2020-173-BR
- Let date
- Friday, April 23, 2021
- Contract
- 62M31 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- This is a bridge repair project that includes bridge deck overlay, partial depth approach reconstruction, joint reconstruction, concrete bridge deck repair, full depth bridge deck repair. Located: IL Route 7 at 86th Ave. within within the Village of Palos Park.
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lorig Construction Company Low bidder | $298,774 | ||
| 2 | MYS, Incorporated | $310,372 | +3.9% | |
| 3 | ERA-Valdivia Contractors, Inc. | $353,590 | +18.3% | |
| 4 | Areatha Construction Co., Inc. | $362,782 | +21.4% | |
| 5 | Rausch Infrastructure, LLC | $474,941 | +59.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lorig Construct… | #2 MYS, Incorporat… | #3 ERA-Valdivia Co… | #4 Areatha Constru… | #5 Rausch Infrastr… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X7011006 | TR CONT-PROT TEMP DET | 1 | EACH | $50,000.00 | $10,000.00 | $12,000.00 | $16,000.00 | $15,000.00 | |
| 2 | Z0001800 | APPROACH SL REP (PD) | 11 | SQ YD | $1,200.00 | $700.00 | $555.00 | $597.00 | $1,500.00 | |
| 3 | Z0006012 | BR DK LTX C OLY 2 1/4 | 293 | SQ YD | $165.00 | $140.00 | $165.00 | $290.00 | $179.00 | |
| 4 | Z0007122 | REM & RE EX RAILING | 194 | FOOT | $40.00 | $88.00 | $46.35 | $0.0100 | $70.00 | |
| 5 | Z0012130 | BR DECK SCAR 3/4 | 293 | SQ YD | $110.00 | $105.00 | $125.00 | $108.00 | $261.00 | |
| 6 | Z0016001 | DECK SLAB REP (FD-T1) | 0.5 | SQ YD | $3,000.00 | $1,000.00 | $3,500.00 | $1,950.00 | $14,500.00 | |
| 7 | Z0016002 | DECK SLAB REP (FD-T2) | 3 | SQ YD | $1,600.00 | $1,000.00 | $1,900.00 | $1,895.00 | $3,200.00 | |
| 8 | 40600290 | BIT MATLS TACK CT | 196 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 9 | 40600400 | MIX CR JTS FLANGEWYS | 0.7 | TON | $4,300.00 | $4,300.00 | $975.00 | $850.00 | $5,200.00 | |
| 10 | 40600982 | HMA SURF REM BUTT JT | 106 | SQ YD | $65.00 | $25.00 | $55.00 | $50.00 | $77.00 | |
| 11 | 40604062 | HMA SC IL-9.5 D N70 | 37 | TON | $420.00 | $470.00 | $685.00 | $597.00 | $505.00 | |
| 12 | 42001300 | PROTECTIVE COAT | 407 | SQ YD | $0.2500 | $4.00 | $6.00 | $4.00 | $21.00 | |
| 13 | 50102400 | CONC REM | 16.9 | CU YD | $1,200.00 | $1,200.00 | $2,250.00 | $1,600.00 | $2,100.00 | |
| 14 | 50157300 | PROTECTIVE SHIELD | 333 | SQ YD | $1.00 | $90.00 | $118.00 | $70.00 | $108.00 | |
| 15 | 50300255 | CONC SUP-STR | 16.9 | CU YD | $1,500.00 | $2,500.00 | $2,500.00 | $2,600.00 | $2,900.00 | |
| 16 | 50300260 | BR DECK GROOVING | 314 | SQ YD | $12.00 | $15.00 | $15.00 | $11.85 | $14.00 | |
| 17 | 50800205 | REINF BARS, EPOXY CTD | 1,470 | POUND | $4.00 | $6.00 | $6.00 | $3.85 | $5.00 | |
| 18 | 52000110 | PREF JT STRIP SEAL | 101 | FOOT | $240.00 | $215.00 | $215.00 | $325.00 | $263.00 | |
| 19 | 60608300 | COMB CC&G TM2.12 | 82 | FOOT | $60.00 | $40.00 | $45.00 | $99.00 | $92.00 | |
| 20 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1,350.00 | $1,200.00 | $2,000.00 | $2,000.00 | $5,500.00 | |
| 21 | 67100100 | MOBILIZATION | 1 | L SUM | $15,000.00 | $20,000.00 | $13,000.00 | $21,000.00 | $28,000.00 | |
| 22 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $30.00 | $35.00 | $31.00 | $25.00 | $36.00 | |
| 23 | 78000200 | THPL PVT MK LINE 4 | 577 | FOOT | $4.25 | $10.00 | $9.50 | $4.25 | $10.00 | |
| 24 | 78009004 | MOD URETH PM LINE 4 | 330 | FOOT | $7.25 | $16.00 | $15.00 | $7.15 | $16.00 | |
| 25 | 78100100 | RAISED REFL PAVT MKR | 4 | EACH | $250.00 | $1,100.00 | $1,025.00 | $875.00 | $1,168.00 |