IDOT Jobs

All dates · 4,218 jobs · $20,005,846,000
★ My Jobs

4,218 jobs · $20,005,846,000 estimated

ExcelCSV
Let date Contract / PPS County / Division Highway Description Estimate Status Added Low bidder
Feb 27, 2026 97889 MonroeDistrict 8 HMA resurfacing of various roadways in the village of Valmeyer. Additionally includes variable depth PCC surface removal, pavement markings, ADA sidewalk improvements and other required work. — Executed Nov 25 New Christ Bros. Asphalt, Inc. $716,678 ·
Feb 27, 2026 99757 WilliamsonDistrict 9 Construction of a roundabout intersection at Cambria Road and Cardinal Road/ Grand Avenue intersection. Work includes PCC pavement, curb and gutter, drainage improvements, lighting and other required work. , Construction of a roundabout intersection at Cambria Road and Cardinal Road/Grand Avenue intersection. Work includes PCC pavement, curb and gutter, drainage improvements, lighting and other required work. — Executed Nov 25 New Samron Midwest Contracting, Inc. $1,715,790 ·
Apr 24, 2026 46670 JerseyMadisonSt. ClairDistrict 8 Pavement marking replacement at various locations in Jersey, Madison and St. Clair Counties. — Executed Nov 25 New A. C. Pavement Striping Co. $202,951 ·
Apr 24, 2026 46671 VariousDistrict 3 Repairing various widths of pavement marking including lines, letters, numbers, and symbols on various highways, freeways, and expressways throughout District 3. — Executed Nov 25 New ROADSAFE TRAFFIC SYSTEMS, INC. $1,689,828 ·
Apr 24, 2026 46672 VariousDistrict 2 Placing various widths of Preformed Plastic and Modified Urethane pavement marking lines, letters and symbols within the limits specified on each individual work order within District 2. — Executed Nov 25 New America's Parking ReMarking, LLC. $2,856,750 ·
Apr 24, 2026 46675 VariousDistrict 2 Maintenance of signs along state maintained routes in District 2. — Executed Nov 25 New ROADSAFE TRAFFIC SYSTEMS, INC. $1,094,894 ·
Apr 24, 2026 46948 MaconDistrict 7 HMA resurfacing of roadway and parking lots, striping of parking lots, culvert replacements, storm sewer replacements, sign replacements, and sidewalk and ADA improvements at two IDNR State Parks; Spitler Woods and Lincoln Trail Homestead. — Executed Nov 25 New Illinois Valley Paving, a div of UCM, Inc. $2,699,505 ·
Apr 24, 2026 61L48 McHenryDistrict 1 Reconstruct and realign Kreutzer Road from east of IL 47 to Haligus Road in Huntley. Includes; pavement removal, earth excavation, HMA pavement, storm sewer, curb and gutter, sidewalks, box culvert, and highway lighting. — Executed Nov 25 New William Charles Construction Company, LLC $12,274,333 ·
Apr 24, 2026 61L54 CookDistrict 1 HMA resurfacing of FAU 1447 (16th St.) from Harlem Ave. to Lombard Ave. in the City of Berwyn. Additional work includes traffic signal improvements, curb and gutter repair, pavement markings and other required work. — Executed Nov 25 New Martam Construction Incorporated $10,340,904 ·
Apr 24, 2026 61L84 DuPageDistrict 1 HMA resurfacing of FAU 1379 (Fullerton Ave.) from Gary Ave. to Schmale Rd. in the Village of Carol Stream. Additional work includes curb and gutter, sidewalks with ADA ramps, street lighting, pavement marking and other required work. — Executed Nov 25 New K-Five Construction Corporation $2,324,754 ·
Apr 24, 2026 61L86 McHenryDistrict 1 Construct a single-span PPC I-girder bridge with RC concrete deck to carry W. Solon Road over the North Branch Nippersink Creek. Includes; HMA approach, driveways, storm sewer, sheet pile retaining wall, and guardrail. — Executed Nov 25 New Dunnet Bay Construction Company $4,604,844 ·
Apr 24, 2026 61M11 KaneDistrict 1 Construct an HMA path adjacent to South Edgelawn Drive at the BNSF Railroad tracks between Jericho Road and Kingsway Drive. — Executed Nov 25 New Alliance Contractors, Inc. $214,945 ·
Apr 24, 2026 61M15 CookDistrict 1 Construct a prefabricated truss bridge with approach spans to carry a shared-use path over US 14 and Union Pacific Railroad. Includes; MSE walls, HMA path, sidewalk, pavement patching, landscaping, and drainage improvements from Melas Park to Meadows Park in Mount Prospect. — Executed Nov 25 New Dunnet Bay Construction Company $10,744,243 ·
Apr 24, 2026 61M17 KaneDistrict 1 Reconstruction of TR 245 (Boyer Road) from Longmeadow Parkway to County Line Road in the Village of Algonquin. Work includes HMA pavement, sidewalk, pipe and culverts. — Executed Nov 25 New Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. $3,694,062 ·
Apr 24, 2026 61M33 KaneDistrict 1 Construction of a single-lane roundabout intersection at the intersection of Highland Ave. and Lyle Ave. in the City of Elgin. Work includes HMA pavement reconstruction, curb and gutter, sidewalks, storm sewer, lighting and other required work. — Rejected Nov 25 New
Apr 24, 2026 61M34 LakeDistrict 1 Resurfacing Brierwoods Lane from Lake Zurich City Limits to Bruce Circle N; Bruce Circle N from Brierwoods Lane to Acorn Drive and Acorn Drive from Bruce Circle N to Old McHenry Road in the Village of Hawthorn Woods. — Executed Nov 25 New Geske and Sons, Inc. $518,460 ·
Apr 24, 2026 61M35 McHenryDistrict 1 Construction of sidewalks along FAU 0006 (Marengo Rd.) and FAU 0005 (Ayer St.) in the City of Harvard. Additional work includes curb and gutter, patching, storm sewer and other required work. — Executed Nov 25 New Landmark Contractors, Inc. $333,272 ·
Apr 24, 2026 61M36 DuPageDistrict 1 Resurfacing Mill Pond Drive from Schmale Road to Exchange Boulevard/President Street in Glendale Heights. — Executed Nov 25 New Builders Paving, LLC $979,958 ·
Apr 24, 2026 61M37 DuPageDistrict 1 Resurfacing on North Grace Street from IL 64/North Avenue to East St. Charles Road in Lombard. — Executed Nov 25 New R. W. Dunteman Company $1,684,000 ·
Apr 24, 2026 61M41 LakeDistrict 1 PCC sidewalk along Sheridan Road from Cedar Avenue to roger Williams Avenue in Highland Park. Includes; HMA resurfacing, PCC driveways, retaining wall, and drainage improvements. — Executed Nov 25 New Alliance Contractors, Inc. $3,060,718 ·
Apr 24, 2026 62K33 CookDistrict 1 (2.03-Mile) The project includes widening and reconstruction of Barrington Road to provide two lanes in each direction separated by a median from Mundhank Road to IL 62, replacing the Poplar Creek box culvert, modernizing and replacing traffic signals, interconnection, sidewalk and shared-use paths, ADA improvements, landscaping. The project is located on Barrington Road from Central Road to IL 62 (Algonquin Road). — Executed Nov 25 New Plote Construction, Inc. $31,680,000 ·
Apr 24, 2026 62L85 CookDistrict 1 Hot-mix asphalt pavement removal and replacement, combination curb and gutter removal and replacement, thermop (1,525-Ft) Standard Overlay consists of hot-mix asphalt pavement removal and replacement, combination curb and gutter removal and replacement, thermoplastic pavement marking, sidewalk removal and replacement. Located in the Village of Forest Park, Cook County. — Executed Nov 25 New K-Five Construction Corporation $852,460 ·
Apr 24, 2026 62P51 CookDistrict 1 Earth excavation, pavement removal, sidewalk removal, driveway removal, (HMA) surface removal, curb and gutter (3,935-Ft) Traffic Signal Modernization and lighting installation project consists of earth excavation, pavement removal, sidewalk removal, driveway removal, (HMA) surface removal, curb and gutter removal, pavement patching, installation of aggregate and (HMA) shoulders, widening with (HMA) base course, resurfacing with polymerized (HMA) binder and polymerized (HMA) surface courses, structure adjustments, installation of storm sewer, drainage structures, sidewalk, shared-use path, driveways, lig — Executed Nov 25 New Martam Construction Incorporated $6,339,172 ·
Apr 24, 2026 62V71 WillDistrict 1 Hot-mix asphalt surface removal, placement of hot mix surface course, placement of hot mix binder course, pede (3.87-Mile) Standard overlay and ADA curb ramp improvement project consists of hot-mix asphalt surface removal, placement of hot mix surface course, placement of hot mix binder course, pedestrian ramp improvements, pavement patching, placement of pavement markings. The project is in the Cities of Lockport and Joliet within Will County. — Executed Nov 25 New D. Construction, Inc. $2,821,627 ·
Apr 24, 2026 62X31 CookWillDistrict 1 (650-Ft) Two culverts (SN 016-2290 and SN 099-0541) will undergo routine maintenance and repairs. Items include structural repair of concrete on headwalls and the removal and replacement of a wingwall. This project is located at FAI Route 57 over Butterfield Creek (0.04 Miles North of Village Commons Drive) and FAI Route 57 over Culvert (0.38 Miles North of Harlem Ave) — Executed Nov 25 New D. Construction, Inc. $135,363 ·
Apr 24, 2026 62X44 CookDistrict 1 Bridge deck concrete sealer upon the entire top surface of the bridge deck, sidewalks, top of inside vertical This improvement consists of bridge deck concrete sealer upon the entire top surface of the bridge deck, sidewalks, top of inside vertical faces of the faces of curbs/raised medians, and inside and outside of dividing walls along walkways of the structure, roadway faces of parapets. (41) SN locations along I-90/94 (Edens and Kennedy Expressways) in the City of Chicago, Villages of Skokie and Wilmette, Cook County. — Executed Nov 25 New Mosley Construction 1, LLC $459,265 ·
Apr 24, 2026 62X57 CookDistrict 1 Pavement patching, resurfacing with polymerized hot-mix asphalt surface course, binder course, ADA improvement (1.27-Mile) Design Overlay consists of pavement patching, resurfacing with polymerized hot-mix asphalt surface course, binder course, ADA improvement and curb and gutter replacement, thermoplastic pavement marking. This improvement is in the Village of Wilmette, Kenilworth and Winnetka. — Executed Nov 25 New Schroeder Asphalt Services, Inc. $1,529,254 ·
Apr 24, 2026 62Y28 CookDistrict 1 Furnishing all labor, materials, equipment, and other incidentals necessary for the conversion of existing ITS The work consists of furnishing all labor, materials, equipment, and other incidentals necessary for the conversion of existing ITS equipment to run on cellular communications. This work also consists of installing temporary fiber optic cable. Improvements associated with this project are located with the Villages of Hillside, Bellwood, Westchester, Broadview, Maywood, Forest Park, and Oak Park, as well as the City of Chicago in Cook County, on I-290 between Wolf Road and Racine Avenue. — Executed Nov 25 New Meade Inc. $9,649,148 ·
Apr 24, 2026 62Y30 CookDistrict 1 Scarify and overlay bridge deck, bridge deck repairs, repair piers and abutments, repair parapets and sidewalk (190-Ft) Bridge Deck Overlay, Bridge Joint Replacement consists of scarify and overlay bridge deck, bridge deck repairs, repair piers and abutments, repair parapets and sidewalk, joint replacement, and graffiti removal on the bridge of US 14 (Peterson Ave) over North Shore Channel. This project is in the City of Chicago in Cook County. — Executed Nov 25 New Martam Construction Incorporated $786,723 ·
Apr 24, 2026 62Y31 VariousDistrict 1 Repairing, installing, and establishing landscape materials and features Roadside development work shall consist of repairing, installing, and establishing landscape materials and features. This work is located within the right-of-way limits along various state-maintained routes located in District One (counties of Cook, DuPage, Kane, Lake, McHenry, and Will). — Executed Nov 25 New McGinty Bros., Inc. $591,935 ·
Apr 24, 2026 62Y34 VariousDistrict 1 Applying selective and non-selective herbicide mixtures to control weeds within medians, guardrails, interchan This work consists of applying selective and non-selective herbicide mixtures to control weeds within medians, guardrails, interchanges, infields, shoulders and slopes within the limits of the right of way areas in District One. — Executed Nov 25 New McGinty Bros., Inc. $802,100 ·
Apr 24, 2026 64L51 Jo DaviessDistrict 2 3.98 miles of milling, Cold in Place recycling and HMA overlay from IL 84 from Wisconsin State Line to 0.2 miles north of US 20. — Executed Nov 25 New Civil Constructors, Inc. d/b/a/ Helm Civil $3,793,443 ·
Apr 24, 2026 64T06 OgleDistrict 2 Bridge repairs and joint replacement on SN's 071-0046/0047, carrying I-39 over IL 72 3.5 miles south of Winnebago County Line and SN's 071-0048/0049 carrying I-39 over DME RR 0.025 miles south of IL 72. — Executed Nov 25 New Martin & Company Excavating $3,168,316 ·
Apr 24, 2026 64T42 StephensonDistrict 2 Bridge repairs and joint replacement on SN'S 089-0048, 089-0049, 089-0050, 089-0055 and 089-00061 along US 20 Freeport Bypass. — Executed Nov 25 New Martin & Company Excavating $4,082,943 ·
Apr 24, 2026 64T73 LeeDistrict 2 2.32 miles US 30 to Wasson Rd in Amboy (designed overlay, cold milling), 0.80 miles Wasson Rd to Water St in Amboy (standard overlay, cold milling). — Executed Nov 25 New Martin & Company Excavating $1,988,394 ·
Apr 24, 2026 64U85 LeeDistrict 2 1 mile of patching from Lowell Park Rd. to Fellows St. in Dixon. — Executed Nov 25 New Civil Constructors, Inc. d/b/a/ Helm Civil $564,716 ·
Apr 24, 2026 64U89 WinnebagoDistrict 2 Bridge repairs, deck overlay and joint replacement on SN 101-0167, carrying US 20 over Grove Creek; 0.3 miles east of the Stephenson County Line. — Executed Nov 25 New Martin & Company Excavating $522,276 ·
Apr 24, 2026 64U90 WinnebagoDistrict 2 Bridge repairs, deck overlay and joint replacement on SN 101-0165, carrying IL 70 over Pecatonica Rd; 1.1 miles north of Cemetery Rd. — Executed Nov 25 New Martin & Company Excavating $1,670,253 ·
Apr 24, 2026 64U93 VariousDistrict 2 Various routes on-call guardrail throughout District 2. — Executed Nov 25 New Northern Contracting, Inc. $973,094 ·
Apr 24, 2026 64U99 WhitesideDistrict 2 Full cleaning and painting of SN 098-0065 and SN 098-0055. — Executed Nov 25 New Venus Painting Co. $731,620 ·
Apr 24, 2026 64V32 VariousDistrict 2 Repair, replace, maintain, or servicing the Department's Intelligent Transportation Equipment in all counties within Districts 2 and 3. — Executed Nov 25 New Laser Electric, Inc. $424,500 ·
Apr 24, 2026 64V38 WinnebagoDistrict 2 Overhead sign structure installation on IL 251, 0.3 miles south of Landstrom Rd. — Executed Nov 25 New ROADSAFE TRAFFIC SYSTEMS, INC. $333,333 ·
Apr 24, 2026 64V43 WhitesideDistrict 2 Concrete sealer applied to the deck of SN 098-6003, carrying US 30 over the Mississippi River. — Executed Nov 25 New All States Painting, Inc. $31,073 ·
Apr 24, 2026 66M03 BureauDistrict 3 Bridge Deck Replacement (SN 006-0090) over the Hennepin Canal 0.4 Mi south of I-80 in Bureau County. — Executed Nov 25 New D. Construction, Inc. $1,719,727 ·
Apr 24, 2026 66M55 LaSalleDistrict 3 Bridge Replacement (SN 050-0033) over the Fox River in Ottawa IL and milling and resurfacing to US 6. 1.75 miles gross length. — Executed Nov 25 New D. Construction, Inc. $20,377,827 ·
Apr 24, 2026 66N58 GrundyDistrict 3 Rehabilitation of SN 032-0025, carrying US 6 over Aux Sable Creek in Grundy County. — Executed Nov 25 New D. Construction, Inc. $1,596,194 ·
Apr 24, 2026 66P68 IroquoisDistrict 3 A SMART resurfacing along with an experimental mix design of the eastbound lane 6.04 mi of 1.5" milling and hot-mix asphalt surface course pavement rehabilitation and minor drainage repairs including culvert work on Old Route 24 and ADA sidewalk ramp improvements. Project consists of a SMART resurfacing along with an experimental mix design of the eastbound lane. — Executed Nov 25 New Iroquois Paving Corporation $2,884,241 ·
Apr 24, 2026 66P86 BureauDistrict 3 5.75 miles of milling and HMA resurfacing of US 6/34 with 3-4 foot aggregate wedge shoulders when curb and gutter is not present, ADA ramp, and other minor drainage improvements. Located on US 6/34 from 175 ft. east of Hazelwood Dr. in Wyanet to 90 ft. west of Main St. in Princeton, within Bureau County. — Executed Nov 25 New Advanced Asphalt Company $4,400,787 ·
Apr 24, 2026 66R50 IroquoisDistrict 3 Milling and resurfacing (designed overlay) with new shoulders and rumble strip. Additional work includes patching, ditch cleaning, drainage improvements, pavement marking, and rest area milling and resurfacing on US-52 from approximately 200' east of US-45 and IL-49 to approximately 1 mile west of IL-1 in Iroquois County. 5.98 miles gross length. — Executed Nov 25 New Iroquois Paving Corporation $6,694,992 ·
Apr 24, 2026 66R61 IroquoisDistrict 3 Scour repair, Deck/Approach, patching, Joint replacement, Slope wall repair and extending deck drains at structure No. 038-0037 carrying US Route 24 over Raymond Creek 2.65 miles east of IL 1 in Iroquois County. — Executed Nov 25 New Iroquois Paving Corporation $434,116 ·
Apr 24, 2026 66R63 BureauDistrict 3 Joint replacement, Deck patch, approach repairs, Beam end repairs, bearing retainer and paint, substructure and parapet repairs at structure SN 006-0149 carrying IL 92 over Bureau creek 1.6 miles west of US 34 in Bureau County. — Executed Nov 25 New D. Construction, Inc. $497,866 ·
Apr 24, 2026 66R64 LaSalleDistrict 3 Joint replacement, Deck patch, approach repairs, bearing retainer and paint, substructure repairs, Anti- Graffiti at structure No. 050-0218 carrying IL 351 over Lone Star Cement Railroad and structure No. 050-0019 carrying IL 351 over Lone Star Cement Railroad 2.0 miles South of US 6 in La Salle County. — Executed Nov 25 New D. Construction, Inc. $660,277 ·
Apr 24, 2026 66R66 FordDistrict 3 Joint replacement, deck patch, substructure repairs_at structure No: SN 027-0082 carrying IL 115 over Trib. Spring Creek 7.76 miles north of IL 9 and at structure No. 027-0083 carrying IL 115 E. Branch Vermilion_River in Ford County. — Executed Nov 25 New Iroquois Paving Corporation $483,342 ·
Apr 24, 2026 66R68 KankakeeDistrict 3 Joint replacement, bearing replacement, deck and approach patch, HMA shoulder and concrete repairs at structure No. 046-0021 carrying IL 1 over Trim Creek 0.2 miles west of Grant Park in Kankakee County. — Executed Nov 25 New Tobey's Construction & Cartage, Inc. $591,428 ·
Apr 24, 2026 66R69 BureauDistrict 3 Joint replacement, deck and approach patching at structure No. 006-0084 carrying IL 29 over Big Bureau Creek 0.1 miles south of IL 26 in Bureau County. — Executed Nov 25 New Gensini Excavating, Inc. $421,787 ·
Apr 24, 2026 66T17 KankakeeDistrict 3 Intermittent HMA milling and resurfacing, pavement marking, raised reflective markers, and detector loops on F Work consists of intermittent HMA milling and resurfacing, pavement marking, raised reflective markers, and detector loops on FAP 840 (IL-50) from north of US 45/52 to south of Brookmont Blvd and Indiana Ave to Fair St in Kankakee. 4.09 miles gross length. — Executed Nov 25 New Kankakee Valley Construction Company, Inc. $2,380,597 ·
Apr 24, 2026 66T25 BureauDistrict 3 Replacing the existing high mast tower lighting with 45 ft. light poles at I-180 and IL 26 interchanges of Exit 7 and Exit 12. — Executed Nov 25 New Helm Electric Facility Solutions, Inc. d/b/a Helm Electric $511,814 ·
Apr 24, 2026 66T58 LaSalleDistrict 3 Routing and filling the cracks along the centerline, significant transverse cracks and pavement markings along US 34 from 12th Rd. west of Earlville to west of the US 34 and IL 23 junction in LaSalle County. 6.44 miles gross length. — Executed Nov 25 New Complete Asphalt Service Co. $49,800 ·
Apr 24, 2026 68H43 VariousDistrict 4 Bridge deck sealing at various locations within District 4. — Executed Nov 25 New All States Painting, Inc. $269,552 ·
Apr 24, 2026 68J16 TazewellDistrict 4 Bridge joint replace and repair, bridge deck overlay, slope wall repair at SN 090-0152 carrying IL 40 ramp to I-74 WB in East Peoria in Tazewell County. — Executed Nov 25 New Stark Excavating, Inc. $478,751 ·
Apr 24, 2026 68J47 VariousDistrict 4 Crack and joint sealing on various routes in various couties in District 4. — Executed Nov 25 New Denler, Inc. $830,029 ·
Apr 24, 2026 68J60 TazewellDistrict 4 5.86 miles of CIR and design overlay of IL 122 from 2.1 miles east of Hopedale to the McLean County line. — Executed Nov 25 New R. A. Cullinan and Son, a div of UCM, Inc. $8,241,332 ·
Apr 24, 2026 68J88 PeoriaDistrict 4 3.49 miles of resurfacing of IL 8 (W. Southport Rd) from 0.7 mile east of Taylor Rd to I-474 in Peoria County. — Executed Nov 25 New Advanced Asphalt Company $1,996,962 ·
Apr 24, 2026 68J89 PeoriaDistrict 4 6.5 miles of resurfacing and cold in-place recycling on IL 8 from Texas Rd to Taylor Rd in Peoria County. — Executed Nov 25 New Advanced Asphalt Company $4,472,093 ·
Apr 24, 2026 68J95 MarshallDistrict 4 8.4 miles of CIR and design overlay of IL 17 from the eastern city limits of Lacon to IL 89. — Executed Nov 25 New Advanced Asphalt Company $9,352,996 ·
Apr 24, 2026 68K12 TazewellDistrict 4 5.656 gross miles of microsurfacing on I-474/US 24 from the Illinois River to I-74 in Tazewell County. — Executed Nov 25 New Beniach Construction Co., Inc. $2,076,981 ·
Apr 24, 2026 68K17 FultonDistrict 4 9.93 miles of 3P resurfacing on US Route 24 from Izaack Walton Road to North of Rut Road in Fulton County. — Executed Nov 25 New Illinois Valley Paving, a div of UCM, Inc. $10,922,962 ·
Apr 24, 2026 68K20 StarkDistrict 4 6.45 miles of resurfacing from the southern city limit of Bradford to the west leg of IL 17. Milling and resurfacing and minor drainage improvements at the IL 40 Camp Grove Rest Area located 0.6 mile north of the west leg of IL 17 are also included. — Executed Nov 25 New Advanced Asphalt Company $2,839,793 ·
Apr 24, 2026 68K22 WoodfordDistrict 4 Bridge repairs on IL 26, south of IL 17:SN 102-0067 over Snag Creek, SN 102-0064 over Dry Creek, SN 102-0063 over Richland Creek, SN 102-0066 over Partridge Creek, SN 102-0065 over Balock Creek in Woodford County. — Executed Nov 25 New Stark Excavating, Inc. $2,172,735 ·
Apr 24, 2026 68K23 KnoxDistrict 4 5.84 miles of 3P resurfacing on US 34 in Knox County from 0.4 mile west of Interstate 74 to Knox Road 900E. — Executed Nov 25 New Gunther Construction, a div of UCM, Inc. $11,296,811 ·
Apr 24, 2026 68K33 MercerDistrict 4 5.93 mile SMART project consisting of resurfacing, replacing guardrail, patching, and all related collateral work along Keithsburg Rd from just north of Main St in Keithsburg to just south of Illinois Route 17 in Mercer County. — Executed Nov 25 New Valley Construction Co. $1,862,714 ·
Apr 24, 2026 68K54 VariousDistrict 4 Pavement marking throughout District 4. — Executed Nov 25 New Varsity Striping & Construction Co. $523,767 ·
Apr 24, 2026 68K86 HendersonWarrenDistrict 4 Removal and replacement of various installations of guardrail in District 4 along Illinois Route 116 (FAP 665), Illinois Route 135 (FAP 546), and Illinois Routes 94/116 (FAP 534) at various locations in Henderson and Warren Counties. — Executed Nov 25 New COLLINS & HERMANN, INC. $879,375 ·
Apr 24, 2026 68K87 TazewellDistrict 4 Fence removal and replacement around Operations Yard in Morton. — Executed Nov 25 New CSD Environmental Services, Inc. $173,612 ·
Apr 24, 2026 68K89 MarshallPutnamDistrict 4 8.9 miles of partial and full depth patching on Illinois Route 29 (FAP 318) beginning at the intersection of Illinois Route 29 and Illinois Route 18 in Marshall County to the northern border of Putnam County. — Executed Nov 25 New G. M. Sipes Construction, Inc. $883,425 ·
Apr 24, 2026 68L05 TazewellDistrict 4 Building demolition at 600 Main St (Parcel No. 4ABL011) in East Peoria, Tazewell County. — Executed Nov 25 New JIMAX Landscape LLC $72,493 ·
Apr 24, 2026 70574 McLeanDistrict 5 Remove and replace existing structure SN 057-0077 on FAP 693 IL. 9 with proposed SN 057-2043. This project is located over a stream, 8.8 mile east of ILL 165, beginning at Station 1646+93.90 and ending at Station 1647+47.10. — Executed Nov 25 New Stark Excavating, Inc. $786,020 ·
Apr 24, 2026 70E14 McLeanDistrict 5 SMART/Standard Overlay resurfacing project on FAI-74 from 0.4 mi E of US 51 Bus S of Bloomington to CH 36 (700 N Rd) at Downs. Approximately 7.08 miles. — Executed Nov 25 New Rowe Construction, a div of UCM, Inc. $14,480,725 ·
Apr 24, 2026 70E82 McLeanDistrict 5 Standard Overlay on IL 9 from Tazwell Co Line to IL 122. Approximately 7.155 miles gross length. — Executed Nov 25 New Rowe Construction, a div of UCM, Inc. $5,132,498 ·
Apr 24, 2026 70F20 McLeanDistrict 5 Remove and reconstruct FAP 693 (ILL 9, US 150) from east of Main St Ave to Towanda Avenue in Bloomington, IL. Approximately 1.231 miles gross length. — Executed Nov 25 New Stark Excavating, Inc. $15,389,316 ·
Apr 24, 2026 70H82 McLeanDistrict 5 0.01 mi patching FAI 39 (I-39) ramps at Hudson Interchange. — Executed Nov 25 New Stark Excavating, Inc. $476,214 ·
Apr 24, 2026 70H85 McLeanDistrict 5 2.19 Miles of Patching from Fox Creek Road to N of Washington St. in Bloomington. — Executed Nov 25 New Kinney Contractors, Inc. $1,233,555 ·
Apr 24, 2026 70H87 PiattDistrict 5 9.178 Miles of Mircosurfacing Joint Repair on I-72 from Bridge St in Monticello to Piatt/Champaign Co Line. — Executed Nov 25 New Beniach Construction Co., Inc. $389,851 ·
Apr 24, 2026 72296 LoganDistrict 6 Bridge deck overlay on SN 054-0102 carrying Old IL 121 over Sugar Creek, 2.5 miles southeast of CH 18 (2300 ST) in Hartsburg. — Executed Nov 25 New County Contractors, Inc. $728,275 ·
Apr 24, 2026 72348 SangamonDistrict 6 5.7 miles of resurfacing on IL 54 from 0.2 miles east of Prairie School Road to north of Bissell Road, northeast of Springfield. — Executed Nov 25 New P. H. Broughton & Sons, Inc. $4,462,601 ·
Apr 24, 2026 72441 LoganDistrict 6 2.5 miles of resurfacing on IL 121 from 0.2 miles west of CH 6 (west of Latham) to 0.1 miles west of the Macon County line. — Executed Nov 25 New Illinois Valley Paving, a div of UCM, Inc. $1,665,367 ·
Apr 24, 2026 72443 LoganTazewellDistrict 6 2 miles of resurfacing on Armington Road (US 136 Spur) from East Third Street in Armington to north of US 136. — Executed Nov 25 New Illinois Valley Paving, a div of UCM, Inc. $624,204 ·
Apr 24, 2026 72503 SangamonDistrict 6 Drainage improvements at the intersection of Old US 36 and Mt. Pulaski Road. — Executed Nov 25 New Phoenix Corporation of the Quad Cities $97,322 ·
Apr 24, 2026 72511 PikeDistrict 6 Bridge deck patching and curb repairs on SN 075-0139 carrying IL 96 over Walnut Creek, 0.8 miles north of I-72 at the Hull interchange. — Executed Nov 25 New County Contractors, Inc. $130,630 ·
Apr 24, 2026 72636 VariousDistrict 6 Maintenance and repair of surveillance cameras, vehicle detectors, dynamic message signs, advanced traffic management systems, fiber optic communications, traffic signal interconnects, ethernet networks, and all peripheral equipment throughout the district. — Executed Nov 25 New Capitol Construction Group, LLC d/b/a Egizii Electric $136,750 ·
Apr 24, 2026 72638 SangamonDistrict 6 0.1 miles of resurfacing on the IL 29 spur west of Hilltop Road; east of Springfield. — Executed Nov 25 New Truman L. Flatt & Sons Co., Inc. $65,135 ·
Apr 24, 2026 72669 MacoupinDistrict 6 Bridge deck overlay, bridge repairs, and bridge painting on SN 059-0049 carrying Shipman Blacktop over Macoupin Creek, 7.7 miles north of IL 16. — Executed Nov 25 New Sangamo Construction Company $1,677,084 ·
Apr 24, 2026 72741 SangamonDistrict 6 Drainage improvements on Old US 36 west of Illiopolis. — Executed Nov 25 New P. H. Broughton & Sons, Inc. $313,859 ·
Apr 24, 2026 72B63 AdamsDistrict 6 9.1 miles of pavement patching, HMA surface removal, HMA surfacing, entrance reconstruction and aggregate wedge shoulders on IL 61 from the IL 94 south junction to 0.2 miles west and on IL 94 from the IL 61 south junction to north of US 24. — Executed Nov 25 New Diamond Construction Company $6,499,144 ·
Apr 24, 2026 72E74 AdamsMacoupinDistrict 6 Railroad interconnects on IL 57 at Radio Road south of Qunicy and on IL 108 at Shipman Blacktop in Carlinville. — Executed Nov 25 New Capitol Construction Group, LLC d/b/a Egizii Electric $80,800 ·
Apr 24, 2026 72E75 AdamsDistrict 6 Bridge painting on portions of two bridges on US 24 and IL 57 near Quincy. (SN 001-0010 and 001-0012) — Executed Nov 25 New ERA-Valdivia Contractors, Inc. $283,520 ·
Apr 24, 2026 72F51 VariousDistrict 6 Maintenance and repair of traffic signals, flashing beacons and roadway lighting along various routes at various locations in the eastern half of District 6. — Executed Nov 25 New Capitol Construction Group, LLC d/b/a Egizii Electric $511,575 ·
Apr 24, 2026 72F52 VariousDistrict 6 Maintenance and repair of traffic signals, flashing beacons and roadway lighting along various routes at various locations in the western half of District 6. — Executed Nov 25 New Capitol Construction Group, LLC d/b/a Egizii Electric $273,790 ·
Apr 24, 2026 72N43 SangamonDistrict 6 Expansion of the Emergency Vehicle Operations Course (EVOC) at the Illinois State Police Training Facility in Pawnee includes site grading, paving, and associated amenities. — Executed Nov 25 New Baxmeyer Construction, Inc. $13,405,307 ·
Apr 24, 2026 74D10 FayetteDistrict 7 2.4 miles of resurfacing and aggregate wedge shoulder on US 51 from 0.5 miles south of Shobonier Spur to the Marion County line. — Executed Nov 25 New Howell Paving, Inc. $1,158,719 ·
1,301–1,400 of 4,218‹ PrevNext ›

Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.