181Let jobs
$220,104,555Total low bids
—Total estimates
—Low bids vs estimates
Mar 2019 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Mar 8, 2019 | 60N83 | Cook District 1 |
1920.01-BR · | — | $8,661,763 | Lorig Construction Company | 5 | |
| Mar 8, 2019 | 62G98 | Will District 1 |
2018-049-B · | — | $7,870,946 | D. Construction, Inc. | 2 | |
| Mar 8, 2019 | 68B78 | Warren District 4 |
101RS,(102,103)RS-2 · | — | $7,678,838 | Gunther Construction, a div of UCM, Inc. | 3 | |
| Mar 8, 2019 | 61F40 | Will District 1 |
15-00059-00-PV · | — | $7,485,866 | K-Five Construction Corporation & Herlihy Mid-Continent Company | 6 | |
| Mar 8, 2019 | 62G62 | Dupage District 1 |
2018-028-RS-SW · | — | $7,098,580 | R. W. Dunteman Company | 2 | |
| Mar 8, 2019 | 62G47 | Cook District 1 |
2018-016-RS&SW-1 · | — | $7,076,939 | R. W. Dunteman Company | 2 | |
| Mar 8, 2019 | 61F41 | Cook District 1 |
10-00055-00-WR · | — | $6,796,581 | Plote Construction, Inc. | 4 | |
| Mar 8, 2019 | 61F57 | Kane District 1 |
14-00446-00-CH · | — | $6,244,244 | Curran Contracting Company | 3 | |
| Mar 8, 2019 | 64D70 | Winnebago District 2 |
105RS-6 & 105BR-1 · | — | $6,048,894 | Curran Contracting Company | 3 | |
| Mar 8, 2019 | 62F49 | Cook, Will District 1 |
3127(1,2,3&3.1)RS-3 · | — | $5,880,439 | D. Construction, Inc. | 6 | |
| Mar 8, 2019 | 72J97 | Sangamon District 6 |
(84-2)&(84-3)BRR · | — | $5,278,821 | Freesen, a div of UCM, Inc. | 3 | |
| Mar 8, 2019 | 62H68 | Will District 1 |
2018-138-BR · | — | $4,978,000 | ICC Group Inc. | 3 | |
| Mar 8, 2019 | 72H53 | Sangamon, Macoupin District 6 |
(D)RS-13,I-1(P)RS-8,N · | — | $4,687,811 | Truman L. Flatt & Sons Co., Inc. | 3 | |
| Mar 8, 2019 | 60T49 | Cook District 1 |
(86[S,W-1]87Y&88Y)RS-3 · | — | $4,073,824 | Arrow Road Construction Co. | 5 | |
| Mar 8, 2019 | 89713 | Tazewell District 4 |
16-00045-01-SW · | — | $3,914,270 | Illinois Civil Contractors, Inc. | 3 | |
| Mar 8, 2019 | 62G64 | Dupage District 1 |
2018-026-RS-SW · | — | $3,428,345 | K-Five Construction Corporation | 3 | |
| Mar 8, 2019 | 62G80 | Cook District 1 |
2018-010-RS-SW · | — | $3,053,618 | Gallagher Asphalt Corporation | 3 | |
| Mar 8, 2019 | 60P68 | Dupage District 1 |
57-RS-3 · | — | $3,038,712 | K-Five Construction Corporation | 3 | |
| Mar 8, 2019 | 78454 | Pulaski District 9 |
(77-1-3)HB-2 · | — | $2,880,705 | E. T. Simonds Construction Company | 2 | |
| Mar 8, 2019 | 76H15 | Clinton District 8 |
(481,482)RS-3 · | — | $2,828,290 | The Kilian Corporation | 2 | |
| Mar 8, 2019 | 62C14 | Kane District 1 |
5VB-BR · | — | $2,789,910 | Herlihy Mid-Continent Company | 5 | |
| Mar 8, 2019 | 62F54 | Dupage District 1 |
(131&542)R-2-RS-1 · | — | $2,773,288 | R. W. Dunteman Company | 5 | |
| Mar 8, 2019 | 62H32 | Kane District 1 |
2018-084-RS · | — | $2,608,470 | Curran Contracting Company | 4 | |
| Mar 8, 2019 | 62G58 | Lake District 1 |
2018-033-RS-SW · | — | $2,327,169 | J. A. Johnson Paving Company | 2 | |
| Mar 8, 2019 | 76K71 | Greene, Jersey District 8 |
6RS-4 · | — | $2,294,259 | Charles E. Mahoney Co. | 2 | |
| Mar 8, 2019 | 60W87 | Cook District 1 |
2013-040BP · | — | $2,284,150 | Eagle Painting & Maintenance Company, Inc. | 4 | |
| Mar 8, 2019 | 62H43 | Cook District 1 |
2018-104-RS&SW · | — | $2,276,865 | Arrow Road Construction Co. | 4 | |
| Mar 8, 2019 | 62H01 | Dupage District 1 |
2018-041-BD&BJR · | — | $2,269,678 | Herlihy Mid-Continent Company | 5 | |
| Mar 8, 2019 | 76L08 | Clinton District 8 |
(3,4)RS-4 · | — | $2,189,288 | Christ Bros. Asphalt, Inc. | 2 | |
| Mar 8, 2019 | 61F45 | Kane District 1 |
16-00115-02-BR · | — | $2,118,804 | D. Construction, Inc. | 4 | |
| Mar 8, 2019 | 70A99 | Edgar District 5 |
(49X,D,E,F)RS-4 · | — | $2,057,468 | Howell Paving, Inc. | 3 | |
| Mar 8, 2019 | 68D22 | Peoria District 4 |
(1-Z)RS-2;(58-1CS)RS-3;(2CS)RS · | — | $1,972,818 | Advanced Asphalt Company | 2 | |
| Mar 8, 2019 | 97672 | Madison District 8 |
15-00028-01-TL · | — | $1,958,010 | Keller Construction, Inc. | 4 | |
| Mar 8, 2019 | 74835 | Macon District 7 |
47N · | — | $1,930,680 | Illinois Valley Paving, a div of UCM, Inc. | 1 | |
| Mar 8, 2019 | 85671 | Rock Island District 2 |
17-00374-00-PP · | — | $1,844,417 | Brandt Construction Co. | 2 | |
| Mar 8, 2019 | 60R68 | Lake District 1 |
12R-1HB-1-BR · | — | $1,777,994 | Areatha Construction Co., Inc. | 3 | |
| Mar 8, 2019 | 62F66 | Cook District 1 |
2017-037-RS · | — | $1,771,483 | Arrow Road Construction Co. | 5 | |
| Mar 8, 2019 | 61F47 | Lake District 1 |
17-00103-00-PV · | — | $1,668,129 | A Lamp Concrete Contractors, Inc. | 1 | |
| Mar 8, 2019 | 64J41 | Boone, Winnebago District 2 |
(129,130)RS · | — | $1,641,800 | William Charles Construction Company, LLC | 3 | |
| Mar 8, 2019 | 97683 | Madison District 8 |
15-00113-03-BR · | — | $1,597,542 | Keller Construction, Inc. | 5 | |
| Mar 8, 2019 | 64M94 | Whiteside District 2 |
(195-2)RS-1 · | — | $1,593,387 | Martin & Company Excavating | 1 | |
| Mar 8, 2019 | 61F49 | Cook District 1 |
16-00053-00-RS · | — | $1,588,343 | A Lamp Concrete Contractors, Inc. | 5 | |
| Mar 8, 2019 | 62H41 | Cook District 1 |
2018-106-I · | — | $1,424,366 | MAT Construction Leasing, Inc. | 3 | |
| Mar 8, 2019 | 68E28 | Woodford District 4 |
113RS-2 · | — | $1,373,783 | Advanced Asphalt Company | 2 | |
| Mar 8, 2019 | 70D15 | Champaign District 5 |
(14-HB)BDR · | — | $1,356,025 | Stark Excavating, Inc. | 2 | |
| Mar 8, 2019 | 62H04 | Dupage District 1 |
2018-044-BD&BJR · | — | $1,330,256 | Martam Construction Incorporated | 5 | |
| Mar 8, 2019 | 62F35 | Mchenry District 1 |
29VB-BR(17) · | — | $1,257,790 | Sjostrom & Sons, Inc. | 5 | |
| Mar 8, 2019 | 62H24 | Dupage District 1 |
2018-092-RS · | — | $1,241,694 | Geneva Construction Company | 1 | |
| Mar 8, 2019 | 76M10 | Monroe District 8 |
67-(1,2,3)RS-1 · | — | $1,221,692 | The Kilian Corporation | 2 | |
| Mar 8, 2019 | 61F54 | Cook District 1 |
18-00091-00-RS · | — | $1,214,960 | Plote Construction, Inc. | 5 | |
| Mar 8, 2019 | 60M72 | Cook District 1 |
1314.1-I · | — | $1,199,708 | Rausch Infrastructure, LLC | 7 | |
| Mar 8, 2019 | 66J11 | Iroquois District 3 |
(123)SFY · | — | $1,187,960 | Iroquois Paving Corporation | 1 | |
| Mar 8, 2019 | 97681 | Marion District 8 |
15-00126-00-RS · | — | $1,158,465 | Howell Paving, Inc. | 1 | |
| Mar 8, 2019 | 95821 | Cumberland District 7 |
14-00076-00-RS · | — | $1,151,588 | Howell Paving, Inc. | 2 | |
| Mar 8, 2019 | 46470 | Various District 2 |
D-2 OVD SIN STR REPL 18-32 · | — | $1,139,658 | COLLINS & HERMANN, INC. | 2 | |
| Mar 8, 2019 | 61F62 | Dupage District 1 |
16-00079-00-PV · | — | $1,120,972 | Schroeder Asphalt Services, Inc. | 4 | |
| Mar 8, 2019 | 97685 | St. Clair District 8 |
15-00253-13-RS · | — | $1,097,760 | The Kilian Corporation | 2 | |
| Mar 8, 2019 | 62G21 | Cook District 1 |
2018-007-RS-1 · | — | $1,035,977 | MAT Construction Leasing, Inc. | 4 | |
| Mar 8, 2019 | 62G48 | Mchenry District 1 |
2018-056-DR-1 · | — | $1,033,397 | Alliance Contractors, Inc. | 3 | |
| Mar 8, 2019 | 68D10 | Knox District 4 |
(111C-5)CR · | — | $979,988 | Kinney Contractors, Inc. | 6 | |
| Mar 8, 2019 | 60R69 | Cook District 1 |
584-B-BR(11) · | — | $973,368 | Martam Construction Incorporated | 4 | |
| Mar 8, 2019 | 61F60 | Cook District 1 |
14-00041-00-BT · | — | $964,375 | K-Five Construction Corporation | 3 | |
| Mar 8, 2019 | 62G90 | Lake District 1 |
2018-058-DNR-PK · | — | $953,418 | Alliance Contractors, Inc. | 7 | |
| Mar 8, 2019 | 61F44 | Will District 1 |
15-16108-01-BR · | — | $945,717 | D. Construction, Inc. | 2 | |
| Mar 8, 2019 | 68E68 | Tazewell, Marshall, Mason District 4 |
D4 BRIDGE WASHING 2019 · | — | $881,690 | All States Painting, Inc. | 1 | |
| Mar 8, 2019 | 74884 | Macon District 7 |
D7 BRIDGE REPAIRS 2019-1 · | — | $852,653 | Freesen, a div of UCM, Inc. | 3 | |
| Mar 8, 2019 | 62H35 | Will District 1 |
2018-112-I · | — | $847,500 | Lakes & Rivers Contracting, Inc. | 3 | |
| Mar 8, 2019 | 74885 | Clark District 7 |
D7 BRIDGE DECK REPAIRS 2019-2 · | — | $843,262 | Sangamo Construction Company | 1 | |
| Mar 8, 2019 | 62G67 | Cook District 1 |
2018-023-RS-SW · | — | $827,549 | K-Five Construction Corporation | 4 | |
| Mar 8, 2019 | 61F59 | Kane, Dupage District 1 |
18-00322-00-TL · | — | $826,220 | H & H Electric Co. | 2 | |
| Mar 8, 2019 | 87622 | Livingston District 3 |
12-00062-02-RS · | — | $824,223 | Kankakee Valley Construction Company, Inc. | 2 | |
| Mar 8, 2019 | 76M07 | Clinton District 8 |
14-1PP-DR-1 · | — | $823,830 | Keeley & Sons, Inc. | 3 | |
| Mar 8, 2019 | 64K59 | Jodaviess District 2 |
29RS-7 · | — | $808,424 | Civil Constructors, Inc. | 1 | |
| Mar 8, 2019 | 68E20 | Peoria District 4 |
D4 ITS 2018 · | — | $790,000 | Oberlander Electric Co. | 2 | |
| Mar 8, 2019 | 70D27 | Vermilion District 5 |
(48X-2)BDR · | — | $737,000 | Big O Services, LLC | 3 | |
| Mar 8, 2019 | 68C63 | Tazewell District 4 |
8[C-1]CR · | — | $734,500 | Kinney Contractors, Inc. | 5 | |
| Mar 8, 2019 | 99608 | Jackson District 9 |
16-00175-00-SP · | — | $721,679 | E. T. Simonds Construction Company | 2 | |
| Mar 8, 2019 | 66J54 | Lasalle District 3 |
(1,1Z)CJS,I-2 · | — | $692,705 | Asphalt Stone Company | 3 | |
| Mar 8, 2019 | 68E64 | Various District 4 |
D4 GUARDRAIL REPAIRS 2019-MCHD · | — | $682,239 | Northern Contracting, Inc. | 1 | |
| Mar 8, 2019 | 62H07 | Cook District 1 |
2018-040-RS · | — | $673,920 | Plote Construction, Inc. | 4 | |
| Mar 8, 2019 | 85678 | Henry District 2 |
17-00108-00-RS · | — | $656,136 | Advanced Asphalt Company | 3 | |
| Mar 8, 2019 | 85677 | Ogle District 2 |
17-00314-00-RS · | — | $629,098 | Martin & Company Excavating | 2 | |
| Mar 8, 2019 | 74879 | Shelby District 7 |
12(W-1 RS-6) · | — | $547,924 | Howell Paving, Inc. | 1 | |
| Mar 8, 2019 | 66J53 | Livingston District 3 |
(113,114)I · | — | $537,261 | Beniach Construction Co., Inc. | 4 | |
| Mar 8, 2019 | 72K73 | Logan District 6 |
(54-4,54-10)BP-1,(118)BP · | — | $526,000 | Venus Painting Co. | 4 | |
| Mar 8, 2019 | 74882 | Fayette District 7 |
D7 PATCHING 2019-3 · | — | $523,215 | G. M. Sipes Construction, Inc. | 3 | |
| Mar 8, 2019 | 85673 | Winnebago District 2 |
14-00042-00-BT · | — | $521,454 | N-Trak Group LLC | 4 | |
| Mar 8, 2019 | 62F37 | Cook District 1 |
2017-023I · | — | $513,202 | D. Construction, Inc. | 6 | |
| Mar 8, 2019 | 97680 | Madison District 8 |
16-00150-02-RS · | — | $511,907 | Stutz Excavating, Inc. | 5 | |
| Mar 8, 2019 | 78662 | Williamson District 9 |
D9 BRIDGE REPAIR 2019-6 · | — | $497,797 | Samron Midwest Contracting, Inc. | 4 | |
| Mar 8, 2019 | 85676 | Lee District 2 |
18-00338-00-RS · | — | $492,578 | Martin & Company Excavating | 2 | |
| Mar 8, 2019 | 95845 | Wayne District 7 |
11-04130-00-BR · | — | $490,950 | Allendale Gravel Co., Inc. | 5 | |
| Mar 8, 2019 | 70D58 | Champaign, Vermilion District 5 |
D5 BRIDGE PAINTING 2019-3 · | — | $486,250 | ERA-Valdivia Contractors, Inc. | 3 | |
| Mar 8, 2019 | 76L67 | St. Clair District 8 |
29-1-N-TS-3 · | — | $479,750 | DMS Contracting, Inc. | 4 | |
| Mar 8, 2019 | 70C97 | Vermilion District 5 |
(48X-3)BR-2 · | — | $478,444 | Big O Services, LLC | 3 | |
| Mar 8, 2019 | 62G50 | Cook District 1 |
(511&525)B-R-1 · | — | $474,229 | MYS, Incorporated | 3 | |
| Mar 8, 2019 | 99614 | Jefferson District 9 |
11-00205-00-RS · | — | $465,785 | E. T. Simonds Construction Company | 2 | |
| Mar 8, 2019 | 76M01 | Various District 8 |
DIST 8 RESURFACING 2019-1 · | — | $460,617 | DMS Contracting, Inc. | 2 | |
| Mar 8, 2019 | 64N29 | Henry District 2 |
D2 BDR 2019-5 · | — | $449,103 | Civil Constructors, Inc. | 3 | |
| Mar 8, 2019 | 64N17 | Various District 2 |
D2 GR (SOUTH) 2019 · | — | $444,125 | Northern Contracting, Inc. | 3 |
1–100 of 181Next ›
Source: IDOT Transportation Bulletin "Unit Price Tabulation of Bids" for each letting. Totals are as read; IDOT does not publish an engineer's estimate there, so estimate columns stay blank. Bid Potato backfills the last two years. Confirm against IDOT's As Accepted tabulation.