15-00063-00-RS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | A Lamp Concrete Contractors, Inc. Low bidder | $1,304,037 | ||
| 2 | Plote Construction, Inc. | $1,371,347 | +5.2% | |
| 3 | Arrow Road Construction Co. | $1,384,123 | +6.1% | |
| 4 | R. W. Dunteman Company | $1,461,926 | +12.1% | |
| 5 | Brothers Asphalt Paving, Inc. | $1,498,715 | +14.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 A Lamp Concrete… | #2 Plote Construct… | #3 Arrow Road Cons… | #4 R. W. Dunteman … | #5 Brothers Asphal… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $12,800.00 | $15,500.00 | $14,000.00 | $14,000.00 | $14,980.00 | |
| 2 | X0326806 | WASHOUT BASIN | 1 | L SUM | $500.00 | $500.00 | $500.00 | $400.00 | $1,337.50 | |
| 3 | X4021000 | TEMP ACCESS- PRIV ENT | 5 | EACH | $50.00 | $100.00 | $84.00 | $150.26 | $30.00 | |
| 4 | X4240430 | PC CONC SIDEWALK 5 SP | 12,800 | SQ FT | $6.35 | $7.00 | $6.50 | $6.25 | $6.58 | |
| 5 | X4400501 | COMB C&G REMOV REPL < = 10FT | 500 | FOOT | $33.00 | $40.00 | $36.50 | $34.00 | $38.68 | |
| 6 | X6030310 | FR & LIDS ADJUST SPL | 69 | EACH | $700.00 | $650.00 | $600.00 | $600.00 | $695.50 | |
| 7 | Z0004562 | COMB C C&G REM & REPL | 5,250 | FOOT | $23.50 | $34.00 | $30.00 | $30.00 | $30.06 | |
| 8 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $19.50 | $10.00 | $10.00 | $10.00 | $19.26 | |
| 9 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 10 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 11 | 20201200 | REM & DISP UNS MATL | 152 | CU YD | $38.00 | $35.00 | $10.00 | $74.92 | $55.00 | |
| 12 | 21101615 | TOPSOIL F & P 4 | 187 | SQ YD | $7.50 | $8.00 | $9.90 | $9.90 | $7.46 | |
| 13 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $3,160.00 | $3,750.00 | $3,960.00 | $3,960.00 | $3,156.50 | |
| 14 | 25000400 | NITROGEN FERT NUTR | 17 | POUND | $4.30 | $5.00 | $2.00 | $2.00 | $4.28 | |
| 15 | 25000600 | POTASSIUM FERT NUTR | 17 | POUND | $4.30 | $5.00 | $2.00 | $2.00 | $4.28 | |
| 16 | 25100630 | EROSION CONTR BLANKET | 867 | SQ YD | $3.75 | $2.75 | $1.10 | $1.10 | $3.75 | |
| 17 | 25200110 | SODDING SALT TOLERANT | 187 | SQ YD | $19.50 | $10.00 | $23.70 | $23.70 | $19.26 | |
| 18 | 25200200 | SUPPLE WATERING | 10 | UNIT | $27.00 | $50.00 | $40.00 | $40.00 | $26.75 | |
| 19 | 40600290 | BIT MATLS TACK CT | 32,015 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.4900 | $0.1000 | |
| 20 | 40600400 | MIX CR JTS FLANGEWYS | 50 | TON | $225.00 | $50.00 | $85.00 | $250.00 | $300.00 | |
| 21 | 40600982 | HMA SURF REM BUTT JT | 420 | SQ YD | $10.00 | $20.00 | $4.70 | $1.01 | $5.00 | |
| 22 | 40603200 | P HMA BC IL-4.75 N50 | 2,609 | TON | $94.00 | $93.00 | $96.10 | $89.29 | $100.00 | |
| 23 | 40604060 | HMA SC IL-9.5 D N50 | 5,312 | TON | $72.00 | $71.00 | $76.70 | $74.12 | $81.25 | |
| 24 | 42300200 | PCC DRIVEWAY PAVT 6 | 240 | SQ YD | $60.00 | $70.00 | $60.00 | $66.00 | $41.73 | |
| 25 | 42400800 | DETECTABLE WARNINGS | 1,090 | SQ FT | $25.00 | $30.00 | $30.00 | $30.00 | $29.96 | |
| 26 | 44000160 | HMA SURF REM 2 3/4 | 47,424 | SQ YD | $2.08 | $3.00 | $2.70 | $4.07 | $2.75 | |
| 27 | 44000200 | DRIVE PAVEMENT REM | 240 | SQ YD | $10.00 | $10.00 | $7.00 | $12.89 | $13.91 | |
| 28 | 44000600 | SIDEWALK REM | 12,800 | SQ FT | $1.00 | $1.50 | $1.25 | $1.65 | $1.97 | |
| 29 | 44201761 | CL D PATCH T1 10 | 205 | SQ YD | $35.00 | $34.00 | $25.00 | $35.00 | $100.00 | |
| 30 | 44201765 | CL D PATCH T2 10 | 240 | SQ YD | $35.00 | $33.00 | $25.00 | $35.00 | $100.00 | |
| 31 | 44201769 | CL D PATCH T3 10 | 305 | SQ YD | $35.00 | $32.00 | $25.00 | $35.00 | $80.00 | |
| 32 | 44201771 | CL D PATCH T4 10 | 340 | SQ YD | $35.00 | $31.00 | $25.00 | $35.00 | $80.00 | |
| 33 | 60406100 | FR & LIDS T1 CL | 18 | EACH | $430.00 | $400.00 | $350.00 | $350.00 | $428.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $75,500.00 | $71,000.00 | $51,777.00 | $87,212.43 | $47,308.70 | |
| 35 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $19,704.00 | $1.00 | $5,549.77 | $1.00 | $16,585.00 | |
| 36 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $11,704.00 | $13,000.00 | $71,900.00 | $11,500.00 | $1.07 | |
| 37 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $11,704.00 | $1.00 | $1.00 | $1.00 | $5,350.00 | |
| 38 | 70300100 | SHORT TERM PAVT MKING | 9,263 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.25 | $1.50 | |
| 39 | 70300150 | SHRT TRM PAVT MK REM | 6,110 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $2.75 | $2.00 | |
| 40 | 78000100 | THPL PVT MK LTR & SYM | 471 | SQ FT | $4.30 | $4.00 | $4.00 | $4.00 | $4.28 | |
| 41 | 78000200 | THPL PVT MK LINE 4 | 28,324 | FOOT | $0.5500 | $0.5000 | $0.5000 | $0.5000 | $0.5300 | |
| 42 | 78000400 | THPL PVT MK LINE 6 | 562 | FOOT | $0.8000 | $0.7500 | $0.7500 | $0.7500 | $0.8000 | |
| 43 | 78000600 | THPL PVT MK LINE 12 | 1,418 | FOOT | $1.60 | $1.50 | $1.50 | $1.50 | $1.60 | |
| 44 | 78000650 | THPL PVT MK LINE 24 | 340 | FOOT | $4.30 | $4.00 | $4.00 | $4.00 | $4.28 | |
| 45 | 78008230 | POLYUREA PM T1 LN 6 | 190 | FOOT | $14.00 | $13.00 | $13.00 | $13.00 | $13.91 | |
| 46 | 78008270 | POLYUREA PM T1 LN 24 | 30 | FOOT | $56.00 | $52.00 | $52.00 | $52.00 | $55.64 | |
| 47 | 88600600 | DET LOOP REPL | 368 | FOOT | $19.25 | $16.00 | $15.70 | $15.70 | $19.15 |