2018-040-RS
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plote Construction, Inc. Low bidder | $673,920 | ||
| 2 | Builders Paving, LLC | $688,000 | +2.1% | |
| 3 | J. A. Johnson Paving Company | $745,385 | +10.6% | |
| 4 | R. W. Dunteman Company | $764,441 | +13.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plote Construct… | #2 Builders Paving… | #3 J. A. Johnson P… | #4 R. W. Dunteman … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | K0029614 | WEED CONT AQUATIC | 1.8 | GALLON | $1,200.00 | $1,200.00 | $1,200.00 | $1,400.00 | |
| 2 | K0029624 | WEED CONTROL TEASEL | 0.9 | GALLON | $990.00 | $990.00 | $990.00 | $1,400.00 | |
| 3 | X0327900 | TREE REMOV UNDER 6 SF | 30 | IN DIA | $10.00 | $25.00 | $15.00 | $25.00 | |
| 4 | X4060004 | P HMA SC SMA 9.5 N80 | 1,506 | TON | $92.00 | $91.00 | $88.00 | $99.77 | |
| 5 | X7030005 | TEMP PAVT MKING REMOV | 4,475 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 6 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $18.00 | $18.00 | $18.00 | $18.00 | |
| 7 | 20100110 | TREE REMOV 6-15 | 42 | UNIT | $25.00 | $25.00 | $42.00 | $25.00 | |
| 8 | 25000750 | MOWING | 6.5 | ACRE | $850.00 | $850.00 | $850.00 | $225.00 | |
| 9 | 25003210 | INTERSEED CL 2A | 3.4 | ACRE | $3,950.00 | $3,950.00 | $3,950.00 | $2,900.00 | |
| 10 | 40600290 | BIT MATLS TACK CT | 17,312 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.5700 | |
| 11 | 40600400 | MIX CR JTS FLANGEWYS | 39 | TON | $75.00 | $300.00 | $325.00 | $80.00 | |
| 12 | 40600827 | P LB MM IL-4.75 N50 | 1,053 | TON | $88.00 | $100.00 | $96.00 | $96.77 | |
| 13 | 40600982 | HMA SURF REM BUTT JT | 121 | SQ YD | $25.00 | $20.00 | $4.00 | $19.71 | |
| 14 | 40603340 | HMA SC "D" N70 | 997 | TON | $80.00 | $84.00 | $86.00 | $82.95 | |
| 15 | 44000159 | HMA SURF REM 2 1/2 | 25,526 | SQ YD | $3.33 | $2.60 | $4.00 | $2.33 | |
| 16 | 44201811 | CL D PATCH T1 14 | 16 | SQ YD | $250.00 | $80.00 | $75.00 | $152.80 | |
| 17 | 44201815 | CL D PATCH T2 14 | 797 | SQ YD | $45.00 | $80.00 | $74.00 | $136.72 | |
| 18 | 44201819 | CL D PATCH T3 14 | 402 | SQ YD | $44.00 | $80.00 | $73.00 | $121.29 | |
| 19 | 44201821 | CL D PATCH T4 14 | 643 | SQ YD | $43.00 | $80.00 | $72.00 | $114.90 | |
| 20 | 64200108 | SHOULDER RUM STRIP 8 | 11,008 | FOOT | $0.5100 | $1.00 | $0.5100 | $0.8600 | |
| 21 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,500.00 | $2,500.00 | $3,000.00 | $1,500.00 | |
| 22 | 67100100 | MOBILIZATION | 1 | L SUM | $35,000.00 | $41,000.00 | $44,000.00 | $48,079.82 | |
| 23 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $77,088.00 | $11,645.93 | $55,788.00 | $5,700.00 | |
| 24 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $5,253.68 | |
| 25 | 70300100 | SHORT TERM PAVT MKING | 2,505 | FOOT | $0.7000 | $1.00 | $1.00 | $0.1000 | |
| 26 | 70300150 | SHRT TRM PAVT MK REM | 835 | SQ FT | $1.50 | $2.00 | $0.5000 | $0.1000 | |
| 27 | 70300210 | TEMP PVT MK LTR & SYM | 78 | SQ FT | $0.0100 | $1.25 | $1.25 | $1.25 | |
| 28 | 70300220 | TEMP PVT MK LINE 4 | 12,384 | FOOT | $0.0100 | $0.2500 | $0.2500 | $0.2500 | |
| 29 | 70300240 | TEMP PVT MK LINE 6 | 360 | FOOT | $0.0100 | $0.5000 | $0.5000 | $0.5000 | |
| 30 | 70300260 | TEMP PVT MK LINE 12 | 994 | FOOT | $0.0100 | $0.7500 | $0.7500 | $0.7500 | |
| 31 | 70300520 | PAVT MARK TAPE T3 4 | 501 | FOOT | $1.50 | $1.50 | $1.50 | $1.50 | |
| 32 | 78000100 | THPL PVT MK LTR & SYM | 78 | SQ FT | $4.50 | $4.50 | $4.50 | $4.50 | |
| 33 | 78000200 | THPL PVT MK LINE 4 | 12,384 | FOOT | $0.5500 | $0.5500 | $0.5500 | $0.5500 | |
| 34 | 78000400 | THPL PVT MK LINE 6 | 360 | FOOT | $1.00 | $1.00 | $1.00 | $1.00 | |
| 35 | 78000600 | THPL PVT MK LINE 12 | 994 | FOOT | $1.85 | $1.85 | $1.85 | $1.85 | |
| 36 | 78100100 | RAISED REFL PAVT MKR | 218 | EACH | $24.00 | $24.00 | $24.00 | $24.00 | |
| 37 | 78300200 | RAISED REF PVT MK REM | 218 | EACH | $11.00 | $13.00 | $5.00 | $12.92 | |
| 38 | 88600600 | DET LOOP REPL | 117 | FOOT | $23.00 | $23.00 | $23.00 | $23.00 |