124CR-1;109CR-1
- Let date
- Friday, August 3, 2018
- Contract
- 78661 · job page
- District
- District 9
- County
- Saline, Jefferson
- Highway
- Limits
- Remove box culverts 041-7056 on IL 37 and 083-7059 on IL 142 and replace with elliptical pipes.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Haier Plumbing and Heating, Inc. Low bidder | $191,911 | ||
| 2 | E. T. Simonds Construction Company | $203,114 | +5.8% | |
| 3 | Sierra Bravo Contractors, LLC | $206,682 | +7.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Haier Plumbing … | #2 E. T. Simonds C… | #3 Sierra Bravo Co… |
|---|---|---|---|---|---|---|---|---|
| 1 | X1700069 | CL C PATCH T4 11.5 | 84 | SQ YD | $135.00 | $185.95 | $147.14 | |
| 2 | X1700070 | CL C PATCH T4 14.5 | 71 | SQ YD | $165.00 | $205.74 | $168.14 | |
| 3 | X7015005 | CHANGEABLE MESSAGE SN | 84 | CAL DA | $85.00 | $45.00 | $108.00 | |
| 4 | 20100110 | TREE REMOV 6-15 | 6 | UNIT | $35.00 | $50.00 | $80.96 | |
| 5 | 20200100 | EARTH EXCAVATION | 65 | CU YD | $6.00 | $18.38 | $31.24 | |
| 6 | 20400800 | FURNISHED EXCAVATION | 253 | CU YD | $12.50 | $16.24 | $41.49 | |
| 7 | 20700220 | POROUS GRAN EMBANK | 195 | CU YD | $30.00 | $75.94 | $102.85 | |
| 8 | 25000200 | SEEDING CL 2 | 0.2 | ACRE | $10,000.00 | $15,400.00 | $5,424.80 | |
| 9 | 25000400 | NITROGEN FERT NUTR | 18 | POUND | $1.50 | $1.27 | $1.28 | |
| 10 | 25000500 | PHOSPHORUS FERT NUTR | 18 | POUND | $1.50 | $1.27 | $1.28 | |
| 11 | 25000600 | POTASSIUM FERT NUTR | 18 | POUND | $1.50 | $1.27 | $1.28 | |
| 12 | 25000700 | AGR GROUND LIMESTONE | 0.4 | TON | $200.00 | $192.50 | $1,601.96 | |
| 13 | 25100630 | EROSION CONTR BLANKET | 968 | SQ YD | $1.00 | $1.93 | $3.29 | |
| 14 | 28100105 | STONE RIPRAP CL A3 | 248 | SQ YD | $32.00 | $30.72 | $16.58 | |
| 15 | 48101600 | AGGREGATE SHLDS B 8 | 55 | SQ YD | $30.00 | $53.51 | $34.70 | |
| 16 | 50100300 | REM EXIST STRUCT N1 | 2 | EACH | $8,030.00 | $7,533.08 | $7,630.16 | |
| 17 | 542A5503 | P CUL CL A 1 EQRS 48 | 128 | FOOT | $425.00 | $307.46 | $335.37 | |
| 18 | 54260315 | TRVRS PIPE GRT CON ES | 219 | FOOT | $45.00 | $75.38 | $54.80 | |
| 19 | 54263348 | CONC ES 542011 48 1:3 | 8 | EACH | $4,600.00 | $4,313.19 | $4,386.61 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $11,340.00 | $9,022.61 | $13,340.58 | |
| 21 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $3,870.00 | $10,028.03 | $3,654.28 | |
| 22 | 70101830 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $2,900.00 | $5,839.15 | $4,127.14 | |
| 23 | 78001110 | PAINT PVT MK LINE 4 | 181 | FOOT | $23.00 | $15.00 | $15.69 |