DIST 8 RESURFACING 2019-1
- Let date
- Friday, March 8, 2019
- Contract
- 76M01 · job page
- District
- District 8
- County
- Various
- Highway
- Limits
- Resurfacing at various locations: 1) 0.81 mile along South SIUE University Drive; 2) 1.0 mile along 1-55 North Frontage Road; 3) 0.89 mile along I-55 South_Frontage Road; 4) Columbia Maintenance Yard; 5) Belleville Maintenance Yard
- Classification
- ·
- Project number
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | DMS Contracting, Inc. Low bidder | $460,617 | ||
| 2 | The Kilian Corporation | $474,501 | +3.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 DMS Contracting… | #2 The Kilian Corp… |
|---|---|---|---|---|---|---|---|
| 1 | X0327979 | PAVMT MRKG REM GRIND | 13,633 | SQ FT | $1.47 | $0.0100 | |
| 2 | 40300200 | BIT MATLS PR CT | 93 | TON | $0.0100 | $365.00 | |
| 3 | 40300400 | BIT MATLS C&S CT | 266 | TON | $774.00 | $868.00 | |
| 4 | 40300500 | COVER COAT AGG | 910 | TON | $82.00 | $66.50 | |
| 5 | 40300600 | SEAL COAT AGG | 910 | TON | $82.00 | $66.50 | |
| 6 | 67100100 | MOBILIZATION | 1 | L SUM | $35,000.00 | $42,750.00 | |
| 7 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $10,100.00 | $11,250.00 | |
| 8 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $11,500.00 | $13,500.00 | |
| 9 | 70107025 | CHANGEABLE MESSAGE SN | 48 | CAL DA | $172.50 | $75.00 | |
| 10 | 70300100 | SHORT TERM PAVT MKING | 330 | FOOT | $16.00 | $0.0100 | |
| 11 | 70300150 | SHRT TRM PAVT MK REM | 110 | SQ FT | $25.00 | $0.0100 | |
| 12 | 78001110 | PAINT PVT MK LINE 4 | 40,988 | FOOT | $0.1500 | $0.1800 | |
| 13 | 78100200 | TEMP RAIS REF PVT MKR | 911 | EACH | $5.35 | $8.85 | |
| 14 | 78300200 | RAISED REF PVT MK REM | 103 | EACH | $14.75 | $19.00 |