(111B-1)BDR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | County Contractors, Inc. Low bidder | $728,275 | ||
| 2 | Freesen, a div of UCM, Inc. | $756,998 | +3.9% | |
| 3 | Otto Baum Company, Inc. | $818,100 | +12.3% | |
| 4 | Sangamo Construction Company | $850,912 | +16.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 County Contract… | #2 Freesen, a div … | #3 Otto Baum Compa… | #4 Sangamo Constru… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X5060601 | C&D N-LEAD PT C RS N1 | 1 | L SUM | $35,500.00 | $35,280.00 | $35,935.39 | $36,631.37 | |
| 2 | X5230172 | DRAINAGE SCUPPERS ADJ | 4 | EACH | $1,250.00 | $1,061.05 | $1,627.58 | $3,525.80 | |
| 3 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $2,275.00 | $2,257.50 | $4,404.19 | $5,872.01 | |
| 4 | X7200203 | DETOUR SIGNING | 1 | L SUM | $23,000.00 | $22,995.00 | $23,356.99 | $23,826.95 | |
| 5 | Z0001800 | APPR SLAB REPAIR (PD) | 30 | SQ YD | $650.00 | $859.02 | $594.75 | $1,467.09 | |
| 6 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $53,250.00 | $52,920.00 | $53,753.08 | $54,947.07 | |
| 7 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 9 | 40600290 | BIT MATLS TACK CT | 169 | POUND | $6.90 | $10.40 | $2.77 | $10.65 | |
| 10 | 40600982 | HMA SURF REM BUTT JT | 376 | SQ YD | $32.00 | $41.33 | $32.00 | $15.61 | |
| 11 | 40600990 | TEMPORARY RAMP | 29 | SQ YD | $65.00 | $15.88 | $55.14 | $49.24 | |
| 12 | 40604050 | HMA SC IL-9.5 C N50 | 37 | TON | $385.00 | $668.85 | $693.24 | $709.62 | |
| 13 | 42001300 | PROTECTIVE COAT | 1,785 | SQ YD | $5.00 | $3.40 | $4.37 | $4.10 | |
| 14 | 48102100 | AGG WEDGE SHLD TYPE B | 9 | TON | $125.00 | $285.59 | $151.74 | $145.70 | |
| 15 | 50102400 | CONC REM | 9.1 | CU YD | $4,000.00 | $3,508.94 | $6,881.32 | $4,186.78 | |
| 16 | 50300255 | CONC SUP-STR | 10.1 | CU YD | $5,750.00 | $3,525.84 | $3,515.34 | $4,813.69 | |
| 17 | 50300260 | BR DECK GROOVING | 1,668 | SQ YD | $8.00 | $12.68 | $10.47 | $8.93 | |
| 18 | 50800205 | REINF BARS, EPOXY CTD | 1,320 | POUND | $4.00 | $4.84 | $3.19 | $3.55 | |
| 19 | 52000110 | PREF JT STRIP SEAL | 67 | FOOT | $315.00 | $293.56 | $317.69 | $327.99 | |
| 20 | 53016002 | DECK SLAB REP (FD-T2) | 10 | SQ YD | $1,650.00 | $1,262.19 | $1,716.82 | $1,591.72 | |
| 21 | 53101002 | BR DECK SCAR 3/4 | 1,760 | SQ YD | $65.00 | $44.76 | $75.56 | $47.63 | |
| 22 | 53101609 | BR DK MIC C OVL 2 1/2 | 1,760 | SQ YD | $100.00 | $140.74 | $109.25 | $154.91 | |
| 23 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,150.00 | $3,918.64 | $1,392.45 | $3,447.83 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $42,500.00 | $23,012.95 | $92,933.65 | $50,203.80 | |
| 25 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $500.00 | $3,478.09 | $853.22 | $1.00 | |
| 26 | 70107025 | CHANGEABLE MESSAGE SN | 70 | CAL DA | $110.00 | $110.25 | $111.99 | $114.24 | |
| 27 | 70300100 | SHORT TERM PAVT MKING | 128 | FOOT | $3.00 | $2.35 | $6.98 | $2.12 | |
| 28 | 70300150 | SHRT TRM PAVT MK REM | 21 | SQ FT | $5.00 | $5.46 | $13.12 | $3.50 | |
| 29 | 78009005 | MOD URETH PM LINE 5 | 1,438 | FOOT | $8.50 | $8.40 | $7.47 | $8.49 | |
| 30 | 78300200 | RAISED REF PVT MK REM | 2 | EACH | $75.00 | $77.92 | $160.12 | $13.98 | |
| 31 | 78300202 | PVT MKG REM WTR BLAST | 599 | SQ FT | $0.0100 | $11.27 | $9.01 | $11.38 |