DIST 8 TREE MIT 2019-1
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stutz Excavating, Inc. Low bidder | $151,861 | ||
| 2 | Prado Construction | $192,350 | +26.7% | |
| 3 | Endrizzi Contracting, Inc | $197,116 | +29.8% | |
| 4 | Nettle Creek Nursery, Inc. | $308,800 | +103.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stutz Excavatin… | #2 Prado Construct… | #3 Endrizzi Contra… | #4 Nettle Creek Nu… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | A2002714 | T-CARYA OVATA 1-3/4 | 51 | EACH | $400.00 | $363.62 | $500.00 | $600.00 | |
| 2 | A2006914 | T-QUERCUS PALUS 1-3/4 | 80 | EACH | $400.00 | $370.14 | $450.00 | $600.00 | |
| 3 | A2007122 | T-QUERCUS RUBRA 3 | 53 | EACH | $525.00 | $424.10 | $700.00 | $860.00 | |
| 4 | 20100110 | TREE REMOV 6-15 | 1,172 | UNIT | $25.00 | $25.34 | $25.00 | $54.00 | |
| 5 | 20100210 | TREE REMOV OVER 15 | 1,538 | UNIT | $22.00 | $36.32 | $32.00 | $64.00 | |
| 6 | 67100100 | MOBILIZATION | 1 | L SUM | $8,500.00 | $36,158.64 | $20,000.00 | $22,900.00 |