CM21-5011
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Beniach Construction Co., Inc. Low bidder | $136,258 | ||
| 2 | Kinney Contractors, Inc. | $184,664 | +35.5% | |
| 3 | G. M. Sipes Construction, Inc. | $198,301 | +45.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Beniach Constru… | #2 Kinney Contract… | #3 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|
| 1 | X1700052 | CL A PATCH T2 12 SPL | 54 | SQ YD | $294.00 | $235.00 | $280.00 | |
| 2 | X1700056 | CL A PATCH T3 13 SPL | 20 | SQ YD | $296.00 | $238.00 | $285.00 | |
| 3 | X1700057 | CL A PATCH T4 13 SPL | 25 | SQ YD | $293.00 | $236.00 | $285.00 | |
| 4 | X1700079 | CL A PATCH T3 12 SPL | 32 | SQ YD | $287.00 | $233.00 | $280.00 | |
| 5 | X1700116 | CL A PATCH T1 12 SPL | 4 | SQ YD | $473.00 | $240.00 | $380.00 | |
| 6 | X2700001 | TEMP RUMBLE STRIPS SP | 16 | EACH | $1,252.00 | $1,400.00 | $1,200.00 | |
| 7 | X4420619 | CL A PATCH T1 14 SPL | 4 | SQ YD | $480.00 | $255.00 | $390.00 | |
| 8 | X4420621 | CL A PATCH T2 14 SPL | 46 | SQ YD | $305.00 | $250.00 | $290.00 | |
| 9 | 44213000 | PATCH REINFORCEMENT | 185 | SQ YD | $66.00 | $70.00 | $90.00 | |
| 10 | 44213200 | SAW CUTS | 680 | FOOT | $0.00 | $6.00 | $5.95 | |
| 11 | 44213204 | TIE BARS 3/4 | 338 | EACH | $10.50 | $16.00 | $10.00 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $7,000.00 | $16,000.00 | $9,000.00 | |
| 13 | 70100420 | TRAF CONT-PROT 701411 | 8 | EACH | $0.00 | $1,000.00 | $100.00 | |
| 14 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $33,000.00 | $67,000.00 | $91,000.00 | |
| 15 | 70103815 | TR CONT SURVEILLANCE | 4 | CAL DA | $0.00 | $10.00 | $0.0100 | |
| 16 | 70107025 | CHANGEABLE MESSAGE SN | 36 | CAL DA | $120.00 | $125.00 | $25.00 |