(3BR)M-1
- Let date
- Friday, September 21, 2018
- Contract
- 64J48 · job page
- District
- District 2
- County
- Rock Island
- Highway
- Limits
- Installation of scour countermeasures at SN 081-9905 carrying US 67 over the Mississippi River.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Byrne & Jones Marine LLC Low bidder | $2,498,590 | ||
| 2 | Phoenix Corporation of the Quad Cities | $2,686,933 | +7.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Byrne & Jones M… | #2 Phoenix Corpora… |
|---|---|---|---|---|---|---|---|
| 1 | X0327990 | BATHYMETRIC SURVEYS | 1 | L SUM | $20,000.00 | $22,000.00 | |
| 2 | X1200210 | FILTER BAGS | 2,307 | CU YD | $245.00 | $269.00 | |
| 3 | X1400343 | GPS GRADE CONTROL SYS | 1 | L SUM | $85,000.00 | $60,000.00 | |
| 4 | 20300100 | CHANNEL EXCAVATION | 9,100 | CU YD | $51.00 | $60.00 | |
| 5 | 28100811 | STONE DUMP RIP CL A6 | 9,350 | TON | $68.00 | $63.00 | |
| 6 | 66900200 | NON SPL WASTE DISPOSL | 9,100 | CU YD | $57.00 | $38.00 | |
| 7 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $12,000.00 | $10,500.00 | |
| 8 | 66900527 | TCLP SOIL ANALYSIS | 25 | EACH | $203.00 | $180.00 | |
| 9 | 66900530 | SOIL DISPOSAL ANALY | 25 | EACH | $1,036.00 | $950.00 | |
| 10 | 66900550 | PCBS SOIL ANALYSIS | 25 | EACH | $114.00 | $95.00 | |
| 11 | 66900615 | METALS/PH SOIL ANALYS | 25 | EACH | $125.00 | $115.00 | |
| 12 | 66900640 | VOCS/SVOCS SOIL ANLYS | 25 | EACH | $412.00 | $350.00 | |
| 13 | 66900645 | PESTICIDE SOIL ANALY | 25 | EACH | $221.00 | $190.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $145,000.00 | $446,000.00 |