134RS-11, 135RS-2
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $1,665,367 | ||
| 2 | P. H. Broughton & Sons, Inc. | $1,666,586 | +0.1% | |
| 3 | Truman L. Flatt & Sons Co., Inc. | $1,765,458 | +6.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 P. H. Broughton… | #3 Truman L. Flatt… |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 2 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 3 | 20200100 | EARTH EXCAVATION | 45 | CU YD | $115.87 | $45.65 | $117.26 | |
| 4 | 35800100 | PREPARATION OF BASE | 281 | SQ YD | $5.10 | $11.50 | $4.56 | |
| 5 | 35800200 | AGG BASE REPAIR | 91 | TON | $39.84 | $63.27 | $65.72 | |
| 6 | 40200800 | AGG SURF COURSE TY B | 18 | TON | $72.14 | $63.27 | $175.30 | |
| 7 | 40600290 | BIT MATLS TACK CT | 30,167 | POUND | $1.01 | $0.6100 | $0.7100 | |
| 8 | 40600370 | LONG JOINT SEALANT | 13,328 | FOOT | $2.71 | $3.23 | $3.07 | |
| 9 | 40600405 | MATL TRANSFER DEVICE | 2,985 | TON | $3.04 | $3.63 | $9.21 | |
| 10 | 40600982 | HMA SURF REM BUTT JT | 2,005 | SQ YD | $7.29 | $11.48 | $12.91 | |
| 11 | 40600990 | TEMPORARY RAMP | 95 | SQ YD | $12.67 | $10.31 | $21.18 | |
| 12 | 40603080 | HMA BC IL-19.0 N50 | 4,478 | TON | $107.16 | $103.78 | $110.05 | |
| 13 | 40604050 | HMA SC IL-9.5 C N50 | 2,985 | TON | $118.80 | $113.38 | $121.46 | |
| 14 | 40800029 | BIT MATLS TACK CT | 808 | POUND | $0.8500 | $0.6100 | $0.7100 | |
| 15 | 40800050 | INCIDENTAL HMA SURF | 304 | TON | $237.94 | $214.86 | $242.35 | |
| 16 | 44000155 | HMA SURF REM 1 1/2 | 44,382 | SQ YD | $1.90 | $1.55 | $3.05 | |
| 17 | 44200168 | PAVT PATCH T2 14 | 91 | SQ YD | $305.97 | $348.02 | $243.14 | |
| 18 | 44200172 | PAVT PATCH T3 14 | 241 | SQ YD | $303.87 | $348.02 | $227.65 | |
| 19 | 44200174 | PAVT PATCH T4 14 | 137 | SQ YD | $301.77 | $348.02 | $217.17 | |
| 20 | 48102100 | AGG WEDGE SHLD TYPE B | 883 | TON | $40.91 | $63.27 | $46.47 | |
| 21 | 48203100 | HMA SHOULDERS | 1,921 | TON | $116.65 | $113.38 | $130.93 | |
| 22 | 64200108 | SHOULDER RUM STRIP 8 | 25,735 | FOOT | $0.2400 | $0.2500 | $0.5300 | |
| 23 | 67000400 | ENGR FIELD OFFICE A | 9 | CAL MO | $3,374.59 | $3,723.66 | $4,182.32 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $38,651.36 | $44,401.14 | $23,358.43 | |
| 25 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $14,805.00 | $21,580.25 | $1,104.56 | |
| 26 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $6,837.83 | $3,865.12 | $14,458.88 | |
| 27 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $3,496.50 | $3,575.23 | $4,418.20 | |
| 28 | 70107025 | CHANGEABLE MESSAGE SN | 15 | CAL DA | $131.25 | $134.21 | $132.00 | |
| 29 | 70300100 | SHORT TERM PAVT MKING | 3,999 | FOOT | $0.9800 | $1.61 | $1.58 | |
| 30 | 70300150 | SHRT TRM PAVT MK REM | 445 | SQ FT | $3.88 | $1.98 | $4.38 | |
| 31 | 78009005 | MOD URETH PM LINE 5 | 32,547 | FOOT | $1.05 | $1.07 | $1.10 | |
| 32 | 78009024 | MOD URETH PM LINE 24 | 24 | FOOT | $5.25 | $5.37 | $5.50 | |
| 33 | 78100100 | RAISED REFL PAVT MKR | 166 | EACH | $45.32 | $46.34 | $47.48 | |
| 34 | 78300200 | RAISED REF PVT MK REM | 166 | EACH | $13.76 | $13.93 | $19.82 |