(50-7,8)SFY,CBL
- Let date
- Friday, April 23, 2021
- Contract
- 66L33 · job page
- District
- District 3
- County
- Lasalle
- Highway
- Limits
- This project consists of the installation of approximately 5.92 miles of high tension cable median barrier from 1.09 miles South of N 36th Rd to 0.88 miles South of N 42nd Rd in LaSalle County.
- Classification
- The installation of approximately 5
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $1,322,328 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… |
|---|---|---|---|---|---|---|
| 1 | X0500002 | HMA MOW STRIP | 13,892 | SQ YD | $41.65 | |
| 2 | 64401100 | HT CBL MEDIAN BARRIER | 31,256 | FOOT | $15.00 | |
| 3 | 64401300 | HT CBL MED BAR TERM | 10 | EACH | $4,400.00 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $79,000.00 | |
| 5 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $145,000.00 | |
| 6 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $2,500.00 | |
| 7 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $100.00 | |
| 8 | 72501100 | TERMINAL MARKER - PM | 10 | EACH | $1.00 | |
| 9 | 78200021 | HT CBL MED BAR REF | 394 | EACH | $4.00 |