apr 23, 2021 | 70E81 | VermilionDistrict 5 | 12.963 Miles of Smart Resurfacing from Ford County Line to IL Rte. 1 at Hoopeston. | — | Executed | Cross Construction, Inc. $3,925,502 · | ||
| Apr 23, 2021 | 70E83 | DeWittDistrict 5 | 5.601 Miles. SMART Resurfacing, ILL 54 to ILL 10 N of Weldon. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $1,982,180 · | ||
| Apr 23, 2021 | 70E92 | DouglasEdgarDistrict 5 | 12.579 Miles of Cape Seal Operations from ILL 130 South to ILL 49. | — | Executed | Beniach Construction Co., Inc. $933,139 · | ||
| Apr 23, 2021 | 70F02 | DeWittPiattDistrict 5 | Bridge beam replacement and bridge repair at SN 074-0076 and 020-0045. | — | Executed | White Construction LLC $880,524 · | ||
| Apr 23, 2021 | 70F04 | DeWittDistrict 5 | 5.179 miles of micro surfacing joint repair from Mclean/Dewitt co line to the Dewitt/Piatt Co. line. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $353,199 · | ||
| Apr 23, 2021 | 70F05 | McLeanDistrict 5 | Class a special patching on nearly 2 miles of Eb/Wb 1-74 near Carlock. | — | Executed | Kinney Contractors, Inc. $121,468 · | ||
| Apr 23, 2021 | 70F06 | McLeanDistrict 5 | .245 Miles of Partial Width Resurfacing Under Veterans Parkway and Under I-55B in Bloomington. | — | Executed | Rowe Construction, a div of UCM, Inc. $143,207 · | ||
| Apr 23, 2021 | 70F08 | DouglasDistrict 5 | 11.36 MI of patching along FAI 57 from S of Arcola to N of Tuscola. | — | Executed | Beniach Construction Co., Inc. $136,258 · | ||
| Apr 23, 2021 | 70F09 | ChampaignDistrict 5 | 0.253 miles, patching, at 1-74 North of Mahomet on ILL 47. | — | Executed | G. M. Sipes Construction, Inc. $145,616 · | ||
| Apr 23, 2021 | 70F10 | VermilionDistrict 5 | 3.072 Ml of patching on FAS 331 from US 150 to Homer/Catlin Rd. | — | Executed | G. M. Sipes Construction, Inc. $138,517 · | ||
| Apr 23, 2021 | 70F11 | VermilionDistrict 5 | 1.36 Mi of patching on FAI 74 from L Street in Tilton to E of IL 1 in Danville. | — | Executed | G. M. Sipes Construction, Inc. $358,400 · | ||
| Apr 23, 2021 | 70F12 | ChampaignDistrict 5 | 0.425 Miles, Longitudinal joint repair, Guardian Dr. to 1-74 Ramps in Urbana. | — | Executed | Cross Construction, Inc. $79,277 · | ||
| Apr 23, 2021 | 70F13 | ChampaignDistrict 5 | Partial width resurfacing 0.216 Mi on US 150, between Elm St to Main St; 0.089 Mi on IL US 150; 0.033 Mi on ILL 49, just N of US 150. | — | Executed | Scanlon Excavating & Concrete, Inc. $245,749 · | ||
| Apr 23, 2021 | 72L67 | SangamonDistrict 6 | Bridge deck repairs on I-55 over the Sangamon River (2.7 miles north of IL 54/ Sangamon Avenue); I-55 over IL 54 / Sangamon Avenue; I-55 over the IC Railroad (0.3 miles north of IL 54 / Sangamon Avenue). (SN 084-0014, 084-0015, 084-0016, 084-0017, 084-0018, 084-0019) | — | Executed | Freesen, a div of UCM, Inc. $3,848,623 · | ||
| Apr 23, 2021 | 72M53 | MacoupinDistrict 6 | Painting SN 059-0009 carrying IL 4 over Union Pacific Railroad, 0.9 miles north of Staunton. | — | Rejected | Eagle Painting & Maintenance Company, Inc. $216,315 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.