(111N-B)B-R
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Austin Tyler Construction, Inc. Low bidder | $1,055,878 | ||
| 2 | D. Construction, Inc. | $1,088,098 | +3.1% | |
| 3 | Dunnet Bay Construction Company | $1,228,074 | +16.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Austin Tyler Co… | #2 D. Construction… | #3 Dunnet Bay Cons… |
|---|---|---|---|---|---|---|---|---|
| 1 | K0013000 | P PL PRAIRI 2X4 DPPLG | 5 | UNIT | $450.00 | $646.80 | $588.00 | |
| 2 | X0325222 | WEED CONT BASAL TRTMT | 2.5 | GALLON | $900.00 | $657.80 | $598.00 | |
| 3 | X0326519 | STEEL RAILING REMOVAL | 45 | FOOT | $12.00 | $13.20 | $0.0100 | |
| 4 | X0326898 | CENTERLN RUM STRIP 16 | 300 | FOOT | $7.00 | $12.54 | $4.50 | |
| 5 | X0327979 | PAVMT MRKG REM GRIND | 377 | SQ FT | $1.25 | $2.20 | $1.50 | |
| 6 | X0900064 | MEMBR WTRPR SYS B STR | 235 | SQ YD | $45.00 | $50.00 | $42.00 | |
| 7 | X2503112 | MOWING SPL | 2,500 | SQ YD | $1.50 | $0.6800 | $0.6200 | |
| 8 | X5860110 | GRANULAR BACKFILL STR | 90 | CU YD | $90.00 | $45.00 | $62.00 | |
| 9 | X6061005 | CONC CURB TB SPL | 64 | FOOT | $70.00 | $30.00 | $53.50 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $13,000.00 | $16,000.00 | $8,250.00 | |
| 11 | X7015005 | CHANGEABLE MESSAGE SN | 115 | CAL DA | $35.00 | $50.00 | $30.00 | |
| 12 | X7800815 | HS THPL PM LN 4 | 380 | FOOT | $7.50 | $10.97 | $9.97 | |
| 13 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,000.00 | $12,500.00 | $10,000.00 | |
| 14 | Z0030850 | TEMP INFO SIGNING | 104 | SQ FT | $15.00 | $25.00 | $10.00 | |
| 15 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 17 | 20101000 | TEMPORARY FENCE | 300 | FOOT | $7.00 | $5.00 | $7.00 | |
| 18 | 20101200 | TREE ROOT PRUNING | 4 | EACH | $250.00 | $550.00 | $500.00 | |
| 19 | 20101700 | SUPPLE WATERING | 13 | UNIT | $60.00 | $55.00 | $50.00 | |
| 20 | 20200100 | EARTH EXCAVATION | 340 | CU YD | $45.00 | $30.00 | $40.00 | |
| 21 | 20201200 | REM & DISP UNS MATL | 134 | CU YD | $25.00 | $30.00 | $40.00 | |
| 22 | 20700220 | POROUS GRAN EMBANK | 206 | CU YD | $63.00 | $50.00 | $58.00 | |
| 23 | 21001000 | GEOTECH FAB F/GR STAB | 771 | SQ YD | $2.00 | $2.20 | $2.50 | |
| 24 | 21101505 | TOPSOIL EXC & PLAC | 200 | CU YD | $70.00 | $15.00 | $36.00 | |
| 25 | 25000310 | SEEDING CL 4 | 0.25 | ACRE | $3,200.00 | $1,777.60 | $1,616.00 | |
| 26 | 25000314 | SEEDING CL 4B | 0.05 | ACRE | $10,000.00 | $3,009.60 | $2,736.00 | |
| 27 | 25000775 | SELECT MOWING STAKES | 4 | EACH | $150.00 | $37.40 | $34.00 | |
| 28 | 25100630 | EROSION CONTR BLANKET | 730 | SQ YD | $1.50 | $0.8800 | $0.8000 | |
| 29 | 25100635 | HD EROS CONTR BLANKET | 590 | SQ YD | $2.00 | $1.76 | $1.60 | |
| 30 | 28000250 | TEMP EROS CONTR SEED | 25 | POUND | $10.00 | $3.30 | $3.00 | |
| 31 | 28000305 | TEMP DITCH CHECKS | 86 | FOOT | $15.00 | $11.11 | $10.10 | |
| 32 | 28000315 | AGG DITCH CHECKS | 11 | TON | $150.00 | $40.00 | $200.00 | |
| 33 | 28000400 | PERIMETER EROS BAR | 700 | FOOT | $3.50 | $2.53 | $2.30 | |
| 34 | 28001100 | TEMP EROS CONTR BLANK | 1,320 | SQ YD | $1.25 | $0.7700 | $0.7000 | |
| 35 | 28100109 | STONE RIPRAP CL A5 | 99 | SQ YD | $60.00 | $65.00 | $160.00 | |
| 36 | 28100705 | STONE DUMP RIP CL A3 | 15 | SQ YD | $20.00 | $50.00 | $110.00 | |
| 37 | 28200200 | FILTER FABRIC | 114 | SQ YD | $5.00 | $3.00 | $7.00 | |
| 38 | 30300001 | AGG SUBGRADE IMPROVE | 55 | CU YD | $54.00 | $50.00 | $60.00 | |
| 39 | 30300112 | AGG SUBGRADE IMPR 12 | 1,414 | SQ YD | $18.00 | $17.50 | $20.00 | |
| 40 | 40600635 | LEV BIND MM N70 | 34 | TON | $160.00 | $85.00 | $125.00 | |
| 41 | 40603340 | HMA SC "D" N70 | 67 | TON | $150.00 | $85.00 | $115.00 | |
| 42 | 40700100 | BIT MATLS TACK CT | 720 | POUND | $3.00 | $0.0100 | $0.0100 | |
| 43 | 40701886 | HMA PAVT FD 10 1/4 | 980 | SQ YD | $45.00 | $44.00 | $57.50 | |
| 44 | 44000100 | PAVEMENT REM | 822 | SQ YD | $18.00 | $12.50 | $14.00 | |
| 45 | 44004250 | PAVED SHLD REMOVAL | 171 | SQ YD | $18.00 | $10.00 | $12.00 | |
| 46 | 48101498 | AGGREGATE SHLDS B 4 | 258 | SQ YD | $23.00 | $7.00 | $12.00 | |
| 47 | 48101600 | AGGREGATE SHLDS B 8 | 371 | SQ YD | $20.00 | $13.50 | $20.00 | |
| 48 | 48203038 | HMA SHOULDERS 10 1/4 | 546 | SQ YD | $45.00 | $43.60 | $57.50 | |
| 49 | 50100100 | REM EXIST STRUCT | 1 | EACH | $20,000.00 | $25,000.00 | $215,100.00 | |
| 50 | 50104000 | BRIDGE RAIL REMOVAL | 45 | FOOT | $100.00 | $13.20 | $0.0100 | |
| 51 | 50200100 | STRUCTURE EXCAVATION | 934 | CU YD | $24.00 | $30.00 | $53.00 | |
| 52 | 50200450 | REM/DISP UNS MATL-STR | 76 | CU YD | $24.00 | $30.00 | $53.00 | |
| 53 | 50300300 | PROTECTIVE COAT | 43 | SQ YD | $4.00 | $3.00 | $10.00 | |
| 54 | 50800205 | REINF BARS, EPOXY CTD | 116,630 | POUND | $1.50 | $2.00 | $1.26 | |
| 55 | 50900200 | STEEL RAIL TYPE 2399 | 179 | FOOT | $175.00 | $191.00 | $173.64 | |
| 56 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $500.00 | $400.00 | |
| 57 | 54003000 | CONC BOX CUL | 425 | CU YD | $800.00 | $750.00 | $700.00 | |
| 58 | 54213447 | END SECTIONS 12 | 2 | EACH | $500.00 | $500.00 | $400.00 | |
| 59 | 58700300 | CONCRETE SEALER | 572 | SQ FT | $4.00 | $2.00 | $4.00 | |
| 60 | 59100100 | GEOCOMPOSITE WALL DR | 13 | SQ YD | $60.00 | $35.00 | $40.00 | |
| 61 | 60100060 | CONC HDWL FOR P DRAIN | 2 | EACH | $450.00 | $300.00 | $450.00 | |
| 62 | 60100945 | PIPE DRAINS 12 | 12 | FOOT | $100.00 | $45.00 | $110.00 | |
| 63 | 60108204 | PIPE UNDERDR T 2 4 | 20 | FOOT | $64.00 | $30.00 | $52.50 | |
| 64 | 60600605 | CONC CURB TB | 64 | FOOT | $70.00 | $35.00 | $53.50 | |
| 65 | 61000050 | CONC THRUST BLOCKS | 2 | EACH | $500.00 | $350.00 | $545.00 | |
| 66 | 61000115 | TY E INLET BOX 610001 | 2 | EACH | $2,500.00 | $3,500.00 | $4,400.00 | |
| 67 | 63000003 | SPBGR TY A 9FT POSTS | 225 | FOOT | $30.00 | $30.20 | $31.00 | |
| 68 | 63100087 | TRAF BAR TERM T6A | 4 | EACH | $3,100.00 | $3,410.00 | $3,100.00 | |
| 69 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $2,425.00 | $2,667.50 | $2,600.00 | |
| 70 | 63200310 | GUARDRAIL REMOV | 831 | FOOT | $5.00 | $5.28 | $4.80 | |
| 71 | 64200108 | SHOULDER RUM STRIP 8 | 614 | FOOT | $4.50 | $12.54 | $3.00 | |
| 72 | 66900200 | NON SPL WASTE DISPOSL | 530 | CU YD | $54.00 | $70.00 | $72.50 | |
| 73 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $4,600.00 | $9,625.00 | $4,200.00 | |
| 74 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,100.00 | $1,375.00 | $900.00 | |
| 75 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,000.00 | $3,000.00 | $2,400.00 | |
| 76 | 67100100 | MOBILIZATION | 1 | L SUM | $62,000.00 | $61,500.00 | $71,450.00 | |
| 77 | 70300100 | SHORT TERM PAVT MKING | 233 | FOOT | $2.00 | $2.00 | $2.00 | |
| 78 | 70300150 | SHRT TRM PAVT MK REM | 77 | SQ FT | $7.00 | $10.00 | $3.50 | |
| 79 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $35.00 | $38.50 | $35.00 | |
| 80 | 78000200 | THPL PVT MK LINE 4 | 1,754 | FOOT | $1.65 | $2.37 | $2.15 | |
| 81 | 78000650 | THPL PVT MK LINE 24 | 17 | FOOT | $15.00 | $14.74 | $13.40 | |
| 82 | 78100100 | RAISED REFL PAVT MKR | 8 | EACH | $300.00 | $600.60 | $546.00 | |
| 83 | 78200005 | GRDRAIL REF TYPE A | 20 | EACH | $12.00 | $13.20 | $12.00 |