(11,12)RS-3
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $4,197,068 | ||
| 2 | P. H. Broughton & Sons, Inc. | $4,513,172 | +7.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 P. H. Broughton… |
|---|---|---|---|---|---|---|---|
| 1 | X4400196 | HMA SURF REM SPL | 7,980 | SQ YD | $10.93 | $10.17 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $9,975.00 | $10,181.85 | |
| 3 | Z0033700 | LONG JOINT SEALANT | 52,023 | FOOT | $2.45 | $2.26 | |
| 4 | Z0070100 | SURV MONUMENT COV ASY | 15 | EACH | $1,050.00 | $1,071.77 | |
| 5 | 20400800 | FURNISHED EXCAVATION | 270 | CU YD | $99.02 | $80.41 | |
| 6 | 25000210 | SEEDING CL 2A | 0.5 | ACRE | $4,147.50 | $1,007.46 | |
| 7 | 25000400 | NITROGEN FERT NUTR | 45 | POUND | $1.21 | $2.14 | |
| 8 | 25000500 | PHOSPHORUS FERT NUTR | 45 | POUND | $1.21 | $2.14 | |
| 9 | 25000600 | POTASSIUM FERT NUTR | 45 | POUND | $1.21 | $2.14 | |
| 10 | 25100115 | MULCH METHOD 2 | 0.5 | ACRE | $2,992.50 | $1,071.78 | |
| 11 | 25100630 | EROSION CONTR BLANKET | 2,086 | SQ YD | $1.52 | $1.61 | |
| 12 | 28000250 | TEMP EROS CONTR SEED | 84 | POUND | $6.82 | $6.74 | |
| 13 | 28000400 | PERIMETER EROS BAR | 559 | FOOT | $7.42 | $6.97 | |
| 14 | 28000500 | INLET & PIPE PROTECT | 2 | EACH | $804.82 | $375.12 | |
| 15 | 40600290 | BIT MATLS TACK CT | 103,446 | POUND | $1.45 | $0.5900 | |
| 16 | 40600990 | TEMPORARY RAMP | 337 | SQ YD | $8.37 | $27.01 | |
| 17 | 40602965 | HMA BC IL-9.5FG N50 | 10,728 | TON | $102.05 | $109.55 | |
| 18 | 40604050 | HMA SC IL-9.5 C N50 | 12,816 | TON | $95.71 | $110.12 | |
| 19 | 40800029 | BIT MATLS TACK CT | 2,103 | POUND | $2.57 | $0.5500 | |
| 20 | 40800050 | INCIDENTAL HMA SURF | 393 | TON | $234.36 | $309.09 | |
| 21 | 44000159 | HMA SURF REM 2 1/2 | 4,093 | SQ YD | $3.14 | $3.17 | |
| 22 | 44000160 | HMA SURF REM 2 3/4 | 145,855 | SQ YD | $3.14 | $3.17 | |
| 23 | 44201863 | CL D PATCH T2 18 | 921 | SQ YD | $256.39 | $249.00 | |
| 24 | 44201867 | CL D PATCH T3 18 | 565 | SQ YD | $256.39 | $249.00 | |
| 25 | 44201869 | CL D PATCH T4 18 | 52 | SQ YD | $255.34 | $247.93 | |
| 26 | 48101200 | AGGREGATE SHLDS B | 4,026 | TON | $26.78 | $27.33 | |
| 27 | 63000001 | SPBGR TY A 6FT POSTS | 812.5 | FOOT | $25.20 | $31.08 | |
| 28 | 63000053 | WPGR ATT CLVRT CASE 4 | 50 | FOOT | $199.50 | $128.61 | |
| 29 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $2,835.00 | $4,179.92 | |
| 30 | 63100167 | TR BAR TRM T1 SPL TAN | 12 | EACH | $2,625.00 | $3,429.68 | |
| 31 | 63200310 | GUARDRAIL REMOV | 1,685 | FOOT | $9.45 | $5.89 | |
| 32 | 67000500 | ENGR FIELD OFFICE B | 6 | CAL MO | $1,523.20 | $3,311.06 | |
| 33 | 67100100 | MOBILIZATION | 1 | L SUM | $112,062.49 | $110,535.82 | |
| 34 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $54,600.00 | $55,732.26 | |
| 35 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $27,992.44 | $27,223.06 | |
| 36 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $3,715.90 | $5,901.40 | |
| 37 | 70300100 | SHORT TERM PAVT MKING | 20,814 | FOOT | $1.11 | $0.6400 | |
| 38 | 70300150 | SHRT TRM PAVT MK REM | 6,938 | SQ FT | $0.0100 | $0.9900 | |
| 39 | 70300220 | TEMP PVT MK LINE 4 | 118,419 | FOOT | $0.0100 | $0.5900 | |
| 40 | 72501000 | TERMINAL MARKER - DA | 12 | EACH | $31.50 | $53.59 | |
| 41 | 78001110 | PAINT PVT MK LINE 4 | 119,391 | FOOT | $0.1300 | $0.1300 | |
| 42 | 78100100 | RAISED REFL PAVT MKR | 650 | EACH | $35.46 | $36.19 | |
| 43 | 78200005 | GRDRAIL REF TYPE A | 34 | EACH | $10.50 | $10.72 | |
| 44 | 78300200 | RAISED REF PVT MK REM | 650 | EACH | $17.31 | $14.18 | |
| 45 | 78300202 | PAVMT MRKG REM WTR BL | 39,473 | SQ FT | $0.0100 | $1.29 |