2018-023-RS-SW
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K-Five Construction Corporation Low bidder | $827,549 | ||
| 2 | Gallagher Asphalt Corporation | $833,282 | +0.7% | |
| 3 | D. Construction, Inc. | $833,345 | +0.7% | |
| 4 | Lindahl Brothers, Inc. | $899,996 | +8.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K-Five Construc… | #2 Gallagher Aspha… | #3 D. Construction… | #4 Lindahl Brother… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2020110 | GRADING & SHAP SHLDRS | 33 | UNIT | $100.00 | $101.25 | $30.00 | $5.00 | |
| 2 | X5537800 | SS CLEANED 12 | 300 | FOOT | $3.00 | $3.06 | $3.30 | $3.00 | |
| 3 | X6030310 | FR & LIDS ADJUST SPL | 55 | EACH | $650.00 | $663.00 | $715.00 | $704.80 | |
| 4 | Z0004562 | COMB C C&G REM & REPL | 1,350 | FOOT | $30.00 | $33.50 | $33.00 | $32.52 | |
| 5 | Z0018500 | DRAINAGE STR CLEANED | 52 | EACH | $325.00 | $244.80 | $264.00 | $352.39 | |
| 6 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $17.00 | $17.35 | $25.00 | $16.27 | |
| 7 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $50,000.00 | $4,200.00 | $3,300.00 | $3,415.52 | |
| 8 | 20100110 | TREE REMOV 6-15 | 25 | UNIT | $25.00 | $30.60 | $27.50 | $32.52 | |
| 9 | 20100210 | TREE REMOV OVER 15 | 75 | UNIT | $30.00 | $40.80 | $33.00 | $43.37 | |
| 10 | 20200100 | EARTH EXCAVATION | 40 | CU YD | $65.00 | $71.10 | $71.50 | $70.48 | |
| 11 | 21101615 | TOPSOIL F & P 4 | 300 | SQ YD | $6.00 | $8.15 | $8.80 | $6.50 | |
| 12 | 25200110 | SODDING SALT TOLERANT | 300 | SQ YD | $8.00 | $11.20 | $12.10 | $8.67 | |
| 13 | 40600290 | BIT MATLS TACK CT | 20,148 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 14 | 40600400 | MIX CR JTS FLANGEWYS | 43 | TON | $50.00 | $341.38 | $1.00 | $276.21 | |
| 15 | 40600827 | P LB MM IL-4.75 N50 | 1,208 | TON | $65.00 | $104.00 | $82.50 | $99.75 | |
| 16 | 40600982 | HMA SURF REM BUTT JT | 480 | SQ YD | $7.00 | $9.85 | $10.00 | $10.84 | |
| 17 | 40601005 | HMA REPL OVER PATCH | 350 | TON | $48.00 | $79.00 | $90.00 | $99.75 | |
| 18 | 40603335 | HMA SC "D" N50 | 2,460 | TON | $55.00 | $80.00 | $65.00 | $78.07 | |
| 19 | 42001300 | PROTECTIVE COAT | 627 | SQ YD | $0.0100 | $1.12 | $1.10 | $1.09 | |
| 20 | 42400200 | PC CONC SIDEWALK 5 | 2,560 | SQ FT | $7.00 | $7.25 | $7.15 | $7.05 | |
| 21 | 42400800 | DETECTABLE WARNINGS | 350 | SQ FT | $32.00 | $35.70 | $35.20 | $34.69 | |
| 22 | 44000158 | HMA SURF REM 2 1/4 | 28,427 | SQ YD | $1.70 | $2.00 | $1.65 | $2.98 | |
| 23 | 44000600 | SIDEWALK REM | 2,560 | SQ FT | $2.00 | $2.25 | $2.20 | $2.17 | |
| 24 | 44002212 | HMA RM OV PATCH 3 | 2,080 | SQ YD | $3.50 | $7.45 | $25.00 | $4.34 | |
| 25 | 44201729 | CL D PATCH T2 7 | 740 | SQ YD | $20.00 | $60.90 | $55.00 | $40.00 | |
| 26 | 44201733 | CL D PATCH T3 7 | 160 | SQ YD | $20.00 | $55.00 | $52.00 | $40.00 | |
| 27 | 44201735 | CL D PATCH T4 7 | 1,180 | SQ YD | $20.00 | $41.80 | $50.00 | $40.00 | |
| 28 | 48102100 | AGG WEDGE SHLD TYPE B | 132 | TON | $20.00 | $54.00 | $28.00 | $45.00 | |
| 29 | 60252800 | CB RECONST | 1 | EACH | $2,500.51 | $1,530.00 | $1,650.00 | $1,626.44 | |
| 30 | 60258200 | MAN RECON NEW T1F CL | 2 | EACH | $2,750.00 | $2,040.00 | $2,200.00 | $2,168.59 | |
| 31 | 60300305 | FR & LIDS ADJUST | 21 | EACH | $325.00 | $331.50 | $357.50 | $352.39 | |
| 32 | 60404950 | FR & GRATES T24 | 4 | EACH | $425.00 | $433.50 | $467.50 | $460.83 | |
| 33 | 60406100 | FR & LIDS T1 CL | 5 | EACH | $325.00 | $331.50 | $357.50 | $352.39 | |
| 34 | 66900200 | NON SPL WASTE DISPOSL | 40 | CU YD | $150.00 | $153.00 | $150.00 | $80.00 | |
| 35 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $150.00 | $1,479.00 | $4,455.00 | $1,450.00 | |
| 36 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,100.00 | $2,142.00 | $2,200.00 | $2,100.00 | |
| 37 | 66901002 | ON-SITE MON REG SUB | 10 | CAL DA | $1,100.00 | $836.40 | $1,045.00 | $820.00 | |
| 38 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $840.00 | $1,836.00 | $2,200.00 | $1,800.00 | |
| 39 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,300.00 | $499.99 | $3,500.00 | $5,500.00 | |
| 40 | 67100100 | MOBILIZATION | 1 | L SUM | $100,000.00 | $43,300.00 | $49,000.00 | $50,000.00 | |
| 41 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $100,000.00 | $13,464.00 | $1.00 | $30,000.00 | |
| 42 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.02 | $21,190.00 | $920.00 | |
| 43 | 70300100 | SHORT TERM PAVT MKING | 5,695 | FOOT | $1.00 | $0.0100 | $0.0100 | $1.00 | |
| 44 | 70300210 | TEMP PVT MK LTR & SYM | 573 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $1.25 | |
| 45 | 70300220 | TEMP PVT MK LINE 4 | 25,117 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.2000 | |
| 46 | 70300240 | TEMP PVT MK LINE 6 | 388 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.3000 | |
| 47 | 70300260 | TEMP PVT MK LINE 12 | 75 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.6000 | |
| 48 | 70300280 | TEMP PVT MK LINE 24 | 250 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.20 | |
| 49 | 70300520 | PAVT MARK TAPE T3 4 | 5,695 | FOOT | $1.00 | $0.0100 | $0.0100 | $0.9000 | |
| 50 | 78000100 | THPL PVT MK LTR & SYM | 573 | SQ FT | $3.75 | $4.10 | $4.40 | $3.75 | |
| 51 | 78000200 | THPL PVT MK LINE 4 | 25,117 | FOOT | $0.5500 | $0.5500 | $0.5900 | $0.5500 | |
| 52 | 78000400 | THPL PVT MK LINE 6 | 388 | FOOT | $0.8200 | $0.9200 | $0.9900 | $0.8200 | |
| 53 | 78000600 | THPL PVT MK LINE 12 | 75 | FOOT | $1.75 | $2.04 | $2.20 | $1.75 | |
| 54 | 78000650 | THPL PVT MK LINE 24 | 250 | FOOT | $3.75 | $4.34 | $4.68 | $3.75 | |
| 55 | 78100100 | RAISED REFL PAVT MKR | 184 | EACH | $35.00 | $24.50 | $26.40 | $35.00 | |
| 56 | 78300200 | RAISED REF PVT MK REM | 125 | EACH | $5.00 | $7.75 | $8.00 | $16.27 | |
| 57 | 88600600 | DET LOOP REPL | 301 | FOOT | $16.00 | $16.35 | $17.60 | $16.00 |