13-00400-00-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sierra Bravo Contractors, LLC Low bidder | $790,284 | ||
| 2 | Depew and Owen Builders, Inc. | $858,488 | +8.6% | |
| 3 | Stutz Excavating, Inc. | $911,729 | +15.4% | |
| 4 | Keeley & Sons, Inc. | $1,126,184 | +42.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sierra Bravo Co… | #2 Depew and Owen … | #3 Stutz Excavatin… | #4 Keeley & Sons, … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $4,501.00 | $7,500.00 | $7,245.00 | $21,890.00 | |
| 2 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 3 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 4 | 20100500 | TREE REMOV ACRES | 1 | ACRE | $12,752.16 | $10,000.00 | $15,000.00 | $17,890.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 14,116 | CU YD | $5.25 | $7.00 | $7.75 | $13.90 | |
| 6 | 20201200 | REM & DISP UNS MATL | 104 | CU YD | $16.63 | $12.00 | $11.40 | $22.90 | |
| 7 | 20300100 | CHANNEL EXCAVATION | 220 | CU YD | $11.91 | $8.00 | $16.20 | $16.40 | |
| 8 | 20400800 | FURNISHED EXCAVATION | 4,806 | CU YD | $9.67 | $10.00 | $8.50 | $18.90 | |
| 9 | 20700110 | POROUS GRAN EMBANK | 213 | TON | $25.86 | $30.00 | $26.25 | $26.90 | |
| 10 | 20800150 | TRENCH BACKFILL | 181 | CU YD | $40.46 | $65.00 | $30.25 | $39.80 | |
| 11 | 25000200 | SEEDING CL 2 | 5 | ACRE | $925.00 | $925.00 | $970.00 | $1,344.26 | |
| 12 | 25000400 | NITROGEN FERT NUTR | 450 | POUND | $1.15 | $1.15 | $1.20 | $1.23 | |
| 13 | 25000500 | PHOSPHORUS FERT NUTR | 450 | POUND | $1.15 | $1.15 | $1.20 | $1.23 | |
| 14 | 25000600 | POTASSIUM FERT NUTR | 450 | POUND | $1.15 | $1.15 | $1.20 | $1.23 | |
| 15 | 25100115 | MULCH METHOD 2 | 5 | ACRE | $875.00 | $875.00 | $920.00 | $995.52 | |
| 16 | 28000250 | TEMP EROS CONTR SEED | 500 | POUND | $2.25 | $2.25 | $2.00 | $5.80 | |
| 17 | 28000305 | TEMP DITCH CHECKS | 1,410 | FOOT | $4.95 | $5.00 | $8.60 | $5.80 | |
| 18 | 28000400 | PERIMETER EROS BAR | 432 | FOOT | $5.25 | $5.25 | $4.00 | $6.41 | |
| 19 | 28000500 | INLET & PIPE PROTECT | 12 | EACH | $145.00 | $150.00 | $75.00 | $227.00 | |
| 20 | 28001100 | TEMP EROS CONTR BLANK | 2,086 | SQ YD | $1.45 | $4.00 | $1.50 | $1.64 | |
| 21 | 28100805 | STONE DUMP RIP CL A3 | 815 | TON | $35.88 | $37.00 | $46.25 | $39.90 | |
| 22 | 28100807 | STONE DUMP RIP CL A4 | 410 | TON | $36.18 | $37.00 | $46.00 | $38.90 | |
| 23 | 40200800 | AGG SURF CSE B | 4,071 | TON | $22.85 | $25.00 | $26.00 | $24.90 | |
| 24 | 40300200 | BIT MATLS PR CT | 12.6 | TON | $1,147.07 | $1,150.00 | $1,080.00 | $1,170.02 | |
| 25 | 40300400 | BIT MATLS C&S CT | 26.1 | TON | $670.06 | $675.00 | $815.00 | $683.47 | |
| 26 | 40300500 | COVER COAT AGG | 210 | TON | $54.04 | $55.00 | $36.75 | $55.13 | |
| 27 | 40300600 | SEAL COAT AGG | 105 | TON | $64.12 | $65.00 | $36.75 | $65.41 | |
| 28 | 50100100 | REM EXIST STRUCT | 1 | EACH | $12,169.85 | $7,500.00 | $7,000.00 | $38,980.00 | |
| 29 | 50105220 | PIPE CULVERT REMOV | 333 | FOOT | $8.00 | $3.00 | $13.00 | $9.85 | |
| 30 | 50300225 | CONC STRUCT | 30.6 | CU YD | $537.94 | $700.00 | $685.00 | $890.15 | |
| 31 | 50300280 | CONCRETE ENCASEMENT | 2.8 | CU YD | $249.00 | $700.00 | $1,090.00 | $2,780.00 | |
| 32 | 50400605 | P P CONC DK BM 33 DP | 1,948 | SQ FT | $71.69 | $82.00 | $90.00 | $92.70 | |
| 33 | 50800105 | REINFORCEMENT BARS | 4,340 | POUND | $1.66 | $1.50 | $1.25 | $1.95 | |
| 34 | 50900205 | STEEL RAILING TY S1 | 166 | FOOT | $107.60 | $98.00 | $113.00 | $98.43 | |
| 35 | 51201600 | FUR STL PILE HP12X53 | 167 | FOOT | $84.53 | $28.00 | $147.50 | $79.80 | |
| 36 | 51202305 | DRIVING PILES | 167 | FOOT | $1.00 | $1.00 | $1.00 | $0.0100 | |
| 37 | 51203600 | TEST PILE ST HP12X53 | 1 | EACH | $2,765.78 | $10,000.00 | $12,925.00 | $2,980.00 | |
| 38 | 51500100 | NAME PLATES | 1 | EACH | $414.02 | $350.00 | $425.00 | $795.00 | |
| 39 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $16,995.03 | $12,500.00 | $14,875.00 | $19,890.00 | |
| 40 | 54011208 | PCBC 12X8 | 42 | FOOT | $824.22 | $1,000.00 | $840.00 | $797.80 | |
| 41 | 542A1063 | P CUL CL A 2 18 | 192 | FOOT | $60.74 | $34.00 | $47.75 | $38.90 | |
| 42 | 542A1069 | P CUL CL A 2 24 | 157 | FOOT | $69.34 | $42.00 | $63.25 | $47.80 | |
| 43 | 542A1075 | P CUL CL A 2 30 | 72 | FOOT | $91.87 | $54.00 | $68.80 | $59.80 | |
| 44 | 542A1081 | P CUL CL A 2 36 | 80 | FOOT | $111.59 | $66.00 | $88.00 | $71.55 | |
| 45 | 542C0220 | P CUL CL C 1 15 | 180 | FOOT | $42.64 | $25.00 | $46.75 | $36.25 | |
| 46 | 542C0223 | P CUL CL C 1 18 | 60 | FOOT | $33.86 | $30.00 | $45.00 | $41.65 | |
| 47 | 59300100 | CONTR LOW-STRENG MATL | 199 | CU YD | $87.31 | $95.00 | $100.00 | $139.80 | |
| 48 | 63100075 | TRAF BAR TERM T5A | 2 | EACH | $1,450.00 | $1,025.00 | $1,525.00 | $1,224.00 | |
| 49 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,555.00 | $3,300.00 | $3,730.00 | $3,264.00 | |
| 50 | 66600105 | FUR ERECT ROW MARKERS | 40 | EACH | $95.00 | $275.00 | $200.00 | $484.50 | |
| 51 | 67100100 | MOBILIZATION | 1 | L SUM | $44,733.03 | $64,540.00 | $50,000.00 | $67,000.00 | |
| 52 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $40.00 | $40.00 | $42.00 | $40.80 |