| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Aug 3, 2018 | 78634 | AlexanderDistrict 9 | Surface preparation and application of bridge deck concrete sealer at SN 002-0022 carrying I-57 over the Mississippi River. | — | Executed | E. T. Simonds Construction Company $23,649 · | ||
| Aug 3, 2018 | 78649 | PopeDistrict 9 | Excavation of slope failures and adding riprap at multiple locations: 1) Two locatins at the IL 145/IL 146 intersection; 2) four locations on IL 146 from 1 mile to 3 miles west of Galconda. | — | Executed | Roadworks, LLC $36,232 · | ||
| Aug 3, 2018 | 78657 | GallatinDistrict 9 | 2.2 miles of patching on IL 1 from just south of IL 13 to SN 030-0020. | — | Executed | G. M. Sipes Construction, Inc. $128,569 · | ||
| Aug 3, 2018 | 78661 | JeffersonSalineDistrict 9 | Remove box culverts 041-7056 on IL 37 and 083-7059 on IL 142 and replace with elliptical pipes. | — | Executed | Haier Plumbing and Heating, Inc. $191,911 · | ||
| Aug 3, 2018 | 78663 | AlexanderDistrict 9 | Approach and connector pavement replacement on SN 002-0023 and 002-0024 on I-57 at the Cairo interchange over IL 3, CNIC Railroad Outer Road and Levee Road. | — | Executed | E. T. Simonds Construction Company $775,259 · | ||
| Aug 3, 2018 | 78665 | JohnsonDistrict 9 | Weed spraying along I-24 and I-57 in Johnson County. | — | Executed | The Daltons Inc. $54,842 · | ||
| Aug 3, 2018 | 78666 | VariousDistrict 9 | Surface preparation and applicatin of bridge deck concrete sealer at various locations in Perry, Jackson and Jefferson County. | — | Executed | All States Painting, Inc. $95,200 · | ||
| Aug 3, 2018 | 87642 | GrundyDistrict 3 | Rahabilitate the structure carrying Braceville Road over the Mazon river, 0.2 mile east of Gorman Road. | — | Executed | D. Construction, Inc. $984,309 · | ||
| Aug 3, 2018 | 87643 | GrundyDistrict 3 | Replace the bridge carrying Grand Ridge Road over Johnny Run, 0.65 mile east of Illinois Route 47. | — | Executed | Riber Construction, Inc. $793,264 · | ||
| Aug 3, 2018 | 89741 | MercerDistrict 4 | Extend six reinforced concrete box culverts, construction of one concrete box culvert, and the removal and replacement of ten corrugated metal pipe culverts on Joy Road between 160th Avenue and 130th Avenue. | — | Rejected | |||
| Aug 3, 2018 | 89746 | TazewellDistrict 4 | Construction of a shared-use path along West Cruger Road from Nofsinger Road to Main Street in the City of Washington. | — | Executed | Stark Excavating, Inc. $359,285 · | ||
| Aug 3, 2018 | 91556 | VermilionDistrict 5 | Sidewalk Construction along Webster Street from Northview Drive to West Vermilion Street in the Village of Catlin. | — | Executed | Duce Construction Company $157,300 · | ||
| Aug 3, 2018 | 93679 | SangamonDistrict 6 | Construction of a 3-span, welded plate girder bridge to carry South Old Route 66 (Oak Street) over the Union Pacific Railroad and Elm Street, and the construction of a new roadway to connect Walnut Street to South Old Route 66, in the Village of Williamsville. | — | Executed | Halverson Construction Co., Inc. $7,094,815 · | ||
| Aug 3, 2018 | 93717 | LoganDistrict 6 | Full depth pavement reclamation cape seal and aggregate shoulders on CH 25 from US 136 to the west corporate limits of Atlanta. | — | Executed | Dunn Company $1,497,997 · | ||
| Aug 3, 2018 | 93718 | LoganDistrict 6 | Replace the bridge carrying Delavan Road over Prairie Creek Ditch, 4 miles northwest of Emden. | — | Executed | Otto Baum Company, Inc. $295,457 · | ||
| Aug 3, 2018 | 99602 | WhiteDistrict 9 | Replace the bridge over unnamed creek, located one mile west of Epworth. | — | Executed | Dees, Inc. $171,534 · | ||
| Aug 3, 2018 | 99606 | HamiltonDistrict 9 | 20.5 miles of A-1 bituminous surface treatment on various routes in Hamilton County. | — | Rejected | Illini Asphalt Corporation $255,416 · | ||
| Sep 21, 2018 | 46475 | VariousDistrict 1 | Placing grooved pavement marking lines, letters, and symbols; removal of existing marking lines within the limits specified on individual work orders. | — | Executed | STF, LLC d/b/a Traffic Control Company $2,301,185 · | ||
| Sep 21, 2018 | 46500 | VariousDistrict 7 | Replacing reflectorized guardrail markers, terminal markers and placing linear delineator panels at various locations throughout District 7. | — | Executed | Endrizzi Contracting, Inc $71,610 · | ||
| Sep 21, 2018 | 60T43 | CookDistrict 1 | Bridge deck replacement and approach slabs of the 167th Street bridge over I-57. Other improvements include underpass lighting, guardrail installation, pavment marking and storm sewers. | — | Executed | D. Construction, Inc. $3,986,073 · | ||
| Sep 21, 2018 | 60V28 | WillDistrict 1 | Replace bridge 099-0170 carrying Illinois Route 102 over Rayn's Creek with a cast in place, 3 cell culvert, in Wesley Township. | — | Executed | Austin Tyler Construction, Inc. $1,055,878 · | ||
| Sep 21, 2018 | 61C21 | DuPageDistrict 1 | Construction of a multi-use path from Butterfield Road to South of Butterfield Road in the City of Elmhurst. | — | Executed | Lorig Construction Company $650,954 · | ||
| Sep 21, 2018 | 61E00 | WillDistrict 1 | Reconstruction of Moen Avenue from Mound Road to Larkin Avenue in the Village of Rockdale. | — | Executed | P. T. Ferro Construction Co. $4,999,401 · | ||
| Sep 21, 2018 | 61E88 | DuPageDistrict 1 | Construction of a shared use path adjacent to Montgomery Road from Waubonsie Creek Trail to Middlebury Drive in the City of Aurora. | — | Executed | D. Construction, Inc. $588,452 · | ||
| Sep 21, 2018 | 61E98 | DuPageDistrict 1 | Roadway resurfacing and sidewalk installation on Greenbrook Boulevard from County Farm Road to Lake Street. | — | Executed | J. A. Johnson Paving Company $885,885 · | ||
| Sep 21, 2018 | 61F02 | CookDistrict 1 | Traffic signal installation at 99th Street and Ridgeland Avenue in the Village of Chicago Ridge. | — | Executed | City Lights, LTD. $578,285 · | ||
| Sep 21, 2018 | 62A28 | CookDistrict 1 | Culvert replacement in the village of Calument. | — | Executed | D. Construction, Inc. $396,566 · | ||
| Sep 21, 2018 | 62B63 | CookDistrict 1 | Pavement widening, resurfacing, traffic signal modernization, and pedestrian ramp improvement for Plainfield Road at Willow Springs Road in Countryside. | — | Executed | Alliance Contractors, Inc. $947,875 · | ||
| Sep 21, 2018 | 62F52 | VariousDistrict 1 | Annual maintenance and operation of traffic signals, highway lighting, pump stations, surveillance, and other electrical systems in District 1. | — | Executed | Meade Inc. $26,979,205 · | ||
| Sep 21, 2018 | 62G45 | CookDistrict 1 | Building demolition located at 1680 Sauk Trail Road in Sauk Village. | — | Executed | Scanlon Excavating & Concrete, Inc. $85,529 · | ||
| Sep 21, 2018 | 62G81 | VariousDistrict 1 | Repair and installation of guardrail along various expressways and arterial highways throughout District One. | — | Executed | Kujo, Inc. $1,878,925 · | ||
| Sep 21, 2018 | 62G82 | VariousDistrict 1 | High tensin cable barrier repairs on various expressway medians district wide. | — | Executed | Fence Masters, Inc. $344,475 · | ||
| Sep 21, 2018 | 64J48 | Rock IslandDistrict 2 | Installation of scour countermeasures at SN 081-9905 carrying US 67 over the Mississippi River. | — | Executed | Byrne & Jones Marine LLC $2,498,590 · | ||
| Sep 21, 2018 | 64M77 | OgleDistrict 2 | Repair Bridge SN 071-0061 carrying Creston Road over FAI 39. | — | Executed | Sjostrom & Sons, Inc. $1,721,200 · | ||
| Sep 21, 2018 | 66J47 | VariousDistrict 3 | On-Call tree removal along state maintained routes, district wide. | — | Executed | Homer Tree Service, Inc. $40,500 · | ||
| Sep 21, 2018 | 68E47 | PeoriaDistrict 4 | Scour mitigation at SN 072-0034 carrying IL 90 over Prince Run. | — | Executed | Illinois Civil Contractors, Inc. $155,436 · | ||
| Sep 21, 2018 | 68E65 | TazewellDistrict 4 | Patching and joint repair on the on-ramps and off-ramps at the westbound I-74 Morton interchange. | — | Executed | G. M. Sipes Construction, Inc. $261,656 · | ||
| Sep 21, 2018 | 70D23 | DeWittDistrict 5 | Four spot locations of bridge painting on FAI 74 over US 150 and FAS 2495. | — | Executed | Venus Painting Co. $696,800 · | ||
| Sep 21, 2018 | 70D35 | DeWittMcLeanVermilionDistrict 5 | Guardrail improvements at 111 locations on various routes in Vermilion, McLean, and Dewitt Counties. | — | Executed | Lovewell Fencing, Inc. $1,446,915 · | ||
| Sep 21, 2018 | 72K68 | SangamonDistrict 6 | HMA surface removal and replacement on East Lke Shore Drive starting at just east of I-55 and proceeding east for 0.67 miles. | — | Executed | Truman L. Flatt & Sons Co., Inc. $161,777 · | ||
| Sep 21, 2018 | 72K70 | MasonDistrict 6 | Installing a cross road pipe culvert, pavement patching and ditch improvements on US 136 between CR 3200E and Cr 3300E. | — | Executed | G. M. Sipes Construction, Inc. $36,717 · | ||
| Sep 21, 2018 | 74870 | MaconDistrict 7 | Weed spraying along US 51 and I-72. | — | Executed | Endrizzi Contracting, Inc $90,538 · | ||
| Sep 21, 2018 | 74871 | EffinghamDistrict 7 | Tree removal in the ROW and median of I-57 from mile marker 164 to the Shelby County line. | — | Executed | J.H. Moore, Inc. $89,200 · | ||
| Sep 21, 2018 | 74872 | RichlandDistrict 7 | Construction of HMA safety shoulders, aggregate shoulder wedge and milled rumble strips on IL 250 beginning at Linn Street in Olney and extending southwest for 8.8 miles. | — | Executed | Howell Paving, Inc. $1,825,938 · | ||
| Sep 21, 2018 | 76K66 | St. ClairDistrict 8 | Repair bridge SN 082-0299 carrying IL 13 over the ICG Railroad, 2.5 miles south of Freeburg. | — | Executed | The Kilian Corporation $387,792 · | ||
| Sep 21, 2018 | 76L45 | St. ClairDistrict 8 | Structural repairs at the Bowman Pump Station on Exchange Avenue in East St. Louis. | — | Executed | Davinroy Mechanical Contractor, Inc. $124,142 · | ||
| Sep 21, 2018 | 76L55 | CalhounGreeneJerseyDistrict 8 | Removal and replacement of the Kampsville and Brussels Ferry loading docks. | — | Executed | St. Louis Bridge Construction Company $614,599 · | ||
| Sep 21, 2018 | 76L77 | CalhounDistrict 8 | Repair and maintenance of the electrical equipment on the Joe Page Bridge (SN 031-0001) in Hardin. | — | Executed | Wissehr Electric, Inc. $58,366 · | ||
| Sep 21, 2018 | 76L78 | VariousDistrict 8 | Repair and maintenance of electrical equipment at various pump stations throughout District 8. | — | Executed | Electrico, Inc. $65,548 · | ||
| Sep 21, 2018 | 76L79 | St. ClairDistrict 8 | Well treatment at various locations within District 8. | — | Rejected | Layne Christensen Company $689,885 · | ||
| Sep 21, 2018 | 76L92 | VariousDistrict 8 | Weed spraying along I-64, I-55, I-55/70, I-255, I-270, and IL 255. | — | Executed | Endrizzi Contracting, Inc $99,284 · | ||
| Sep 21, 2018 | 76L93 | VariousDistrict 8 | Weed spraying for Johnson Grass along I-64, I-55, I-55/70, I-255, I-270 and IL 255. | — | Executed | The Daltons Inc. $59,336 · | ||
| Sep 21, 2018 | 76L94 | VariousDistrict 8 | Tree removal and mitigation at various locations throughout District 8. | — | Executed | Stutz Excavating, Inc. $151,861 · | ||
| Sep 21, 2018 | 78615 | JohnsonDistrict 9 | Bridge repairs including joint reconstruction, overlay removal and replacement bearing removal and replacement, structural steel repairs and substructure repairs on SN 044-0035 carrying Tunnel Hill Road over I-24. | — | Executed | Sierra Bravo Contractors, LLC $297,796 · | ||
| Sep 21, 2018 | 78645 | JohnsonUnionWilliamsonDistrict 9 | Inserting culvert liners at 3 locations: 1) SN 100-7038, located 2 miles NW of I-57 near Neber Road on IL 148 in Williamson County; 2) SN 091-7089 located 0.3 miles north of exit 40 along I-57 in Johnson County; 3) SN 044-7073 located at MP 27.9 along I-57 SB in Union County. | — | Executed | Samron Midwest Contracting, Inc. $271,925 · | ||
| Sep 21, 2018 | 78679 | VariousDistrict 9 | Weed spraying on I-57 in Alexander, Pulaski and Union Counties. | — | Executed | Endrizzi Contracting, Inc $86,884 · | ||
| Sep 21, 2018 | 85644 | Rock IslandDistrict 2 | Resurface 38th Street from 7th Avenue to Blackhawk Road in the City of Rock Island. | — | Executed | Brandt Construction Co. $2,330,106 · | ||
| Sep 21, 2018 | 93711 | AdamsDistrict 6 | Construction of a multi-use trail from 18th Street to 24th Street along Cedar Creek in Quincy. | — | Rejected | Laverdiere Construction, Inc. $2,138,329 · | ||
| Sep 21, 2018 | 93720 | MorganDistrict 6 | Mill and surface East Michigan Avenue from South Main Street to Hardin Avenue in the City of Jacksonville. | — | Executed | K. E. Vas Company $657,302 · | ||
| Sep 21, 2018 | 97675 | MarionDistrict 8 | Replace the bridge carrying CH 5 over Jim's Creek, located 4.0 miles southeast of Patoka. | — | Executed | Sierra Bravo Contractors, LLC $790,284 · | ||
| Sep 21, 2018 | 97676 | BondDistrict 8 | Replace the bridge carrying TR 82 over Elm Point Branch, located 2.0 miles south of Panama. | — | Executed | Depew and Owen Builders, Inc. $638,688 · | ||
| Sep 21, 2018 | 99609 | MassacDistrict 9 | Resurface Grand Chain Road from CH 4 North Junction to CH 4 South Junction. | — | Executed | E. T. Simonds Construction Company $335,394 · | ||
| Nov 9, 2018 | 46472 | DuPageWillDistrict 1 | Replacing damaged and deteriorated overhead sign structures, componenets, and supports, described in the schedule of locations. | — | Executed | Aldridge Electric, Inc. $3,199,710 · | ||
| Nov 9, 2018 | 46473 | CookDistrict 1 | Repairing and replacing damaged or deteriorated overhead sign structures, components, and supports at locations described in the Schedule of Locations. | — | Executed | Kujo, Inc. $2,862,608 · | ||
| Nov 9, 2018 | 46496 | MadisonSt. ClairDistrict 8 | Repairing of replacing damaged or deteriorated overhead sign structures, components, and supports, repairing and moving signal heads and controller units. | — | Executed | T.M.F. Construction Company $623,730 · | ||
| Nov 9, 2018 | 46504 | VariousDistrict 7 | Repairing various widths of hot spray thermo, thermoplastic, modified urethane preformed plastic pavement marking lines, letters and sysmbols; grooving and the removal of existing pavement marking on a work order basis. | — | Executed | Varsity Striping & Construction Co. $876,636 · | ||
| Nov 9, 2018 | 46903 | WinnebagoDistrict 2 | 4.0 miles of HMA resurfacing to internal park roads, pavement widening, construction of a shared use path, lighting, removal and replacement of a 160' three span structure (SN 101-9974), box culvert installation, retaining wall construction, pavment marking and other miscellaneous in Rock Cut State Park in Winnebago County. | — | Executed | N-Trak Group, LLC and Sjostrom & Sons, Inc. Joint Venture $5,398,925 · | ||
| Nov 9, 2018 | 46914 | VermilionDistrict 5 | Remove debris that has accumulated at the piers of SN 092-9904 carrying Skyline Drive over the Vermilion River in the Kickapoo State Recreation Area. | — | Executed | Kovilic Construction Company, Inc. $125,000 · | ||
| Nov 9, 2018 | 60R79 | LakeDistrict 1 | Bridge deck overlay and bridge joint repairs at two structures carrying US 12 over Nippersink Lake Channel and over Pistkee Lake Channel. | — | Executed | Lorig Construction Company $2,241,247 · | ||
| Nov 9, 2018 | 60T13 | McHenryDistrict 1 | Channelization and traffic signal installation at the intersection of IL Route 173 and Wilmot Road. | — | Executed | Campanella and Sons, Inc. $1,983,425 · | ||
| Nov 9, 2018 | 60X79 | CookDistrict 1 | Widening, realignment, and reconstruction of eastbound I-290 ramp to I-90/94 northbound of the Jane Byrne Interchange, includes construction of five concrete retaining walls, drainage work and ITS in the City of Chicago. | — | Executed | James McHugh Construction Co. $33,852,455 · | ||
| Nov 9, 2018 | 60X93 | CookDistrict 1 | Reconstruction of five major system center ramps of Jane Byrne Interchange, some are on structures with retaining walls, ITS and signing, in the City of Chicago. | — | Executed | James McHugh Construction Co. $63,047,568 · | ||
| Nov 9, 2018 | 61E06 | DuPageDistrict 1 | Intersection improvement with signal timing progression and resurfacing on FAU Route 1504 (55th Street) from Dunham Road to Clerendon Hills Road. | — | Executed | R. W. Dunteman Company $8,525,282 · | ||
| Nov 9, 2018 | 61E67 | KaneDistrict 1 | Reconstruct the intersection of Main Street and Deerpath Road in the City of Batavia. | — | Executed | R. W. Dunteman Company $1,716,769 · | ||
| Nov 9, 2018 | 61E99 | KaneDistrict 1 | Traffic signal improvement on Randall Road from Silver Glen Road to County Line Road. | — | Executed | Thorne Electric, Inc. $4,681,132 · | ||
| Nov 9, 2018 | 61F03 | CookDistrict 1 | Sidewalk construction on 26th Street from Harlem Avenue to Riverside Drive; Riverside Drive from Maple Avenue to 27th Street; and Riverside Drive from 26th Street to Home Avenue in the City of Berwyn. | — | Rejected | Davis Concrete Construction Co. $181,996 · | ||
| Nov 9, 2018 | 61F04 | KaneDistrict 1 | construct a portion of Long Meadow Parkway on a new alignment, widen and reconstruct IL 25, including the intersection with Bolz Road. Located near the intersection of IL 25 and Bolz Road in the Village of Carpentersville. | — | Executed | Plote Construction, Inc. $5,591,043 · | ||
| Nov 9, 2018 | 61F05 | DuPageDistrict 1 | Install conduit, handholes and fiber optic interconnect cable to connect existing traffic signal controllers to the existing DuPage County Central System Network, located at various locations in DuPage County. | — | Executed | Thorne Electric, Inc. $3,355,558 · | ||
| Nov 9, 2018 | 61F07 | CookDistrict 1 | Resurfacing Kirchoff Road from Hicks Road to New Wilke Road in the City of Rolling Meadows. | — | Executed | Arrow Road Construction Co. $2,073,879 · | ||
| Nov 9, 2018 | 61F11 | KaneDistrict 1 | Resurfcing Aucutt Road from Orchard Road to IL Route 31 in the Village of Montgomery. | — | Executed | D. Construction, Inc. $522,896 · | ||
| Nov 9, 2018 | 61F14 | CookDistrict 1 | Resurfacing and ADA sidewalk improvements on Smith Street from Palatine Road to Dundee Road in the Village of Palatine. | — | Executed | Arrow Road Construction Co. $1,357,145 · | ||
| Nov 9, 2018 | 61F16 | CookDistrict 1 | Roadway reconstruction on FAU Route 1076 (Locust Road) from Lake Avenue to Wilmette Avenue in the Village of Wilmette. | — | Executed | A Lamp Concrete Contractors, Inc. $4,089,411 · | ||
| Nov 9, 2018 | 61F19 | WillDistrict 1 | Reconstruction and resurfacing on Sioux Drive and Dove Drive from Sunset Drive to West Eames Street and from Navajo Drive to Sunsewt Drive in the Village of Channahon. | — | Executed | P. T. Ferro Construction Co. $1,607,993 · | ||
| Nov 9, 2018 | 62A36 | CookDistrict 1 | Intersection improvement, drainage, traffic modernization, shared-use path and watermain relocation on IL 68 in the Villages of Barrington and Inverness. | — | Executed | Martam Construction Incorporated $2,526,633 · | ||
| Nov 9, 2018 | 62B31 | KaneDistrict 1 | Removal and replacement of existing box culverts over Harmony Creek and over Eakin Creek West. This project includes new culverts, pavement markings, signage, and new guardrail. | — | Executed | Rausch Infrastructure LLC_DO NOT USE $2,373,225 · | ||
| Nov 9, 2018 | 62C71 | CookDistrict 1 | Resurfacing on IL 7/US 6 (Wolf Road from just north of Southwest Highway to approximately 75 ft north of 151 Street in the Village of Orland Park. | — | Executed | D. Construction, Inc. $1,200,451 · | ||
| Nov 9, 2018 | 62D35 | LakeDistrict 1 | Drainage improvements along IL 59 and IL 22 in the village of North Barrington. Includes storm sewer, culvert lining and partial culvert barrel replacement. | — | Executed | Martam Construction Incorporated $889,433 · | ||
| Nov 9, 2018 | 62D43 | KaneKendallDistrict 1 | Bridge repair and overlay at IL 31 over BNSF railroad structure. Work includes deck scarification, concrete joint repair and construction, structural repair of concrete and approach slab replacement. | — | Executed | D. Construction, Inc. $2,429,071 · | ||
| Nov 9, 2018 | 62F16 | KaneDistrict 1 | Intersection reconstruction with installation of a roundabout at IL 47 and Plato Road. | — | Executed | Curran Contracting Company $3,377,730 · | ||
| Nov 9, 2018 | 62F57 | DuPageDistrict 1 | 4.5 miles of resurfacing (3P) and pedestrian ramps on IL 64 from Gary Avenue to IL 53. | — | Executed | R. W. Dunteman Company $6,955,644 · | ||
| Nov 9, 2018 | 62G32 | CookDistrict 1 | Bridge repair that includes structural steel repair to the structure carrying 79th Street over the CSX Railroad in the Village of Bridgeview. | — | Executed | Sumit Construction Co., Inc. $103,465 · | ||
| Nov 9, 2018 | 62G84 | CookDistrict 1 | Cleaning and painting designated steel surfaces of SN 016-0669 carrying Addison Street over I-90/94 in the City of Chicago. | — | Executed | Capital Industrial Services $899,933 · | ||
| Nov 9, 2018 | 62G89 | CookDistrict 1 | Cleaning and painting 2 structures on I-90/94 in Chicago: 1) SN 016-0204 - eastbound ramp to Ohio; 2) SN 016-2551 - reversible to Ohio. | — | Executed | Capital Industrial Services $733,300 · | ||
| Nov 9, 2018 | 62G91 | WillDistrict 1 | Resurfacing on Blodgett Road from Kelly Road to 1.8 miles east of Kelly Road in Wilmington Township. | — | Executed | Iroquois Paving Corporation $389,562 · | ||
| Nov 9, 2018 | 64B87 | WinnebagoDistrict 2 | Interchange reconstruction and bridge replacment on US 20 from Simpson Road to Rock River and IL2, south of Southrock Drive to south of US 20 Interchange. | — | Executed | William Charles Construction Company, LLC $24,199,990 · | ||
| Nov 9, 2018 | 64M78 | HenryDistrict 2 | Deck repair, latex modified concrete overlay, expansion joint replacement, and bearing replacement for I-80 under US 6 in Colona. | — | Executed | Brandt Construction Co. $774,304 · | ||
| Nov 9, 2018 | 64M95 | Rock IslandDistrict 2 | Washing two bridges over the Mississippi River (SN 081-001 and SN 081-0106). | — | Executed | Interstate Maintenance, Incorporated $190,800 · | ||
| Nov 9, 2018 | 64M96 | CarrollRock IslandWhitesideDistrict 2 | Washing three bridges over the Mississippi River (SN 008-0052, 081-9905 and 098-6003). | — | Executed | Interstate Maintenance, Incorporated $120,650 · | ||
| Nov 9, 2018 | 64M97 | HenryWhitesideDistrict 2 | Washing six bridges over the Rock River. | — | Executed | All States Painting, Inc. $83,710 · | ||
| Nov 9, 2018 | 64M98 | HenryRock IslandDistrict 2 | Washing five bridges over the Rock River at various locations. | — | Executed | All States Painting, Inc. $73,560 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.