Z[1V-RS-5;D-15D-RS-8;15D-RS-6]
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $1,996,962 | ||
| 2 | R. A. Cullinan and Son, a div of UCM, Inc. | $2,562,434 | +28.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… | #2 R. A. Cullinan … |
|---|---|---|---|---|---|---|---|
| 1 | XZ013798 | CONSTR STA LAYOUT | 1 | L SUM | $6,000.00 | $3,762.27 | |
| 2 | X4400196 | HMA SURF REM SPL | 1,024 | SQ YD | $14.00 | $19.99 | |
| 3 | X5430215 | CUR-IN-PL PIPE LNR 15 | 56 | FOOT | $270.00 | $343.69 | |
| 4 | X6060097 | CLASS SI CONC OUT SPL | 24 | CU YD | $595.00 | $913.50 | |
| 5 | X6062700 | CONC GUTTER TA SPL | 242 | FOOT | $60.00 | $99.75 | |
| 6 | X6350204 | LINEAR DELIN PANELS 4 | 47 | EACH | $75.00 | $78.75 | |
| 7 | Z0001002 | GDRL AGG EROS CONT | 1,014 | TON | $55.00 | $121.80 | |
| 8 | Z0076600 | TRAINEES | 2,000 | HOUR | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 2,000 | HOUR | $15.00 | $15.00 | |
| 10 | 20200600 | EXC & GR EX SHOULDER | 9 | UNIT | $150.00 | $1,102.11 | |
| 11 | 40200800 | AGG SURF COURSE TY B | 134 | TON | $52.56 | $44.10 | |
| 12 | 40600295 | P BIT MATLS TACK CT | 80,516 | POUND | $0.8500 | $1.13 | |
| 13 | 40600405 | MATL TRANSFER DEVICE | 11,026 | TON | $2.00 | $2.07 | |
| 14 | 40600982 | HMA SURF REM BUTT JT | 3,289 | SQ YD | $10.00 | $18.57 | |
| 15 | 40600990 | TEMPORARY RAMP | 445 | SQ YD | $15.00 | $8.11 | |
| 16 | 40603205 | P HMA BC IL-9.5 N50 | 5,153 | TON | $105.00 | $125.43 | |
| 17 | 40604162 | P HMA SC IL-9.5 D N70 | 6,108 | TON | $105.00 | $132.45 | |
| 18 | 40800050 | INCIDENTAL HMA SURF | 297 | TON | $150.00 | $273.27 | |
| 19 | 44000155 | HMA SURF REM 1 1/2 | 53,395 | SQ YD | $1.65 | $2.50 | |
| 20 | 44000200 | DRIVE PAVEMENT REM | 50 | SQ YD | $30.00 | $30.45 | |
| 21 | 44000400 | GUTTER REM | 400 | FOOT | $20.00 | $19.95 | |
| 22 | 48102100 | AGG WEDGE SHLD TYPE B | 1,442 | TON | $40.00 | $44.10 | |
| 23 | 48203021 | HMA SHOULDERS 6 | 287 | SQ YD | $40.00 | $70.07 | |
| 24 | 63000001 | SPBGR TY A 6FT POSTS | 3,513 | FOOT | $28.00 | $29.40 | |
| 25 | 63100167 | TR BAR TRM T1 SPL TAN | 17 | EACH | $2,950.00 | $3,097.50 | |
| 26 | 63100169 | TR BAR TRM T1 SPL FLR | 3 | EACH | $2,250.00 | $2,362.50 | |
| 27 | 63200310 | GUARDRAIL REMOV | 4,487 | FOOT | $4.00 | $4.20 | |
| 28 | 64200214 | SINUSOIDAL RUM STP 14 | 16,562 | FOOT | $0.6500 | $1.20 | |
| 29 | 67100100 | MOBILIZATION | 1 | L SUM | $7,000.00 | $28,141.84 | |
| 30 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $100.00 | $6,681.00 | |
| 31 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $21,980.00 | $4,021.52 | |
| 32 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $100.00 | $3,861.20 | |
| 33 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $125.00 | $144.61 | |
| 34 | 70300100 | SHORT TERM PAVT MKING | 6,780 | FOOT | $1.50 | $1.52 | |
| 35 | 70300150 | SHRT TRM PAVT MK REM | 754 | SQ FT | $2.00 | $13.38 | |
| 36 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 9,278 | FOOT | $0.2700 | $0.2800 | |
| 37 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 35,603 | FOOT | $0.2300 | $0.2400 | |
| 38 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 92 | FOOT | $13.50 | $14.18 | |
| 39 | 72501000 | TERMINAL MARKER - DA | 20 | EACH | $50.00 | $52.50 | |
| 40 | 78009004 | MOD URETH PM LINE 4 | 9,278 | FOOT | $1.05 | $1.10 | |
| 41 | 78009006 | MOD URETH PM LINE 6 | 36,728 | FOOT | $1.05 | $1.10 | |
| 42 | 78009024 | MOD URETH PM LINE 24 | 92 | FOOT | $20.00 | $21.00 | |
| 43 | 78011025 | GRV RCSD PVT MRKG 5 | 9,278 | FOOT | $0.1500 | $0.1600 | |
| 44 | 78011035 | GRV RCSD PVT MRKG 7 | 35,603 | FOOT | $0.1000 | $0.1100 | |
| 45 | 78011125 | GRV RCSD PVT MRKG 25 | 92 | FOOT | $9.50 | $9.98 | |
| 46 | 78100100 | RAISED REFL PAVT MKR | 232 | EACH | $48.00 | $50.40 | |
| 47 | 78300200 | RAISED REF PVT MK REM | 232 | EACH | $13.00 | $24.34 |