14-00042-00-BT
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | N-Trak Group LLC Low bidder | $521,454 | ||
| 2 | William Charles Construction Company, LLC | $588,661 | +12.9% | |
| 3 | Stenstrom Excavation & Blacktop, Inc. | $704,595 | +35.1% | |
| 4 | Fischer Excavating, Inc. | $779,020 | +49.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 N-Trak Group LLC | #2 William Charles… | #3 Stenstrom Excav… | #4 Fischer Excavat… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | XX000970 | PARKWAY RESTORATION | 1 | L SUM | $9,250.00 | $29,182.07 | $46,727.00 | $45,250.00 | |
| 2 | XX006821 | CONC TRUCK WASHOUT | 1 | L SUM | $251.61 | $0.0100 | $908.00 | $500.00 | |
| 3 | XX008675 | PAVT REM & REPL | 131 | SQ YD | $62.27 | $169.91 | $110.55 | $14.00 | |
| 4 | X0322936 | REMOV EX FLAR END SEC | 7 | EACH | $107.28 | $270.61 | $351.00 | $200.00 | |
| 5 | X0324450 | SEG CONC BLK WALL, SP | 505 | SQ FT | $39.79 | $54.11 | $50.65 | $49.00 | |
| 6 | X0327036 | BIKE PATH REM | 11 | SQ YD | $10.99 | $3.47 | $285.65 | $14.00 | |
| 7 | X0327149 | RELO BENCH | 1 | EACH | $1,240.73 | $1,649.30 | $820.75 | $950.00 | |
| 8 | X0327979 | PAVMT MRKG REM GRIND | 495 | SQ FT | $1.20 | $1.85 | $1.95 | $1.20 | |
| 9 | X3400004 | RETAINING WALL REMOV | 23 | FOOT | $15.28 | $86.10 | $125.50 | $23.00 | |
| 10 | X4401198 | HMA SURF REM VAR DP | 535 | SQ YD | $6.00 | $17.84 | $11.00 | $21.00 | |
| 11 | X4402815 | ISLAND PAVT RM & REPL | 846 | SQ FT | $14.80 | $10.43 | $13.00 | $25.00 | |
| 12 | X5091765 | PIPE HANDRAIL SPL | 166 | FOOT | $261.59 | $261.49 | $258.25 | $332.25 | |
| 13 | X6024242 | INLETS SPL N1 | 1 | EACH | $2,480.10 | $1,905.57 | $1,954.00 | $3,000.00 | |
| 14 | X6024244 | INLETS SPL N2 | 4 | EACH | $2,480.09 | $1,905.57 | $1,954.00 | $3,900.00 | |
| 15 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $9,250.00 | $9,246.44 | $13,055.00 | $9,250.00 | |
| 16 | X8140115 | HANDHOLE TO BE ADJUST | 4 | EACH | $1,502.00 | $1,190.04 | $1,552.00 | $1,502.00 | |
| 17 | Z0001110 | GAS VALVE ADJUSTED | 4 | EACH | $36.49 | $268.74 | $500.00 | $1,500.00 | |
| 18 | Z0007126 | HANDRAIL REMOVAL | 33 | FOOT | $10.65 | $23.25 | $21.25 | $37.00 | |
| 19 | 20101350 | TREE PRUN OVER 10 | 4 | EACH | $582.24 | $469.82 | $258.25 | $470.00 | |
| 20 | 20200100 | EARTH EXCAVATION | 1,230 | CU YD | $24.50 | $43.90 | $26.50 | $35.00 | |
| 21 | 20400800 | FURNISHED EXCAVATION | 150 | CU YD | $0.0100 | $60.00 | $36.50 | $25.00 | |
| 22 | 25100630 | EROSION CONTR BLANKET | 10,940 | SQ YD | $1.20 | $0.9500 | $0.9800 | $0.9500 | |
| 23 | 28000400 | PERIMETER EROS BAR | 5,686 | FOOT | $2.44 | $1.50 | $1.55 | $1.50 | |
| 24 | 28000500 | INLET & PIPE PROTECT | 20 | EACH | $202.57 | $119.95 | $123.95 | $120.00 | |
| 25 | 35101800 | AGG BASE CSE B 6 | 5,790 | SQ YD | $7.36 | $6.61 | $7.85 | $8.00 | |
| 26 | 35800100 | PREPARATION OF BASE | 388 | SQ YD | $3.27 | $3.03 | $34.75 | $10.00 | |
| 27 | 35800200 | AGG BASE REPAIR | 44 | TON | $18.15 | $10.83 | $60.50 | $25.00 | |
| 28 | 40600275 | BIT MATLS PR CT | 21,250 | POUND | $0.1500 | $0.0100 | $0.0100 | $0.0100 | |
| 29 | 40603335 | HMA SC "D" N50 | 60 | TON | $88.00 | $138.00 | $139.40 | $135.00 | |
| 30 | 40603415 | HMA SC IL-9.5FG N50 | 995 | TON | $88.00 | $80.27 | $98.10 | $95.00 | |
| 31 | 42400200 | PC CONC SIDEWALK 5 | 4,050 | SQ FT | $7.82 | $10.71 | $7.15 | $11.00 | |
| 32 | 42400800 | DETECTABLE WARNINGS | 870 | SQ FT | $17.24 | $17.99 | $29.00 | $28.00 | |
| 33 | 44000161 | HMA SURF REM 3 | 388 | SQ YD | $6.00 | $3.73 | $10.50 | $16.00 | |
| 34 | 44000200 | DRIVE PAVEMENT REM | 291 | SQ YD | $6.49 | $4.06 | $20.00 | $17.00 | |
| 35 | 44000400 | GUTTER REM | 15 | FOOT | $16.32 | $9.26 | $31.25 | $10.00 | |
| 36 | 44000500 | COMB CURB GUTTER REM | 583 | FOOT | $7.45 | $16.50 | $10.75 | $10.00 | |
| 37 | 50105220 | PIPE CULVERT REMOV | 140 | FOOT | $8.92 | $7.71 | $20.45 | $28.00 | |
| 38 | 542C5485 | P CUL CL C 1 EQRS 30 | 16 | FOOT | $88.28 | $139.27 | $208.00 | $145.00 | |
| 39 | 54213657 | PRC FLAR END SEC 12 | 7 | EACH | $792.89 | $702.88 | $758.00 | $700.00 | |
| 40 | 54213660 | PRC FLAR END SEC 15 | 1 | EACH | $856.74 | $734.87 | $843.00 | $795.00 | |
| 41 | 54214305 | END SEC EQV R-S 30 | 4 | EACH | $681.69 | $515.94 | $1,284.50 | $880.00 | |
| 42 | 550A0050 | STORM SEW CL A 1 12 | 142 | FOOT | $46.81 | $39.67 | $67.35 | $75.00 | |
| 43 | 550A0070 | STORM SEW CL A 1 15 | 61 | FOOT | $46.79 | $42.86 | $85.95 | $82.00 | |
| 44 | 550A0090 | STORM SEW CL A 1 18 | 269 | FOOT | $53.88 | $42.14 | $70.25 | $85.00 | |
| 45 | 56400400 | FIRE HYDNTS RELOCATED | 1 | EACH | $2,438.90 | $4,684.78 | $6,825.00 | $5,555.00 | |
| 46 | 60265700 | VV ADJUST | 2 | EACH | $405.73 | $268.74 | $435.00 | $955.00 | |
| 47 | 60603500 | COMB CC&G TB6.06 | 41 | FOOT | $47.31 | $33.65 | $31.00 | $38.00 | |
| 48 | 60603800 | COMB CC&G TB6.12 | 36 | FOOT | $33.06 | $38.32 | $34.00 | $43.00 | |
| 49 | 60604400 | COMB CC&G TB6.18 | 426 | FOOT | $33.37 | $32.31 | $35.75 | $36.00 | |
| 50 | 60605000 | COMB CC&G TB6.24 | 64 | FOOT | $36.32 | $37.18 | $39.15 | $45.00 | |
| 51 | 66900200 | NON SPL WASTE DISPOSL | 100 | CU YD | $0.0100 | $0.0100 | $78.95 | $82.00 | |
| 52 | 66900205 | SPL WASTE DISPOSAL | 100 | CU YD | $0.0100 | $0.0100 | $81.92 | $86.00 | |
| 53 | 66900210 | HAZARD WASTE DISPOSAL | 50 | CU YD | $0.0100 | $0.0100 | $731.80 | $1,150.00 | |
| 54 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,120.00 | $1,219.53 | $1,259.00 | $1,220.00 | |
| 55 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $6,000.00 | $2,199.15 | $2,271.00 | $1,000.00 | |
| 56 | 66901002 | ON-SITE MON REG SUB | 40 | CAL DA | $0.0100 | $0.0100 | $619.75 | $600.00 | |
| 57 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,200.00 | $999.61 | $1,032.57 | $2,200.00 | |
| 58 | 67100100 | MOBILIZATION | 1 | L SUM | $30,000.00 | $35,500.00 | $16,291.00 | $45,000.00 | |
| 59 | 72000100 | SIGN PANEL T1 | 179 | SQ FT | $25.00 | $24.99 | $25.82 | $22.10 | |
| 60 | 72900100 | METAL POST TY A | 646 | FOOT | $10.00 | $10.00 | $10.33 | $11.35 | |
| 61 | 78000200 | THPL PVT MK LINE 4 | 1,302 | FOOT | $0.9000 | $0.6200 | $1.03 | $0.6200 | |
| 62 | 78000400 | THPL PVT MK LINE 6 | 1,336 | FOOT | $1.35 | $0.9500 | $1.55 | $0.9500 | |
| 63 | 78000500 | THPL PVT MK LINE 8 | 37 | FOOT | $1.80 | $1.25 | $2.07 | $1.25 | |
| 64 | 78000600 | THPL PVT MK LINE 12 | 1,854 | FOOT | $2.70 | $1.95 | $3.10 | $1.95 | |
| 65 | 78000650 | THPL PVT MK LINE 24 | 265 | FOOT | $5.40 | $4.25 | $6.20 | $4.25 | |
| 66 | 78001110 | PAINT PVT MK LINE 4 | 90 | FOOT | $2.50 | $5.00 | $2.07 | $5.00 | |
| 67 | 78001150 | PAINT PVT MK LINE 12 | 9 | FOOT | $7.50 | $10.00 | $6.20 | $10.00 | |
| 68 | 81028360 | UNDRGRD C PVC 2 1/2 | 22 | FOOT | $28.50 | $78.55 | $29.43 | $28.50 | |
| 69 | 87301215 | ELCBL C SIGNAL 14 2C | 501 | FOOT | $1.97 | $2.28 | $2.03 | $1.97 | |
| 70 | 87301235 | ELCBL C SIGNAL 14 4C | 511 | FOOT | $2.33 | $2.56 | $2.41 | $2.33 | |
| 71 | 87601100 | PED P-B POST GALVS T1 | 2 | EACH | $887.00 | $1,466.69 | $915.97 | $887.00 | |
| 72 | 87900200 | DRILL EX HANDHOLE | 2 | EACH | $230.00 | $303.50 | $237.51 | $230.00 | |
| 73 | 88102825 | PED SH P LED 1F BM CT | 2 | EACH | $671.00 | $761.42 | $692.92 | $671.00 | |
| 74 | 88102845 | PED SH P LED 2F BM CT | 1 | EACH | $1,502.00 | $1,471.32 | $1,551.05 | $1,502.00 | |
| 75 | 88800100 | PED PUSH-BUTTON | 4 | EACH | $442.00 | $348.76 | $456.44 | $442.00 | |
| 76 | 89502200 | MOD EX CONTR | 1 | EACH | $3,000.00 | $2,828.52 | $3,097.97 | $3,000.00 |