15-00066-03-BR
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $295,457 | ||
| 2 | County Contractors, Inc. | $313,687 | +6.2% | |
| 3 | Stark Excavating, Inc. | $328,483 | +11.2% | |
| 4 | Freesen, a div of UCM, Inc. | $350,299 | +18.6% | |
| 5 | Sangamo Construction Company | $399,019 | +35.1% | |
| 6 | Laverdiere Construction, Inc. | $413,705 | +40.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 County Contract… | #3 Stark Excavatin… | #4 Freesen, a div … | #5 Sangamo Constru… | #6 Laverdiere Cons… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0301852 | DEWATERING STRUCT N1 | 1 | EACH | $4,928.41 | $5,350.00 | $5,500.00 | $28,810.02 | $15,283.35 | $30,000.00 | |
| 2 | X0900064 | MEMBR WTRPR SYS B STR | 107 | SQ YD | $26.97 | $72.00 | $40.00 | $47.13 | $72.65 | $115.00 | |
| 3 | X2070302 | POROUS GRAN EMB SPEC | 600 | TON | $26.09 | $43.00 | $20.50 | $28.30 | $39.24 | $50.00 | |
| 4 | X2090210 | POROUS GRAN BACK SPEC | 40 | CU YD | $100.66 | $70.00 | $87.50 | $89.96 | $89.98 | $140.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 350 | CU YD | $28.45 | $19.00 | $33.00 | $21.23 | $34.85 | $20.00 | |
| 6 | 28100807 | STONE DUMP RIP CL A4 | 280 | TON | $68.09 | $64.00 | $79.75 | $68.00 | $74.27 | $75.00 | |
| 7 | 35101400 | AGG BASE CSE B | 174 | TON | $31.28 | $38.00 | $30.00 | $40.62 | $41.94 | $40.00 | |
| 8 | 48101200 | AGGREGATE SHLDS B | 133 | TON | $50.08 | $50.00 | $34.00 | $43.73 | $55.58 | $45.00 | |
| 9 | 50100100 | REM EXIST STRUCT | 1 | EACH | $29,592.58 | $6,000.00 | $20,000.00 | $12,683.16 | $25,849.77 | $30,000.00 | |
| 10 | 50800205 | REINF BARS, EPOXY CTD | 32,020 | POUND | $1.26 | $1.50 | $1.40 | $1.29 | $1.39 | $1.60 | |
| 11 | 50900205 | STEEL RAILING TY S1 | 63 | FOOT | $184.37 | $168.00 | $159.00 | $166.95 | $168.53 | $190.00 | |
| 12 | 51500100 | NAME PLATES | 1 | EACH | $592.15 | $650.00 | $550.00 | $617.51 | $447.24 | $500.00 | |
| 13 | 54003000 | CONC BOX CUL | 162.3 | CU YD | $687.41 | $790.00 | $900.00 | $972.73 | $1,067.72 | $975.00 | |
| 14 | 542D0223 | P CUL CL D 1 18 | 42 | FOOT | $37.06 | $50.00 | $43.00 | $42.35 | $39.76 | $65.00 | |
| 15 | 63100075 | TRAF BAR TERM T5A | 4 | EACH | $1,340.87 | $1,090.00 | $1,030.00 | $1,081.50 | $1,091.72 | $1,300.00 | |
| 16 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,966.75 | $2,840.00 | $2,685.00 | $2,819.25 | $2,845.90 | $3,200.00 | |
| 17 | 67100100 | MOBILIZATION | 1 | L SUM | $5,734.25 | $19,750.00 | $18,000.00 | $12,073.11 | $23,542.12 | $15,000.00 | |
| 18 | 70101830 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $4,424.89 | $2,990.00 | $3,000.00 | $3,902.71 | $5,301.55 | $7,000.00 | |
| 19 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $44.70 | $40.00 | $37.50 | $39.38 | $39.75 | $45.00 |