16-00311-00-BT
- Let date
- Friday, September 21, 2018
- Contract
- 61E88 · job page
- District
- District 1
- County
- Dupage, Kane
- Highway
- Limits
- Construction of a shared use path adjacent to Montgomery Road from Waubonsie Creek Trail to Middlebury Drive in the City of Aurora.
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $588,452 | ||
| 2 | A Lamp Concrete Contractors, Inc. | $649,345 | +10.3% | |
| 3 | K-Five Construction Corporation | $657,058 | +11.7% | |
| 4 | Lorusso Cement Contractors, Inc. | $695,621 | +18.2% | |
| 5 | Landmark Contractors, Inc. | $716,189 | +21.7% | |
| 6 | Alliance Contractors, Inc. | $755,018 | +28.3% | |
| 7 | Copenhaver Construction, Inc. | $809,711 | +37.6% | |
| 8 | Construction Management Corp. of America | $833,603 | +41.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 A Lamp Concrete… | #3 K-Five Construc… | #4 Lorusso Cement … | #5 Landmark Contra… | #6 Alliance Contra… | #7 Copenhaver Cons… | #8 Construction Ma… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | A2000116 | T-ACERX FREM AB 2 | 1 | EACH | $550.00 | $575.00 | $501.00 | $605.00 | $550.00 | $350.00 | $700.00 | $500.00 | |
| 2 | A2004610 | T-GLEDIT TRI IN PER 2 | 2 | EACH | $495.00 | $520.00 | $451.00 | $605.00 | $550.00 | $350.00 | $700.00 | $450.00 | |
| 3 | A2007816 | T-TILIA AMER 2 | 2 | EACH | $522.50 | $520.00 | $476.00 | $605.00 | $550.00 | $350.00 | $700.00 | $475.00 | |
| 4 | XX006947 | HMA DRIVE REM & REP | 57 | SQ YD | $40.00 | $55.00 | $147.00 | $54.88 | $101.90 | $65.00 | $48.00 | $48.86 | |
| 5 | XX008824 | CATCH BASINS SPECIAL | 7 | EACH | $1,000.00 | $1,600.00 | $1,370.00 | $1,702.40 | $2,500.00 | $3,550.00 | $2,600.00 | $1,519.14 | |
| 6 | X0322917 | PRO SS CONN TO EX MAN | 9 | EACH | $1,100.00 | $750.00 | $1,300.00 | $594.72 | $800.00 | $750.00 | $1,200.00 | $530.56 | |
| 7 | X0326899 | SOLAR-POWER FB AS CMP | 2 | EACH | $10,862.50 | $16,200.00 | $11,600.00 | $15,900.00 | $11,520.00 | $11,520.00 | $13,000.00 | $11,520.00 | |
| 8 | X0327980 | PAVMT MRKG REM WTR BL | 430 | SQ FT | $5.50 | $5.00 | $5.05 | $5.50 | $5.00 | $5.00 | $6.00 | $5.00 | |
| 9 | X5427600 | REM & RELOC END SECT | 1 | EACH | $650.00 | $1,100.00 | $530.00 | $1,083.50 | $1,500.00 | $1,000.00 | $700.00 | $985.00 | |
| 10 | X8140115 | HANDHOLE TO BE ADJUST | 1 | EACH | $1,760.00 | $1,600.00 | $2,450.00 | $1,563.00 | $2,430.00 | $2,430.00 | $3,000.00 | $2,430.00 | |
| 11 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $9,000.00 | $6,150.00 | $13,750.00 | $7,500.00 | $9,585.00 | $20,000.00 | $12,500.00 | |
| 12 | 20100110 | TREE REMOV 6-15 | 12 | UNIT | $16.50 | $21.00 | $15.05 | $38.50 | $15.00 | $15.00 | $30.00 | $15.00 | |
| 13 | 20100210 | TREE REMOV OVER 15 | 72 | UNIT | $18.70 | $46.00 | $17.10 | $40.15 | $17.00 | $17.00 | $34.00 | $17.00 | |
| 14 | 20101100 | TREE TRUNK PROTECTION | 2 | EACH | $99.00 | $460.00 | $91.00 | $495.00 | $90.00 | $90.00 | $60.00 | $90.00 | |
| 15 | 20101200 | TREE ROOT PRUNING | 20 | EACH | $44.00 | $50.00 | $41.00 | $385.00 | $40.00 | $40.00 | $20.00 | $40.00 | |
| 16 | 20101300 | TREE PRUN 1-10 | 20 | EACH | $82.50 | $69.00 | $76.00 | $247.50 | $75.00 | $75.00 | $20.00 | $75.00 | |
| 17 | 20101350 | TREE PRUN OVER 10 | 1 | EACH | $38.50 | $173.00 | $36.00 | $385.00 | $35.00 | $35.00 | $30.00 | $35.00 | |
| 18 | 20200100 | EARTH EXCAVATION | 1,430 | CU YD | $20.00 | $35.00 | $47.00 | $28.45 | $63.00 | $20.00 | $28.00 | $48.48 | |
| 19 | 20201200 | REM & DISP UNS MATL | 433 | CU YD | $30.00 | $15.00 | $47.00 | $38.08 | $64.00 | $20.00 | $28.00 | $55.39 | |
| 20 | 20800150 | TRENCH BACKFILL | 14 | CU YD | $100.00 | $50.00 | $61.50 | $99.68 | $20.00 | $100.00 | $80.00 | $85.79 | |
| 21 | 21001000 | GEOTECH FAB F/GR STAB | 5,242 | SQ YD | $3.00 | $1.25 | $0.9500 | $2.80 | $1.60 | $1.00 | $1.50 | $2.00 | |
| 22 | 21101615 | TOPSOIL F & P 4 | 5,480 | SQ YD | $4.95 | $5.20 | $4.75 | $4.68 | $4.25 | $0.1000 | $7.00 | $4.50 | |
| 23 | 21301072 | EXPLOR TRENCH 72 | 100 | FOOT | $35.00 | $10.00 | $26.25 | $50.40 | $35.30 | $1.00 | $10.00 | $44.50 | |
| 24 | 25000210 | SEEDING CL 2A | 1.25 | ACRE | $2,145.00 | $2,250.00 | $2,000.00 | $1,650.00 | $1,500.00 | $4,840.00 | $3,000.00 | $1,950.00 | |
| 25 | 25000400 | NITROGEN FERT NUTR | 110 | POUND | $2.75 | $3.00 | $2.55 | $1.38 | $1.25 | $1.00 | $4.00 | $2.50 | |
| 26 | 25000600 | POTASSIUM FERT NUTR | 110 | POUND | $2.75 | $3.00 | $2.55 | $1.38 | $1.25 | $1.00 | $4.00 | $2.50 | |
| 27 | 25100630 | EROSION CONTR BLANKET | 5,480 | SQ YD | $1.82 | $1.90 | $1.75 | $1.38 | $1.25 | $4.00 | $3.20 | $1.65 | |
| 28 | 28000305 | TEMP DITCH CHECKS | 153 | FOOT | $8.25 | $5.00 | $7.60 | $16.50 | $15.00 | $12.00 | $15.00 | $7.50 | |
| 29 | 28000400 | PERIMETER EROS BAR | 505 | FOOT | $2.48 | $1.00 | $2.35 | $6.60 | $6.00 | $3.75 | $2.00 | $2.25 | |
| 30 | 28000510 | INLET FILTERS | 26 | EACH | $181.50 | $15.00 | $170.00 | $190.40 | $156.55 | $25.00 | $25.00 | $165.00 | |
| 31 | 28100105 | STONE RIPRAP CL A3 | 8 | SQ YD | $100.00 | $80.00 | $76.00 | $112.00 | $201.45 | $200.00 | $120.00 | $156.88 | |
| 32 | 30300001 | AGG SUBGRADE IMPROVE | 433 | CU YD | $50.00 | $15.00 | $34.00 | $50.40 | $40.80 | $22.00 | $35.00 | $62.84 | |
| 33 | 35101800 | AGG BASE CSE B 6 | 5,242 | SQ YD | $9.20 | $8.50 | $8.78 | $7.28 | $11.25 | $14.75 | $10.00 | $9.82 | |
| 34 | 40600275 | BIT MATLS PR CT | 9,416 | POUND | $0.0100 | $0.0100 | $0.1000 | $0.5400 | $0.1000 | $0.9900 | $0.9000 | $0.6900 | |
| 35 | 40600290 | BIT MATLS TACK CT | 948 | POUND | $0.0100 | $0.0100 | $0.1000 | $0.5400 | $0.1000 | $1.53 | $3.00 | $0.9000 | |
| 36 | 40601005 | HMA REPL OVER PATCH | 5 | TON | $0.0100 | $300.00 | $244.50 | $250.88 | $325.00 | $365.00 | $480.00 | $445.50 | |
| 37 | 40603335 | HMA SC "D" N50 | 946 | TON | $81.00 | $91.50 | $91.00 | $96.54 | $91.50 | $114.62 | $160.00 | $101.15 | |
| 38 | 42400300 | PC CONC SIDEWALK 6 | 1,887 | SQ FT | $6.50 | $8.65 | $6.60 | $6.72 | $10.70 | $13.00 | $8.00 | $12.00 | |
| 39 | 42400800 | DETECTABLE WARNINGS | 457 | SQ FT | $5.00 | $25.00 | $29.00 | $34.72 | $18.80 | $15.00 | $25.00 | $35.00 | |
| 40 | 44000100 | PAVEMENT REM | 238 | SQ YD | $15.00 | $15.00 | $14.50 | $14.22 | $20.10 | $30.00 | $15.00 | $35.18 | |
| 41 | 44000500 | COMB CURB GUTTER REM | 513 | FOOT | $8.00 | $6.50 | $4.90 | $6.72 | $13.70 | $30.00 | $6.00 | $6.78 | |
| 42 | 44000600 | SIDEWALK REM | 16,067 | SQ FT | $1.50 | $1.00 | $1.40 | $1.90 | $1.40 | $3.00 | $1.50 | $3.89 | |
| 43 | 44002206 | HMA RM OV PATCH 1 1/2 | 52 | SQ YD | $15.00 | $15.00 | $20.00 | $20.89 | $20.00 | $1.00 | $30.00 | $42.84 | |
| 44 | 44201757 | CL D PATCH T3 9 | 19 | SQ YD | $100.00 | $135.00 | $225.00 | $107.52 | $165.00 | $175.00 | $300.00 | $312.30 | |
| 45 | 44201759 | CL D PATCH T4 9 | 27 | SQ YD | $90.00 | $130.00 | $225.00 | $109.76 | $165.00 | $175.00 | $300.00 | $312.30 | |
| 46 | 48101498 | AGGREGATE SHLDS B 4 | 109 | SQ YD | $8.00 | $7.00 | $70.50 | $7.62 | $38.90 | $40.00 | $44.00 | $28.38 | |
| 47 | 50901720 | BICYCLE RAILING | 273 | FOOT | $247.50 | $335.00 | $243.00 | $247.50 | $225.00 | $225.00 | $247.00 | $225.00 | |
| 48 | 54260615 | SLP MT ES WG 15",1:4 | 1 | EACH | $875.00 | $1,500.00 | $515.00 | $1,089.00 | $6,800.00 | $750.00 | $1,000.00 | $990.00 | |
| 49 | 550A0340 | STORM SEW CL A 2 12 | 120 | FOOT | $73.00 | $80.00 | $87.00 | $100.80 | $125.00 | $100.00 | $80.00 | $89.71 | |
| 50 | 550A0360 | STORM SEW CL A 2 15 | 10 | FOOT | $90.00 | $100.00 | $92.00 | $99.68 | $150.00 | $110.00 | $140.00 | $88.50 | |
| 51 | 55100500 | STORM SEWER REM 12 | 145 | FOOT | $12.50 | $1.00 | $39.00 | $48.16 | $20.00 | $10.00 | $14.00 | $42.90 | |
| 52 | 56400100 | FIRE HYDNTS TO BE MVD | 3 | EACH | $2,500.00 | $1,000.00 | $5,050.00 | $8,827.84 | $6,800.00 | $6,500.00 | $3,100.00 | $7,881.67 | |
| 53 | 60207605 | CB TC T8G | 4 | EACH | $1,400.00 | $1,900.00 | $1,800.00 | $1,933.12 | $2,000.00 | $1,775.00 | $2,300.00 | $1,725.75 | |
| 54 | 60210500 | CB TD 3 DIA T1F OL | 1 | EACH | $1,700.00 | $1,950.00 | $2,500.00 | $1,948.80 | $3,800.00 | $2,650.00 | $2,100.00 | $1,740.00 | |
| 55 | 60218400 | MAN TA 4 DIA T1F CL | 2 | EACH | $2,350.00 | $3,000.00 | $3,000.00 | $2,609.60 | $5,400.00 | $3,550.00 | $2,900.00 | $2,330.00 | |
| 56 | 60235700 | INLETS TA T3F&G | 1 | EACH | $1,300.00 | $1,800.00 | $1,300.00 | $2,133.60 | $1,500.00 | $1,775.00 | $1,000.00 | $1,905.00 | |
| 57 | 60250200 | CB ADJUST | 2 | EACH | $725.00 | $350.00 | $565.00 | $512.96 | $209.95 | $375.00 | $650.00 | $457.50 | |
| 58 | 60250500 | CB ADJ NEW T1F CL | 11 | EACH | $900.00 | $500.00 | $920.00 | $809.76 | $700.00 | $675.00 | $850.00 | $722.50 | |
| 59 | 60255500 | MAN ADJUST | 15 | EACH | $700.00 | $350.00 | $600.00 | $548.80 | $500.00 | $375.00 | $650.00 | $490.00 | |
| 60 | 60255800 | MAN ADJ NEW T1F CL | 1 | EACH | $900.00 | $500.00 | $930.00 | $845.60 | $800.00 | $675.00 | $1,000.00 | $755.00 | |
| 61 | 60265700 | VV ADJUST | 1 | EACH | $700.00 | $350.00 | $640.00 | $548.80 | $500.00 | $375.00 | $500.00 | $490.00 | |
| 62 | 60266600 | VALVE BOX ADJ | 1 | EACH | $400.00 | $250.00 | $425.00 | $329.28 | $385.00 | $150.00 | $500.00 | $293.75 | |
| 63 | 60500105 | FILL MANHOLES | 1 | EACH | $400.00 | $500.00 | $320.00 | $952.00 | $350.00 | $1,000.00 | $400.00 | $850.00 | |
| 64 | 60603800 | COMB CC&G TB6.12 | 450 | FOOT | $25.00 | $33.00 | $26.00 | $23.52 | $42.95 | $83.00 | $25.00 | $45.00 | |
| 65 | 60604400 | COMB CC&G TB6.18 | 45 | FOOT | $35.00 | $40.00 | $30.00 | $28.56 | $54.15 | $85.00 | $29.00 | $45.00 | |
| 66 | 66900200 | NON SPL WASTE DISPOSL | 8 | CU YD | $150.00 | $200.00 | $155.00 | $296.80 | $215.00 | $325.00 | $500.00 | $285.48 | |
| 67 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $6,215.00 | $5,000.00 | $3,800.00 | $4,233.60 | $4,100.00 | $2,500.00 | $5,000.00 | $4,000.00 | |
| 68 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,650.00 | $1,800.00 | $2,350.00 | $2,530.00 | $1,450.00 | $1,500.00 | $1,400.00 | $1,250.00 | |
| 69 | 67100100 | MOBILIZATION | 1 | L SUM | $35,000.00 | $38,000.96 | $40,000.00 | $49,400.00 | $25,600.00 | $73,178.00 | $48,000.00 | $105,498.29 | |
| 70 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $15,000.00 | $45,500.00 | $5,100.00 | $5,500.00 | $5,000.00 | $5,000.00 | $57,000.00 | $5,000.00 | |
| 71 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.0100 | $1.00 | $1.05 | $110.00 | $1.00 | $1.00 | $100.00 | $1.00 | |
| 72 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $0.0100 | $1.00 | $1.05 | $110.00 | $1.00 | $1.00 | $100.00 | $5,000.00 | |
| 73 | 72000100 | SIGN PANEL T1 | 23 | SQ FT | $27.50 | $25.00 | $26.00 | $27.50 | $25.00 | $25.00 | $30.00 | $25.00 | |
| 74 | 72400500 | RELOC SIN PAN ASSY TA | 7 | EACH | $192.50 | $250.00 | $176.00 | $192.50 | $175.00 | $175.00 | $200.00 | $175.00 | |
| 75 | 72800100 | TELES STL SIN SUPPORT | 120 | FOOT | $16.50 | $15.00 | $15.20 | $16.50 | $15.00 | $15.00 | $17.00 | $15.00 | |
| 76 | 78000200 | THPL PVT MK LINE 4 | 483 | FOOT | $1.30 | $1.45 | $1.20 | $1.29 | $1.17 | $1.17 | $1.50 | $1.12 | |
| 77 | 78000400 | THPL PVT MK LINE 6 | 726 | FOOT | $2.00 | $2.00 | $1.85 | $2.00 | $1.82 | $1.82 | $2.00 | $1.68 | |
| 78 | 78000600 | THPL PVT MK LINE 12 | 740 | FOOT | $4.00 | $4.00 | $3.65 | $4.00 | $3.64 | $3.64 | $4.00 | $3.35 | |
| 79 | 78005150 | EPOXY PVT MK LINE 12 | 494 | FOOT | $6.00 | $7.00 | $5.50 | $6.01 | $5.46 | $5.46 | $7.00 | $2.00 | |
| 80 | 78005180 | EPOXY PVT MK LINE 24 | 205 | FOOT | $12.00 | $14.00 | $10.95 | $12.00 | $10.92 | $10.92 | $14.00 | $4.00 | |
| 81 | 88600600 | DET LOOP REPL | 120 | FOOT | $32.45 | $31.00 | $30.00 | $31.00 | $29.80 | $29.80 | $33.00 | $29.80 | |
| 82 | 89500400 | RELOC EX PED PUSH-BUT | 2 | EACH | $577.50 | $175.00 | $590.00 | $170.00 | $585.00 | $585.00 | $700.00 | $585.00 |