18-00091-00-RS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plote Construction, Inc. Low bidder | $1,214,960 | ||
| 2 | J. A. Johnson Paving Company | $1,250,669 | +2.9% | |
| 3 | Arrow Road Construction Co. | $1,258,574 | +3.6% | |
| 4 | Builders Paving, LLC | $1,345,888 | +10.8% | |
| 5 | R. W. Dunteman Company | $1,394,350 | +14.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plote Construct… | #2 J. A. Johnson P… | #3 Arrow Road Cons… | #4 Builders Paving… | #5 R. W. Dunteman … |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $5,500.00 | $10,000.00 | $7,600.00 | $5,000.00 | $7,600.00 | |
| 2 | X0327036 | BIKE PATH REM | 212 | SQ YD | $20.00 | $11.00 | $32.00 | $15.00 | $14.23 | |
| 3 | X6026050 | SANITARY MANHOLE ADJ | 2 | EACH | $1,500.00 | $1,100.00 | $1,500.00 | $1,500.00 | $1,500.00 | |
| 4 | X6030310 | FR & LIDS ADJUST SPL | 37 | EACH | $820.00 | $950.00 | $885.00 | $820.00 | $820.00 | |
| 5 | X7810300 | REC REF PVT MARKER | 194 | EACH | $28.00 | $35.00 | $35.00 | $35.00 | $35.00 | |
| 6 | Z0030850 | TEMP INFO SIGNING | 103 | SQ FT | $15.00 | $16.00 | $9.00 | $9.00 | $18.00 | |
| 7 | Z0033700 | LONG JOINT SEALANT | 18,552 | FOOT | $1.00 | $2.00 | $2.09 | $2.00 | $2.18 | |
| 8 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 10 | 20101200 | TREE ROOT PRUNING | 5 | EACH | $120.00 | $95.00 | $250.00 | $150.00 | $150.00 | |
| 11 | 21101625 | TOPSOIL F & P 6 | 282 | SQ YD | $10.50 | $10.00 | $24.80 | $10.00 | $9.98 | |
| 12 | 25000400 | NITROGEN FERT NUTR | 4 | POUND | $3.00 | $4.00 | $20.00 | $5.00 | $4.00 | |
| 13 | 25000600 | POTASSIUM FERT NUTR | 4 | POUND | $3.00 | $4.00 | $20.00 | $5.00 | $4.00 | |
| 14 | 25200110 | SODDING SALT TOLERANT | 282 | SQ YD | $11.50 | $25.00 | $18.59 | $15.00 | $16.00 | |
| 15 | 25200200 | SUPPLE WATERING | 1 | UNIT | $200.00 | $100.00 | $382.00 | $0.0100 | $100.00 | |
| 16 | 28000250 | TEMP EROS CONTR SEED | 4 | POUND | $14.50 | $10.00 | $71.50 | $5.00 | $10.00 | |
| 17 | 28000510 | INLET FILTERS | 103 | EACH | $150.00 | $25.00 | $150.00 | $150.00 | $150.00 | |
| 18 | 35101600 | AGG BASE CSE B 4 | 394 | SQ YD | $9.00 | $4.00 | $11.00 | $5.50 | $8.53 | |
| 19 | 40600290 | BIT MATLS TACK CT | 34,324 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 20 | 40600400 | MIX CR JTS FLANGEWYS | 11 | TON | $600.00 | $425.00 | $150.00 | $300.00 | $476.04 | |
| 21 | 40600827 | P LB MM IL-4.75 N50 | 2,136 | TON | $87.00 | $85.00 | $85.40 | $86.50 | $101.45 | |
| 22 | 40600982 | HMA SURF REM BUTT JT | 220 | SQ YD | $19.00 | $1.00 | $11.10 | $20.00 | $13.36 | |
| 23 | 40603340 | HMA SC "D" N70 | 6,407 | TON | $72.00 | $75.00 | $73.35 | $72.50 | $81.15 | |
| 24 | 42001300 | PROTECTIVE COAT | 482 | SQ YD | $1.00 | $0.1000 | $1.00 | $0.1000 | $1.00 | |
| 25 | 42400200 | PC CONC SIDEWALK 5 | 4,534 | SQ FT | $6.00 | $6.20 | $6.00 | $6.50 | $6.00 | |
| 26 | 42400800 | DETECTABLE WARNINGS | 397 | SQ FT | $30.00 | $32.00 | $30.00 | $32.00 | $30.00 | |
| 27 | 44000164 | HMA SURF REM 3 3/4 | 37,931 | SQ YD | $3.75 | $4.00 | $4.00 | $3.65 | $4.81 | |
| 28 | 44000500 | COMB CURB GUTTER REM | 398 | FOOT | $25.00 | $9.00 | $10.00 | $9.00 | $10.00 | |
| 29 | 44000600 | SIDEWALK REM | 1,599 | SQ FT | $2.10 | $2.00 | $2.00 | $2.00 | $2.00 | |
| 30 | 44201737 | CL D PATCH T1 8 | 380 | SQ YD | $10.00 | $15.00 | $22.00 | $70.00 | $48.24 | |
| 31 | 44201741 | CL D PATCH T2 8 | 569 | SQ YD | $10.00 | $15.00 | $22.00 | $68.00 | $38.93 | |
| 32 | 44201745 | CL D PATCH T3 8 | 569 | SQ YD | $10.00 | $15.00 | $22.00 | $68.00 | $36.38 | |
| 33 | 44201747 | CL D PATCH T4 8 | 380 | SQ YD | $10.00 | $15.00 | $22.00 | $58.00 | $36.49 | |
| 34 | 56400400 | FIRE HYDNTS RELOCATED | 1 | EACH | $8,800.00 | $4,100.00 | $8,800.00 | $8,800.00 | $8,800.00 | |
| 35 | 60603800 | COMB CC&G TB6.12 | 173 | FOOT | $33.00 | $35.00 | $35.00 | $36.00 | $35.00 | |
| 36 | 60604400 | COMB CC&G TB6.18 | 1,898 | FOOT | $33.00 | $31.00 | $35.00 | $33.00 | $35.00 | |
| 37 | 67100100 | MOBILIZATION | 1 | L SUM | $72,500.00 | $75,109.29 | $70,000.00 | $80,000.00 | $68,512.96 | |
| 38 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $49,000.00 | $45,000.00 | $32,500.00 | $10,228.15 | $18,033.98 | |
| 39 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $8,000.00 | $1.00 | $1.00 | $100.00 | |
| 40 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 | |
| 41 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $500.00 | $1.00 | $1.00 | $100.00 | |
| 42 | 70107025 | CHANGEABLE MESSAGE SN | 320 | CAL DA | $5.00 | $20.00 | $10.00 | $10.00 | $30.00 | |
| 43 | 70300100 | SHORT TERM PAVT MKING | 72,183 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.5000 | $0.0100 | |
| 44 | 70300150 | SHRT TRM PAVT MK REM | 12,766 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.7500 | $0.0100 | |
| 45 | 78000100 | THPL PVT MK LTR & SYM | 728 | SQ FT | $3.75 | $3.50 | $4.00 | $3.50 | $3.50 | |
| 46 | 78000200 | THPL PVT MK LINE 4 | 27,921 | FOOT | $0.5000 | $0.5000 | $0.5000 | $0.5000 | $0.5000 | |
| 47 | 78000400 | THPL PVT MK LINE 6 | 4,185 | FOOT | $0.7500 | $0.7500 | $0.7500 | $0.7500 | $0.7500 | |
| 48 | 78000600 | THPL PVT MK LINE 12 | 1,630 | FOOT | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 | |
| 49 | 78000650 | THPL PVT MK LINE 24 | 194 | FOOT | $4.00 | $3.50 | $3.50 | $3.50 | $3.50 | |
| 50 | 78300200 | RAISED REF PVT MK REM | 501 | EACH | $14.81 | $0.0100 | $7.00 | $11.50 | $10.96 | |
| 51 | 85000200 | MAIN EX TR SIG INSTAL | 2 | EACH | $1,100.00 | $2,100.00 | $1,100.00 | $2,100.00 | $2,100.00 | |
| 52 | 88600600 | DET LOOP REPL | 368 | FOOT | $16.90 | $16.00 | $16.90 | $16.00 | $16.00 |