2017-023I
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $513,202 | ||
| 2 | ERA-Valdivia Contractors, Inc. | $517,423 | +0.8% | |
| 3 | Path Construction Company, Inc. | $623,598 | +21.5% | |
| 4 | Alliance Contractors, Inc. | $702,586 | +36.9% | |
| 5 | Vixen Construction, Inc. | $711,104 | +38.6% | |
| 6 | Sumit Construction Co., Inc. | $829,592 | +61.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 ERA-Valdivia Co… | #3 Path Constructi… | #4 Alliance Contra… | #5 Vixen Construct… | #6 Sumit Construct… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327980 | PAVMT MRKG REM WTR BL | 324 | SQ FT | $8.80 | $7.70 | $10.00 | $8.00 | $8.40 | $10.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $22,962.50 | $16,500.00 | $20,000.00 | $10,800.00 | $11,340.00 | $60,000.00 | |
| 3 | X7030005 | TEMP PAVT MKING REMOV | 2,866 | SQ FT | $1.00 | $0.2300 | $2.00 | $0.3000 | $0.3500 | $1.00 | |
| 4 | Z0001800 | APPROACH SL REP (PD) | 7 | SQ YD | $500.00 | $650.00 | $550.00 | $1,800.00 | $896.00 | $6,000.00 | |
| 5 | Z0012754 | STR REP CON DP = < 5 | 285 | SQ FT | $120.00 | $139.00 | $170.00 | $197.60 | $194.00 | $200.00 | |
| 6 | Z0012755 | STR REP CON DP OVER 5 | 310 | SQ FT | $160.00 | $179.00 | $200.00 | $211.60 | $208.00 | $220.00 | |
| 7 | Z0016200 | DECK SLAB REP (PART) | 3 | SQ YD | $1,200.00 | $550.00 | $1,200.00 | $1,800.00 | $1,017.00 | $1,300.00 | |
| 8 | Z0030850 | TEMP INFO SIGNING | 154.2 | SQ FT | $16.50 | $16.50 | $15.00 | $15.00 | $15.75 | $16.00 | |
| 9 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $7,392.00 | $5,500.00 | $15,000.00 | $5,000.00 | $12,500.00 | $10,000.00 | |
| 10 | 50102400 | CONC REM | 52.3 | CU YD | $1,500.00 | $1,675.00 | $1,500.00 | $2,300.00 | $1,190.00 | $2,200.00 | |
| 11 | 50300255 | CONC SUP-STR | 52.3 | CU YD | $2,100.00 | $1,950.00 | $2,650.00 | $5,745.00 | $3,740.00 | $3,000.00 | |
| 12 | 50800205 | REINF BARS, EPOXY CTD | 7,180 | POUND | $2.80 | $2.85 | $3.00 | $1.50 | $1.85 | $6.00 | |
| 13 | 50800515 | BAR SPLICERS | 72 | EACH | $53.38 | $58.55 | $55.00 | $25.00 | $25.60 | $40.00 | |
| 14 | 52000110 | PREF JT STRIP SEAL | 344 | FOOT | $180.00 | $260.00 | $280.00 | $50.00 | $420.00 | $500.00 | |
| 15 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,500.00 | $1,200.00 | $3,500.00 | $500.00 | $3,000.00 | $2,000.00 | |
| 16 | 67100100 | MOBILIZATION | 1 | L SUM | $30,500.00 | $18,000.00 | $36,000.00 | $38,535.00 | $41,000.00 | $10,000.00 | |
| 17 | 70300904 | PAVT MARK TAPE T4 4 | 8,598 | FOOT | $0.9900 | $1.10 | $1.00 | $1.00 | $1.05 | $1.20 | |
| 18 | 70300906 | PAVT MARK TAPE T4 6 | 55 | FOOT | $1.65 | $1.80 | $2.00 | $2.00 | $2.10 | $2.20 | |
| 19 | 70400100 | TEMP CONC BARRIER | 775 | FOOT | $30.00 | $29.25 | $41.00 | $27.70 | $46.00 | $40.00 | |
| 20 | 70400200 | REL TEMP CONC BARRIER | 675 | FOOT | $15.00 | $6.90 | $9.00 | $6.00 | $28.00 | $12.00 | |
| 21 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $3,850.00 | $4,900.00 | $3,500.00 | $3,500.00 | $3,600.00 | $5,000.00 | |
| 22 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $1,650.00 | $2,750.00 | $750.00 | $750.00 | $780.00 | $2,500.00 | |
| 23 | 78000200 | THPL PVT MK LINE 4 | 312 | FOOT | $6.77 | $8.80 | $12.00 | $8.00 | $3.70 | $4.00 | |
| 24 | 78003110 | PREF PL PM TB LINE 4 | 658 | FOOT | $4.13 | $6.50 | $7.00 | $5.50 | $2.65 | $3.00 | |
| 25 | 78200011 | BARR WALL REF TYPE C | 14 | EACH | $16.50 | $22.00 | $10.00 | $15.00 | $15.75 | $17.00 |