$420.37Avg low bid / EACH
$617.01Avg of all bids
—Avg engineer's estimate
5Jobs · 27 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 2 | 2 | $450.00 | $586.25 |
| 2025 | 3 | 25 | $418.00 | $620.13 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 80D00 | CookDistrict 1 | 1 EACH | $435.00 | Plote Construction, Inc. |
| Feb 27, 2026 | 62X88 | CookDistrict 1 | 1 EACH | $465.00 | Peter Baker & Son Co. |
| Sep 19, 2025 | 61K52 | LakeDistrict 1 | 1 EACH | $550.00 | Dunnet Bay Construction Company |
| Jun 13, 2025 | 62X35 | MchenryDistrict 1 | 20 EACH | $398.00 | Plote Construction, Inc. |
| Mar 7, 2025 | 62R58 | Cook, DupageDistrict 1 | 4 EACH | $485.00 | R. W. Dunteman Company |