2017-037-RS
- Let date
- Friday, March 8, 2019
- Contract
- 62F66 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- 1.91 miles of HMA resurfcing, pavement patching, removal and replacement of curb and gutter, sidewalk removal and replacement and placement of thermoplastic markings along Avondale Avenue from Ogallah Avenue to Bryn Mawr Avenue in Chicago.
- Classification
- ·
- Project number
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Arrow Road Construction Co. Low bidder | $1,771,483 | ||
| 2 | Builders Paving, LLC | $1,825,500 | +3.0% | |
| 3 | Plote Construction, Inc. | $1,841,487 | +4.0% | |
| 4 | J. A. Johnson Paving Company | $1,855,755 | +4.8% | |
| 5 | Bigane Paving Company | $2,042,416 | +15.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Arrow Road Cons… | #2 Builders Paving… | #3 Plote Construct… | #4 J. A. Johnson P… | #5 Bigane Paving C… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | K0029618 | WEED CONT BROADLF TRF | 1 | GALLON | $1,600.00 | $350.00 | $162.00 | $600.00 | $1,600.00 | |
| 2 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $8,745.00 | $10,000.00 | $6,250.00 | $6,000.00 | $27,000.00 | |
| 3 | X0327036 | BIKE PATH REM | 65 | SQ YD | $12.00 | $32.96 | $40.00 | $12.00 | $32.00 | |
| 4 | X4240800 | DETECTABLE WARN SPL | 423 | SQ FT | $32.00 | $32.96 | $32.00 | $32.00 | $30.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 1,600 | SQ YD | $2.30 | $6.00 | $1.00 | $3.50 | $12.00 | |
| 6 | X5537800 | SS CLEANED 12 | 350 | FOOT | $3.00 | $3.00 | $2.50 | $2.50 | $3.00 | |
| 7 | X6030310 | FR & LIDS ADJUST SPL | 67 | EACH | $688.00 | $650.00 | $650.00 | $650.00 | $650.00 | |
| 8 | X7030005 | TEMP PAVT MKING REMOV | 5,198 | SQ FT | $0.3500 | $0.3000 | $0.3000 | $0.0100 | $0.5000 | |
| 9 | Z0004562 | COMB C C&G REM & REPL | 15,089 | FOOT | $27.00 | $27.81 | $27.00 | $27.00 | $26.50 | |
| 10 | Z0018500 | DRAINAGE STR CLEANED | 65 | EACH | $350.00 | $360.50 | $350.00 | $350.00 | $315.00 | |
| 11 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $18.00 | $18.00 | $18.00 | $18.00 | $15.00 | |
| 12 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $7,875.00 | $10,000.00 | $6,500.00 | $5,000.00 | $5,000.00 | |
| 13 | Z0064800 | SELECTIVE CLEARING | 5 | UNIT | $440.00 | $440.00 | $100.00 | $440.00 | $335.00 | |
| 14 | 20100110 | TREE REMOV 6-15 | 166 | UNIT | $18.00 | $18.00 | $40.00 | $18.00 | $27.00 | |
| 15 | 20100210 | TREE REMOV OVER 15 | 30 | UNIT | $90.00 | $90.00 | $40.00 | $90.00 | $40.00 | |
| 16 | 20101350 | TREE PRUN OVER 10 | 16 | EACH | $120.00 | $120.00 | $90.00 | $120.00 | $195.00 | |
| 17 | 20200100 | EARTH EXCAVATION | 44 | CU YD | $55.00 | $56.65 | $55.00 | $55.00 | $55.00 | |
| 18 | 21101615 | TOPSOIL F & P 4 | 2,600 | SQ YD | $2.00 | $4.00 | $6.40 | $6.98 | $7.50 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 49 | POUND | $8.00 | $4.20 | $3.00 | $4.00 | $3.00 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 49 | POUND | $8.00 | $4.20 | $3.00 | $4.00 | $3.00 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 49 | POUND | $8.00 | $4.20 | $3.00 | $4.00 | $3.00 | |
| 22 | 25100115 | MULCH METHOD 2 | 0.2 | ACRE | $2,000.00 | $14,520.00 | $2,200.00 | $20,950.00 | $6,000.00 | |
| 23 | 25200100 | SODDING | 2,600 | SQ YD | $12.00 | $4.00 | $8.00 | $11.00 | $14.25 | |
| 24 | 25200200 | SUPPLE WATERING | 65 | UNIT | $85.00 | $134.77 | $0.0100 | $25.00 | $50.00 | |
| 25 | 35501308 | HMA BASE CSE 6 | 100 | SQ YD | $70.45 | $60.00 | $71.00 | $82.50 | $133.00 | |
| 26 | 35501316 | HMA BASE CSE 8 | 20 | SQ YD | $100.75 | $80.00 | $96.00 | $109.50 | $133.00 | |
| 27 | 40600290 | BIT MATLS TACK CT | 36,905 | POUND | $0.7400 | $0.0100 | $0.0100 | $0.0100 | $0.7000 | |
| 28 | 40600400 | MIX CR JTS FLANGEWYS | 82 | TON | $185.00 | $300.00 | $100.00 | $300.00 | $200.00 | |
| 29 | 40600827 | P LB MM IL-4.75 N50 | 2,232 | TON | $92.40 | $78.00 | $90.00 | $85.00 | $113.00 | |
| 30 | 40600982 | HMA SURF REM BUTT JT | 573 | SQ YD | $10.85 | $24.00 | $15.00 | $1.00 | $16.00 | |
| 31 | 40601005 | HMA REPL OVER PATCH | 417 | TON | $50.00 | $110.00 | $132.00 | $47.25 | $92.00 | |
| 32 | 40603335 | HMA SC "D" N50 | 4,545 | TON | $75.05 | $65.00 | $72.00 | $75.00 | $88.00 | |
| 33 | 42001300 | PROTECTIVE COAT | 4,047 | SQ YD | $0.7500 | $0.7700 | $0.7500 | $0.7500 | $0.7500 | |
| 34 | 42300200 | PCC DRIVEWAY PAVT 6 | 150 | SQ YD | $75.00 | $77.25 | $75.00 | $75.00 | $72.00 | |
| 35 | 42300400 | PCC DRIVEWAY PAVT 8 | 20 | SQ YD | $85.00 | $87.55 | $85.00 | $85.00 | $85.00 | |
| 36 | 42400200 | PC CONC SIDEWALK 5 | 3,384 | SQ FT | $6.25 | $6.44 | $6.25 | $6.25 | $6.25 | |
| 37 | 42400410 | PC CONC SIDEWALK 8 | 718 | SQ FT | $7.50 | $7.73 | $7.50 | $8.50 | $9.00 | |
| 38 | 44000100 | PAVEMENT REM | 32 | SQ YD | $30.00 | $20.60 | $20.00 | $12.00 | $20.00 | |
| 39 | 44000158 | HMA SURF REM 2 1/4 | 54,101 | SQ YD | $2.45 | $4.00 | $2.60 | $3.50 | $4.00 | |
| 40 | 44000200 | DRIVE PAVEMENT REM | 290 | SQ YD | $18.00 | $30.00 | $18.00 | $18.00 | $18.00 | |
| 41 | 44000600 | SIDEWALK REM | 3,812 | SQ FT | $2.00 | $2.06 | $2.00 | $2.00 | $2.00 | |
| 42 | 44002216 | HMA RM OV PATCH 4 | 1,860 | SQ YD | $5.00 | $12.80 | $12.00 | $17.50 | $6.40 | |
| 43 | 44201741 | CL D PATCH T2 8 | 705 | SQ YD | $76.00 | $70.00 | $80.00 | $72.00 | $65.00 | |
| 44 | 44201745 | CL D PATCH T3 8 | 374 | SQ YD | $73.00 | $60.00 | $75.00 | $60.50 | $65.00 | |
| 45 | 44201747 | CL D PATCH T4 8 | 338 | SQ YD | $70.00 | $60.00 | $75.00 | $60.50 | $65.00 | |
| 46 | 44201765 | CL D PATCH T2 10 | 100 | SQ YD | $96.00 | $85.00 | $115.00 | $100.00 | $75.00 | |
| 47 | 44201769 | CL D PATCH T3 10 | 80 | SQ YD | $90.00 | $85.00 | $100.00 | $72.50 | $75.00 | |
| 48 | 44201771 | CL D PATCH T4 10 | 54 | SQ YD | $90.00 | $80.00 | $100.00 | $72.50 | $75.00 | |
| 49 | 60252800 | CB RECONST | 10 | EACH | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 | |
| 50 | 60255500 | MAN ADJUST | 2 | EACH | $450.00 | $450.00 | $450.00 | $450.00 | $450.00 | |
| 51 | 60257900 | MAN RECONST | 2 | EACH | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 | |
| 52 | 60300105 | FR & GRATES ADJUST | 10 | EACH | $400.00 | $400.00 | $400.00 | $400.00 | $400.00 | |
| 53 | 60300305 | FR & LIDS ADJUST | 65 | EACH | $400.00 | $400.00 | $400.00 | $400.00 | $350.00 | |
| 54 | 60404940 | FR & GRATES T23 | 4 | EACH | $415.00 | $415.00 | $415.00 | $415.00 | $415.00 | |
| 55 | 60406000 | FR & LIDS T1 OL | 40 | EACH | $315.00 | $315.00 | $315.00 | $315.00 | $315.00 | |
| 56 | 60406100 | FR & LIDS T1 CL | 35 | EACH | $315.00 | $315.00 | $315.00 | $315.00 | $315.00 | |
| 57 | 66900200 | NON SPL WASTE DISPOSL | 44 | CU YD | $210.00 | $90.00 | $101.00 | $105.00 | $135.00 | |
| 58 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,500.00 | $1,500.00 | $1,450.00 | $1,800.00 | $1,800.00 | |
| 59 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,000.00 | $3,000.00 | $2,100.00 | $3,300.00 | $3,300.00 | |
| 60 | 66901002 | ON-SITE MON REG SUB | 15 | CAL DA | $700.00 | $525.00 | $500.00 | $680.00 | $600.00 | |
| 61 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $1,000.00 | $2,000.00 | $1,800.00 | $900.00 | $900.00 | |
| 62 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,500.00 | $2,500.00 | $4,300.00 | $2,500.00 | $3,000.00 | |
| 63 | 67100100 | MOBILIZATION | 1 | L SUM | $48,915.00 | $109,000.00 | $110,490.00 | $110,000.00 | $104,200.00 | |
| 64 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $67,450.00 | $10,099.50 | $61,000.00 | $56,899.97 | $100.00 | |
| 65 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $1.00 | $100.00 | $100.00 | $1.00 | $24,000.00 | |
| 66 | 70102634 | TR CONT & PROT 701611 | 1 | L SUM | $1.00 | $100.00 | $100.00 | $1.00 | $100.00 | |
| 67 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $100.00 | $100.00 | $1.00 | $100.00 | |
| 68 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1,500.00 | $100.00 | $100.00 | $1,500.00 | $100.00 | |
| 69 | 70300100 | SHORT TERM PAVT MKING | 7,376 | FOOT | $0.0100 | $0.6500 | $0.0100 | $0.0100 | $1.00 | |
| 70 | 70300150 | SHRT TRM PAVT MK REM | 2,459 | SQ FT | $2.55 | $1.52 | $0.0100 | $0.0100 | $2.00 | |
| 71 | 70300210 | TEMP PVT MK LTR & SYM | 78 | SQ FT | $0.0100 | $1.35 | $1.35 | $0.0100 | $1.00 | |
| 72 | 70300220 | TEMP PVT MK LINE 4 | 5,254 | FOOT | $0.0100 | $0.4500 | $0.4500 | $0.0100 | $0.1000 | |
| 73 | 70300240 | TEMP PVT MK LINE 6 | 2,119 | FOOT | $0.0100 | $0.7000 | $0.7000 | $0.0100 | $0.2000 | |
| 74 | 70300250 | TEMP PVT MK LINE 8 | 61 | FOOT | $0.0100 | $0.9000 | $0.9000 | $0.0100 | $0.3000 | |
| 75 | 70300260 | TEMP PVT MK LINE 12 | 1,769 | FOOT | $0.0100 | $1.35 | $1.35 | $0.0100 | $0.5000 | |
| 76 | 70300280 | TEMP PVT MK LINE 24 | 348 | FOOT | $0.0100 | $2.70 | $2.70 | $0.0100 | $0.7500 | |
| 77 | 70300520 | PAVT MARK TAPE T3 4 | 1,844 | FOOT | $1.00 | $1.40 | $0.0100 | $1.00 | $0.9000 | |
| 78 | 78000100 | THPL PVT MK LTR & SYM | 78 | SQ FT | $4.25 | $4.00 | $4.00 | $4.00 | $4.00 | |
| 79 | 78000200 | THPL PVT MK LINE 4 | 5,254 | FOOT | $0.5600 | $0.4000 | $0.4000 | $0.6300 | $0.7000 | |
| 80 | 78000400 | THPL PVT MK LINE 6 | 2,119 | FOOT | $0.8600 | $1.12 | $1.12 | $1.02 | $1.05 | |
| 81 | 78000500 | THPL PVT MK LINE 8 | 61 | FOOT | $1.20 | $3.12 | $3.12 | $1.36 | $1.40 | |
| 82 | 78000600 | THPL PVT MK LINE 12 | 1,769 | FOOT | $2.00 | $2.30 | $2.30 | $2.00 | $2.00 | |
| 83 | 78000650 | THPL PVT MK LINE 24 | 348 | FOOT | $4.25 | $4.00 | $4.00 | $4.00 | $4.00 | |
| 84 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $1,000.00 | $15,000.09 | $14,850.00 | $14,850.00 | $14,850.00 |