16-00119-00-BT
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $359,285 | ||
| 2 | R. A. Cullinan and Son, a div of UCM, Inc. | $361,892 | +0.7% | |
| 3 | Otto Baum Company, Inc. | $372,390 | +3.6% | |
| 4 | C. & G. Concrete Construction Co., Inc. | $384,000 | +6.9% | |
| 5 | Illinois Civil Contractors, Inc. | $388,590 | +8.2% | |
| 6 | Laverdiere Construction, Inc. | $488,773 | +36.0% | |
| 7 | Lee Hood d/b/a Hood Demolition & Excavation | $489,541 | +36.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 R. A. Cullinan … | #3 Otto Baum Compa… | #4 C. & G. Concret… | #5 Illinois Civil … | #6 Laverdiere Cons… | #7 Lee Hood d/b/a … |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327979 | PAVMT MRKG REM GRIND | 61 | SQ FT | $6.00 | $6.83 | $7.57 | $10.00 | $15.84 | $10.00 | $12.29 | |
| 2 | X5427600 | REM & RELOC END SECT | 1 | EACH | $950.00 | $380.57 | $651.85 | $1,552.36 | $503.31 | $600.00 | $500.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $10,000.00 | $11,983.03 | $4,972.28 | $10,000.00 | $12,000.00 | $50,000.00 | $6,000.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,500.00 | $9,324.00 | $6,166.67 | $6,325.00 | $5,891.62 | $16,000.00 | $13,205.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 865 | CU YD | $43.25 | $59.54 | $61.83 | $35.00 | $20.00 | $46.00 | $16.00 | |
| 6 | 20800150 | TRENCH BACKFILL | 3 | CU YD | $35.00 | $43.67 | $18.79 | $30.00 | $44.23 | $100.00 | $60.00 | |
| 7 | 25000210 | SEEDING CL 2A | 1.25 | ACRE | $2,100.00 | $1,407.00 | $4,260.61 | $2,588.00 | $2,410.21 | $2,000.00 | $1,300.00 | |
| 8 | 25000400 | NITROGEN FERT NUTR | 114 | POUND | $1.50 | $3.41 | $1.12 | $2.30 | $2.14 | $3.00 | $2.00 | |
| 9 | 25000500 | PHOSPHORUS FERT NUTR | 114 | POUND | $1.50 | $3.41 | $1.12 | $2.30 | $2.14 | $3.00 | $2.00 | |
| 10 | 25000600 | POTASSIUM FERT NUTR | 114 | POUND | $1.50 | $3.41 | $1.12 | $2.30 | $2.14 | $3.00 | $2.00 | |
| 11 | 25100125 | MULCH METHOD 3 | 1.25 | ACRE | $1,500.00 | $1,365.00 | $4,260.61 | $5,405.00 | $5,034.66 | $1,800.00 | $2,500.00 | |
| 12 | 28000250 | TEMP EROS CONTR SEED | 375 | POUND | $1.65 | $1.84 | $2.80 | $2.30 | $8.17 | $5.20 | $1.50 | |
| 13 | 28000305 | TEMP DITCH CHECKS | 119 | FOOT | $13.50 | $9.87 | $16.82 | $17.25 | $9.39 | $15.00 | $15.00 | |
| 14 | 28000400 | PERIMETER EROS BAR | 2,364 | FOOT | $3.50 | $3.62 | $3.14 | $3.22 | $3.44 | $3.00 | $6.00 | |
| 15 | 28000500 | INLET & PIPE PROTECT | 41 | EACH | $60.00 | $131.25 | $141.72 | $200.00 | $171.61 | $150.00 | $19.51 | |
| 16 | 35101100 | AGG BASE CSE A 12 | 73 | SQ YD | $48.00 | $33.10 | $20.56 | $25.00 | $34.06 | $30.00 | $24.65 | |
| 17 | 35102000 | AGG BASE CSE B 8 | 18 | SQ YD | $45.00 | $33.34 | $22.67 | $12.00 | $26.12 | $20.00 | $22.22 | |
| 18 | 42000301 | PCC PVT 8 JOINTED | 73 | SQ YD | $102.00 | $74.48 | $106.14 | $100.00 | $74.89 | $112.00 | $105.00 | |
| 19 | 42300200 | PCC DRIVEWAY PAVT 6 | 78 | SQ YD | $61.25 | $66.27 | $63.85 | $75.00 | $63.13 | $70.00 | $80.00 | |
| 20 | 42400200 | PC CONC SIDEWALK 5 | 49,796.5 | SQ FT | $4.32 | $3.94 | $4.18 | $4.50 | $5.01 | $5.50 | $7.50 | |
| 21 | 42400800 | DETECTABLE WARNINGS | 46.4 | SQ FT | $23.00 | $25.29 | $29.83 | $25.00 | $25.61 | $70.00 | $28.00 | |
| 22 | 44000100 | PAVEMENT REM | 71 | SQ YD | $21.75 | $17.93 | $24.00 | $30.00 | $27.02 | $12.00 | $28.00 | |
| 23 | 44000500 | COMB CURB GUTTER REM | 144 | FOOT | $5.50 | $12.29 | $5.20 | $14.00 | $9.51 | $20.00 | $4.00 | |
| 24 | 44004000 | PAVED DITCH REMOVAL | 5 | FOOT | $47.00 | $30.24 | $104.67 | $200.00 | $67.43 | $22.00 | $10.00 | |
| 25 | 52200800 | SEG CONC BLOCK WALL | 76 | SQ FT | $72.00 | $73.50 | $78.48 | $49.00 | $60.27 | $66.00 | $56.00 | |
| 26 | 54248510 | CONCRETE COLLAR | 0.3 | CU YD | $4,900.00 | $2,101.67 | $1,137.13 | $1,200.00 | $3,733.87 | $5,100.00 | $5,000.00 | |
| 27 | 550A0070 | STORM SEW CL A 1 15 | 5 | FOOT | $150.00 | $154.39 | $153.77 | $400.00 | $114.73 | $190.00 | $100.00 | |
| 28 | 60255500 | MAN ADJUST | 15 | EACH | $550.00 | $692.72 | $362.05 | $1,266.00 | $464.90 | $1,250.00 | $200.00 | |
| 29 | 60600605 | CONC CURB TB | 51.5 | FOOT | $7.50 | $54.66 | $52.21 | $45.00 | $44.09 | $50.00 | $32.00 | |
| 30 | 60605000 | COMB CC&G TB6.24 | 140 | FOOT | $61.50 | $62.78 | $58.61 | $45.00 | $43.06 | $58.00 | $32.00 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $16,793.42 | $14,529.46 | $18,034.41 | $15,000.00 | $23,000.00 | $15,000.00 | $20,000.00 | |
| 32 | 72000100 | SIGN PANEL T1 | 21.8 | SQ FT | $27.50 | $28.35 | $30.27 | $26.00 | $28.92 | $35.00 | $55.04 | |
| 33 | 72400710 | RELOC SIGN PANEL T1 | 17 | SQ FT | $34.00 | $35.70 | $38.12 | $25.00 | $36.42 | $41.00 | $17.64 | |
| 34 | 72900100 | METAL POST TY A | 30 | FOOT | $21.00 | $22.73 | $24.27 | $24.00 | $23.19 | $30.00 | $10.00 | |
| 35 | 78005150 | EPOXY PVT MK LINE 12 | 217 | FOOT | $31.00 | $30.85 | $32.94 | $36.73 | $31.47 | $26.00 | $6.00 | |
| 36 | 78005180 | EPOXY PVT MK LINE 24 | 27 | FOOT | $52.50 | $52.50 | $56.06 | $62.50 | $53.56 | $60.00 | $12.00 |