2018-112-I
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lakes & Rivers Contracting, Inc. Low bidder | $847,500 | ||
| 2 | D. Construction, Inc. | $1,227,803 | +44.9% | |
| 3 | ICC Group Inc. | $1,423,000 | +67.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lakes & Rivers … | #2 D. Construction… | #3 ICC Group Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | XZ039900 | REM PIER PROT CELL | 1 | L SUM | $125,000.00 | $150,000.00 | $220,258.60 | |
| 2 | X0321809 | PERMANENT GRND ANCHOR | 24 | EACH | $9,000.00 | $15,000.00 | $12,500.00 | |
| 3 | X0326685 | NAVIGATIONAL LIGHT | 1 | L SUM | $2,000.00 | $2,500.00 | $1,500.00 | |
| 4 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $1.00 | $1,000.00 | $1.00 | |
| 5 | Z0030850 | TEMP INFO SIGNING | 25.7 | SQ FT | $1.00 | $25.00 | $32.00 | |
| 6 | 50200300 | COFFERDAM EXCAVATION | 178 | CU YD | $75.00 | $220.00 | $210.00 | |
| 7 | 50300225 | CONC STRUCT | 159 | CU YD | $345.00 | $500.00 | $575.00 | |
| 8 | 50300265 | SEAL COAT CONC | 675 | CU YD | $285.00 | $300.00 | $550.00 | |
| 9 | 50500405 | F & E STRUCT STEEL | 500 | POUND | $3.00 | $15.00 | $1.00 | |
| 10 | 50500505 | STUD SHEAR CONNECTORS | 900 | EACH | $24.00 | $8.00 | $12.00 | |
| 11 | 50800205 | REINF BARS, EPOXY CTD | 1,860 | POUND | $4.00 | $3.00 | $3.50 | |
| 12 | 52200015 | PERM SHT PILING | 3,430 | SQ FT | $49.00 | $84.00 | $85.00 | |
| 13 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $1,750.00 | $4,000.00 | $2,000.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $40,030.30 | $72,000.00 | $85,000.00 | |
| 15 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $0.0100 | $1.00 | |
| 16 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $1.00 | $0.0100 | $1.00 | |
| 17 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $1.00 | $100.00 | $1.00 |