Bid tab 68E47

Let Sep 21, 2018 · District 4 · Peoria Sign up free

‹ Sep 2018 results

(102B-1)SCR

Let date
Friday, September 21, 2018
Contract
68E47 · job page
District
District 4
County
Peoria
Highway
Limits
Scour mitigation at SN 072-0034 carrying IL 90 over Prince Run.

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Illinois Civil Contractors, Inc. Low bidder $155,436
2 Lee Hood d/b/a Hood Demolition & Excavation $169,809 +9.2%
3 CSD Environmental Services, Inc. $191,140 +23.0%

Bid tab: unit prices 9 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Illinois Civil …#2 Lee Hood d/b/a …#3 CSD Environment…
1X0301852 DEWATERING STRUCT N11EACH $10,000.00 $24,000.00 $15,500.00
2Z0012754 STR REP CON DP = < 595.3SQ FT $320.00 $144.40 $500.00
320100110 TREE REMOV 6-15100UNIT $50.00 $89.00 $70.00
420300100 CHANNEL EXCAVATION183CU YD $40.00 $40.00 $75.00
528000305 TEMP DITCH CHECKS15FOOT $30.00 $78.00 $55.00
628100109 STONE RIPRAP CL A5635SQ YD $137.00 $138.60 $132.70
728200200 FILTER FABRIC635SQ YD $5.00 $2.75 $5.00
867100100 MOBILIZATION1L SUM $9,000.00 $16,000.00 $11,500.00
970100450 TRAF CONT-PROT 7012011L SUM $3,000.00 $8,900.00 $7,500.00