| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jan 18, 2019 | 62G87 | CookLakeMcHenryDistrict 1 | Cleaning and painting existing steel on structures. IL 137 over US 45, IL 31 over UPRR, and Green Bay Road over North Shore Channel. | — | Executed | Eagle Painting & Maintenance Company, Inc. $302,850 · | ||
| Jan 18, 2019 | 62G88 | DuPageDistrict 1 | Cleaning and painting designated steel surfaces of I-290 bridge (SN 022-0107) at Metra (north of IL 19 - Irving Park Road) in the Village of Itasca. | — | Executed | Eagle Painting & Maintenance Company, Inc. $805,200 · | ||
| Jan 18, 2019 | 62G93 | DuPageDistrict 1 | Bridge deck overlay and approach pavement with latex concrete. Adjacent HMA pavement will be resurfaced to provide a smooth transition. | — | Executed | Martam Construction Incorporated $164,813 · | ||
| Jan 18, 2019 | 62G95 | DuPageDistrict 1 | Drainage improvement project in the median of IL 83 from 67th Street to Plainfield Road. | — | Executed | Scanlon Excavating & Concrete, Inc. $88,287 · | ||
| Jan 18, 2019 | 62G99 | WillDistrict 1 | Bridge deck overlay, joint repairs, structural repair of concrete, and drainage repairs on 099-0264 carrying US 30 over WCL RR in Joliet. | — | Executed | D. Construction, Inc. $1,673,197 · | ||
| Jan 18, 2019 | 62H31 | CookLakeDistrict 1 | Crack and joint sealing on US 12 (Rand Rd.) from Ela Road to IL 58 (Golf Rd.) | — | Executed | Freehill Asphalt, Inc. $451,265 · | ||
| Jan 18, 2019 | 62H47 | CookDistrict 1 | Resurfacing on Palatine Rd. approximately 100 feet west of the centerline of US 14 (Northwest Hwy.) to 70 feet east of centerline of US 12 (Rand Rd.). 2.93 miles. | — | Executed | Builders Paving, LLC $3,557,204 · | ||
| Jan 18, 2019 | 62H65 | VariousDistrict 1 | Expressway mowing south. | — | Executed | Lion Construction 1, LLC $224,380 · | ||
| Jan 18, 2019 | 62H66 | VariousDistrict 1 | Expressway mowing north. | — | Executed | McGinty Bros., Inc. $211,296 · | ||
| Jan 18, 2019 | 62H67 | VariousDistrict 1 | Cleaning (sweeping) various expressway and arterial highways throughout District 1. | — | Executed | Elgin Sweeping Services, Inc. $12,612,286 · | ||
| Jan 18, 2019 | 64L50 | HenryDistrict 2 | Cleaning and painting structural steel on SN 037-0117 carrying township 400A over I-80, 2.8 miles west of IL 78. | — | Executed | Eagle Painting & Maintenance Company, Inc. $195,626 · | ||
| Jan 18, 2019 | 64M21 | OgleWinnebagoDistrict 2 | 19.53 miles routing, cleaning, and sealing the centerline and shoulder joints on I-39 from the Lee County line to 0.4 miles north of Baxter Road. | — | Executed | Freehill Asphalt, Inc. $666,361 · | ||
| Jan 18, 2019 | 64N07 | HenryDistrict 2 | Cleaning and painting structural steel on SN 037-0102 carrying N 1900th Avenue over I-74, 1.0 mile south of I-80. | — | Executed | Eagle Painting & Maintenance Company, Inc. $199,110 · | ||
| Jan 18, 2019 | 64N08 | HenryDistrict 2 | Clean and paint structural steel on SN 037-0103 carrying N 1700th Avenue over I-74, 3.0 miles south of I-80. | — | Executed | Eagle Painting & Maintenance Company, Inc. $193,240 · | ||
| Jan 18, 2019 | 64N09 | HenryDistrict 2 | Cleaning and painting structrual steel on SN 037-0104 carrying N 1200th Ave. over I-74, 2.0 miles north of IL 81. | — | Executed | Eagle Painting & Maintenance Company, Inc. $193,591 · | ||
| Jan 18, 2019 | 64N16 | VariousDistrict 2 | "On-Call" guardrail and fence repairs along state maintained routes in Boone, Carroll, Jo Davies, Ogle, Stephenson and Winnebago Counties. | — | Rejected | Northern Contracting, Inc. $394,187 · | ||
| Jan 18, 2019 | 64N17 | VariousDistrict 2 | "On-Call" guardrail and fence repairs along state maintained routes in Henry, Lee, Rock Island, Whiteside, and portions of LaSalle Counties. | — | Rejected | Northern Contracting, Inc. $444,125 · | ||
| Jan 18, 2019 | 64N19 | StephensonDistrict 2 | Pavement patchingh on US 20 from Ayp Road to Browns Mill Road. | — | Executed | G. M. Sipes Construction, Inc. $286,378 · | ||
| Jan 18, 2019 | 64N21 | OgleDistrict 2 | Cold milling and HMA resurfacing on IL 2 from chestnut Street to 0.2 mile north in Byron. | — | Executed | Martin & Company Excavating $149,653 · | ||
| Jan 18, 2019 | 64N23 | WhitesideDistrict 2 | Mill and resurface I-88 bridge roadway approaches on SN 098-0084(EB), 098-0087(EB), 098-0088(WB), 098-0089(WB), and 098-0090(EB). | — | Executed | Martin & Company Excavating $210,983 · | ||
| Jan 18, 2019 | 64N24 | LeeDistrict 2 | Removal and replacement of culvert in the south leg of the intersection of IL 251 and US 30. | — | Executed | O'Brien Civil Works, Inc. $118,640 · | ||
| Jan 18, 2019 | 64N30 | WinnebagoDistrict 2 | Expansion joint replacement, beam end repairs, and bearing replacements on SN 101-0144 carrying Rotary Road over I-39. | — | Executed | Civil Constructors, Inc. $117,814 · | ||
| Jan 18, 2019 | 66C58 | LaSalleDistrict 3 | Removal and replacemnt of SN 050-0073 carrying IL 170 over the BNSF Railroad at the Village of Ransom. Work includes embankment, guardrail, landscaping, and pavement striping. | — | Executed | D. Construction, Inc. $3,144,188 · | ||
| Jan 18, 2019 | 66E75 | LaSalleDistrict 3 | Paching, milling, and resurfacing at various locations on IL 23/IL 71 from Freemont St. to 0.2 miles south of McKinley Rd., and 0.1 mile south of Lincoln Place. | — | Executed | Advanced Asphalt Company $4,638,064 · | ||
| Jan 18, 2019 | 66E99 | LaSalleDistrict 3 | 3P milling and resurfacing of US 6 from IL 178 to the west city limits of Ottawa. 7.11 miles. | — | Executed | Advanced Asphalt Company $2,864,832 · | ||
| Jan 18, 2019 | 66F57 | KankakeeDistrict 3 | Substructure widening and superstructure replacement on SN 046-0035, 0036 carrying IL 17 over Baker Creek. | — | Executed | Tobey's Construction & Cartage, Inc. $3,708,133 · | ||
| Jan 18, 2019 | 66H81 | BureauDistrict 3 | Cleaning and painting all strucutral steel of SN 006-0090 carrying IL 40 over Hennepin Canal. | — | Executed | Thomas Industrial Coatings, Inc. $99,935 · | ||
| Jan 18, 2019 | 66J04 | LaSalleDistrict 3 | Removal of the existing parking lot pavement and replacement with a new parking area. | — | Executed | Universal Asphalt & Excavating, Inc. $250,991 · | ||
| Jan 18, 2019 | 66J13 | DeKalbDistrict 3 | Install span wire mounted four-way flashing read beacon at the intersection of IL 23 and IL 72. The project includes installation of post-mounted flashing yellow beacon on the advance intersection warning signs adjacent to the north, east, and west legs. | — | Executed | William Charles Construction Co, LLC $72,000 · | ||
| Jan 18, 2019 | 66J37 | BureauDistrict 3 | Concrete deck, bearing, expansion joint, floor drain, guardrail/terminal section removal and replacement, and installing steel bridge railing to SN 006-0061 carrying US 6 over King Creek. | — | Executed | D. Construction, Inc. $426,461 · | ||
| Jan 18, 2019 | 66J42 | FordDistrict 3 | removal and replacement of a 3'x 2' concrete box culvert with 30' ERS RCCP culv ert located on IL 115, 0.7 mile south of Main Street in Cabery. | — | Executed | Scanlon Excavating & Concrete, Inc. $36,875 · | ||
| Jan 18, 2019 | 66J43 | BureauDistrict 3 | Cleaning and painting all structural steel of SN 006-0039 carrying FAI 180 over FAI 80 approximately 4 miles east of Princeton. | — | Executed | ERA-Valdivia Contractors, Inc. $424,473 · | ||
| Jan 18, 2019 | 66J46 | BureauDistrict 3 | Cleaning and painting all structural steel of SN 006-0142 carrying IL 89 over a branch of Brush Creek approximately 0.8 miles south of Arlington. | — | Executed | Thomas Industrial Coatings, Inc. $101,065 · | ||
| Jan 18, 2019 | 66J67 | GrundyLivingstonDistrict 3 | Two application of spray mixtures at designated times, once in the Spring and once in the summer, along I-80, I-55 and IL 113 in Grundy County and along I-55, IL 47, and IL 23 in Livingston County. | — | Executed | Endrizzi Contracting, Inc $126,725 · | ||
| Jan 18, 2019 | 68A91 | FultonDistrict 4 | Resurfacing on US 24 from Maple St. in Lewistown to Little America, and on IL 97 from US 24 to North Clark Rd. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $3,428,793 · | ||
| Jan 18, 2019 | 68D59 | TazewellDistrict 4 | Bridge repair on Washington Street (IL 40) and the Industrial Spur (IL 40). | — | Executed | Halverson Construction Co., Inc. $3,848,556 · | ||
| Jan 18, 2019 | 68D79 | WoodfordDistrict 4 | Resurfacing I-39 from the Mclean County line to 0.25 mile north of US 24, includes repair on bridges SN 102-0058 and 102-0059. | — | Executed | Rowe Construction, a div of UCM, Inc. $13,273,213 · | ||
| Jan 18, 2019 | 68E20 | PeoriaDistrict 4 | Installation of fiber optic cable, communications equipment and CCTV for a new traffic signal system in Peoria. | — | Rejected | Oberlander Electric Co. $790,000 · | ||
| Jan 18, 2019 | 68E69 | VariousDistrict 4 | Dead tree removal throughout District 4. | — | Executed | Clean Cut Tree Service, Inc. $167,467 · | ||
| Jan 18, 2019 | 68E74 | KnoxDistrict 4 | Structural steel repairs to beams on SN 048-0065 carrying Farnham Street over US 34. | — | Executed | Halverson Construction Co., Inc. $147,930 · | ||
| Jan 18, 2019 | 68E76 | TazewellDistrict 4 | Installation and removal of guardrail, inlet adjustments and miscellaneous concrete work to separate US 150 (West Jackson Street) from the adjacent multi-use trial from Beverly Avenue to Cedar Avenue, on the northwest side of Morton | — | Executed | Illinois Civil Contractors, Inc. $149,100 · | ||
| Jan 18, 2019 | 68E78 | TazewellDistrict 4 | Install communications duct, communications vaults, fiber optic cable, CCTV cameras along US 24 and Business Route 24 in and around Washington. | — | Executed | Bodine Electric of Decatur $427,439 · | ||
| Jan 18, 2019 | 70997 | ChampaignDistrict 5 | Standard overlay with ADA improvements on US 150 between Mattis Ave. and Propect Ave. in Champaign. | — | Executed | Cross Construction, Inc. $1,135,000 · | ||
| Jan 18, 2019 | 70A61 | ChampaignDistrict 5 | Replace the structure carrying Bradley Avenue over I-57, including 0.578 miles of widening and resurfacing on Bradley Avenue. | — | Executed | Stark Excavating, Inc. $4,943,503 · | ||
| Jan 18, 2019 | 70D49 | DeWittMcLeanPiattDistrict 5 | 5.88 miles of Class A patching from Champaign County line to east of Downs on I-74, and one spot location just south of Hudson on I-39. | — | Executed | G. M. Sipes Construction, Inc. $193,089 · | ||
| Jan 18, 2019 | 70D51 | ChampaignDouglasDistrict 5 | 25.51 miles of Class A (SPL) and Class B patching_on I-57 between Tuscola and Rantoul, and on I-72 from Champaign to the Piatt County Line. | — | Executed | G. M. Sipes Construction, Inc. $353,033 · | ||
| Jan 18, 2019 | 72C83 | ChristianDistrict 6 | Culvert replacement on US 51 over a ditch, 0.9 mile north of IL 16. | — | Executed | Stutz Excavating, Inc. $702,444 · | ||
| Jan 18, 2019 | 72K03 | AdamsHancockDistrict 6 | Clean 3 bridges: 1) SN 001-0019, US 24 EB over the Mississippi River in Quincy, 2) SN 001-0068, US 24 WD over the Mississippi River in Quincy, 3) SN 034-0062 US 136 over the Mississippi River near Keokuk, IA. | — | Executed | Interstate Maintenance, Incorporated $68,999 · | ||
| Jan 18, 2019 | 72K67 | AdamsDistrict 6 | 9.9 miles of micro-surfacing, cape seal on pavement and fog seal on shoulders, on IL 110/336 and north interchange ramps, and overhead roadway at the IL 61 and IL 110/336 interchange. | — | Executed | A. C. Pavement Striping Co. $2,670,026 · | ||
| Jan 18, 2019 | 72K69 | SchuylerDistrict 6 | Installing cross road pipe culver, existing pipe culvert removal and fill, and related ditch improvements on IL 99 just south of Vaughn Lane, south of Camden. | — | Executed | County Contractors, Inc. $156,000 · | ||
| Jan 18, 2019 | 72K72 | MontgomeryDistrict 6 | Paint 3 bridges on I-55 in northern Montgomery County(SN 068-0036, 0040, 0041). | — | Executed | ERA-Valdivia Contractors, Inc. $649,450 · | ||
| Jan 18, 2019 | 72K73 | LoganDistrict 6 | Painting portions of four bridges on I-55, I-155 and US 136 in Logan County (SN 054-0052, 054-0027, 054-0076, 054-0077). | — | Rejected | Venus Painting Co. $526,000 · | ||
| Jan 18, 2019 | 72K74 | SangamonDistrict 6 | Painting portions of 4 bridges on I-72, Business 55, and IL 4 in Sangamon County. | — | Rejected | Civil Coatings and Construction Inc. $434,065 · | ||
| Jan 18, 2019 | 72K91 | MontgomeryDistrict 6 | Bituminous surface treatment and resurfacing on I-55 West Frontage Road, from IL 108 to 18th Avenue, and on I-55 East Frontage Road from IL 48 to IL 108. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $907,730 · | ||
| Jan 18, 2019 | 72K94 | MorganDistrict 6 | Centerline microsurfacing on I-72 from 0.7 mile west of US 67 to 3.3 miles east of Business IL 72. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $274,398 · | ||
| Jan 18, 2019 | 72K97 | MacoupinDistrict 6 | Replacing expansion joints, placing microsilica overlay, performing substructure repairs and painting beam ends on SN 059-0035 carrying IL 108 over Lick Creek. | — | Executed | RCS Construction, Inc. $365,553 · | ||
| Jan 18, 2019 | 74177 | LawrenceDistrict 7 | Replacement of two structures on US 50 over an abandoned railroad and Otter Pond Ditch; and replacement of two superstructures on US 50 over IL 1 and CH 12 north of Lawrenceville (SN 051-0012, 0013, 0014, 0015). | — | Executed | Sangamo Construction Company $10,061,291 · | ||
| Jan 18, 2019 | 74261 | ColesDistrict 7 | 3.1 miles of pavement patching, HMA milling and resurfacing, rehab of 2 bridges 3 culvert extensions and guardrail on IL 16 from Ashmore to the Edgar County line. | — | Executed | Howell Paving, Inc. $2,177,289 · | ||
| Jan 18, 2019 | 74432 | CumberlandDistrict 7 | Removing and replacing concrete deck beams with a PCC slab superstructure, Bridge approach pavements, HMA resurfacing and guardrail on Montrose Blacktop approximately 1.5 miles south of IL 121 (SN 018-0056). | — | Executed | White Construction, Inc. $633,093 · | ||
| Jan 18, 2019 | 74561 | ColesDistrict 7 | Superstructure replacement on SN 015-0070 carrying 900 N/IL 316 over Riley Creek Branch, 0.8 miles northwest of Loxa. | — | Executed | County Contractors, Inc. $511,648 · | ||
| Jan 18, 2019 | 74849 | MaconDistrict 7 | Culvert removal and replacement on Old US 36 over an unnamed stream approximately 0.1 mile west of US 36. | — | Executed | Otto Baum Company, Inc. $509,397 · | ||
| Jan 18, 2019 | 74863 | VariousDistrict 7 | Sealing the bridge decks on 114 structures throughout District 7. | — | Executed | All States Painting, Inc. $118,898 · | ||
| Jan 18, 2019 | 74868 | ColesDistrict 7 | 7.8 miles of microsurfacing on Old IL 316 from 0.2 mile north of IL 16 to D Street in Charleston. | — | Executed | A. C. Pavement Striping Co. $494,881 · | ||
| Jan 18, 2019 | 74869 | MoultrieDistrict 7 | 8.1 miles of bituminous surface treatment on Cadwell Road from IL 121 to IL 133. | — | Executed | Beniach Construction Co., Inc. $313,710 · | ||
| Jan 18, 2019 | 74888 | RichlandDistrict 7 | 8.3 miles of base repair, pot hole patching and application of bituminous surface treatment at 2 locations on Old US 50; 1) from just west of the Lawrenceville Correctional Center (CR 2100 E) to the intersection of US 50/IL 250; 2) from 1100 North (IL 250 to 1400 East (St. Marie Road). | — | Executed | Mt. Carmel Stabilization Group, Inc. $328,966 · | ||
| Jan 18, 2019 | 74889 | ColesShelbyDistrict 7 | 10.5 miles of bituminous surface treatment at 3 locations in Coles County and 4 locations in Shelby County. | — | Executed | Earl Walker Company, Inc. $418,569 · | ||
| Jan 18, 2019 | 74892 | ClayDistrict 7 | Placing aggregate wedge shoulders on the Kinmundy/Louisville Blacktop from the Marion County line to US 45 in Louisville. | — | Executed | Phoenix Corporation of the Quad Cities $163,597 · | ||
| Jan 18, 2019 | 76J12 | MadisonDistrict 8 | Replace bridge 060-2454 carrying IL 157 over Silver Creek Tributary south of Hamel. | — | Executed | Baxmeyer Construction, Inc. $644,578 · | ||
| Jan 18, 2019 | 76K30 | MadisonDistrict 8 | Bridge joint replacement at south abutment and other repairs on Clark Bridge (US 67 over the Mississippi River (SN 060-0255). | — | Executed | Keeley & Sons, Inc. $567,212 · | ||
| Jan 18, 2019 | 76L35 | MadisonDistrict 8 | Crack and joint sealing on I-55 from 1.3 miles north of Il 140 to the Macoupin County line. | — | Executed | Freehill Asphalt, Inc. $96,445 · | ||
| Jan 18, 2019 | 76L99 | MadisonDistrict 8 | Bridge painting SN 060-0238 and 060-0239 on I-255 over Collinsville Road. | — | Executed | ERA-Valdivia Contractors, Inc. $397,725 · | ||
| Jan 18, 2019 | 76M03 | ClintonDistrict 8 | Bridge and jooint repair on SN 014-0031 on Old US 50 approximately 1.2 miles east of Aviston. | — | Executed | Keller Construction, Inc. $305,388 · | ||
| Jan 18, 2019 | 76M04 | St. ClairDistrict 8 | Bridge and joint repair on Sn 082-0267 carryingh Bond Avenue over Alton and Southern Railroad. | — | Executed | Keeley & Sons, Inc. $249,557 · | ||
| Jan 18, 2019 | 76M05 | MadisonDistrict 8 | Bridge repair and guardrail improvements on SN 060-0177 carrying I-55 over Maple Grove Road. | — | Executed | Keeley & Sons, Inc. $357,463 · | ||
| Jan 18, 2019 | 76M06 | BondDistrict 8 | Patching on IL 127 from Montgomery County line to IL 140. | — | Executed | G. M. Sipes Construction, Inc. $419,131 · | ||
| Jan 18, 2019 | 76M08 | GreeneDistrict 8 | Patching on US 67 from Pine Street to Walnut Street in Carrolton. | — | Executed | Kinney Contractors, Inc. $53,955 · | ||
| Jan 18, 2019 | 78455 | JeffersonDistrict 9 | Removal and replacement SN 041-055 carrying CH 42 over I-57 at Ina. | — | Executed | Sierra Bravo Contractors, LLC $2,683,572 · | ||
| Jan 18, 2019 | 78502 | MassacDistrict 9 | Removal and replacement of the existing structures (SN 064-0024 and SN 064-0028) carrying I-24 over CH13 (Country Club Road) near Metropolis. | — | Executed | E. T. Simonds Construction Company $4,921,275 · | ||
| Jan 18, 2019 | 78596 | UnionDistrict 9 | 1.3 miles of patching, resurfacing and sidewalk ramps along IL 146 in Anna. | — | Executed | E. T. Simonds Construction Company $1,235,395 · | ||
| Jan 18, 2019 | 78617 | UnionDistrict 9 | Scour repair below SN 091-0068 carrying IL 127 over Clear Creek south of Alto Pass. | — | Executed | Pinoy Construction Inc. $47,537 · | ||
| Jan 18, 2019 | 78630 | WhiteDistrict 9 | Inlaying 1.5" HMA, deck repairs, joint replacement and bearing replacement on SN 097-000 and 097-0004 carrying I-64 over the Wabash River into Indiana. | — | Executed | E. T. Simonds Construction Company $763,012 · | ||
| Jan 18, 2019 | 78650 | VariousDistrict 9 | Steel, bearing and joint repairs on 11 structures in Alexander, Hamilton and Jefferson Counties. (SN 041-0007, 0087, 0088, 0077, 0078, 002-0032, 033-0038, 0041-0041, 0042, 0097) | — | Executed | Sangamo Construction Company $1,642,481 · | ||
| Jan 18, 2019 | 78658 | FranklinDistrict 9 | 0.66 miles of HMA partial depth patching over existing PCC pavement on IL 149 from Ken Grey Boulevard to Joiner Street | — | Executed | E. T. Simonds Construction Company $134,883 · | ||
| Jan 18, 2019 | 78659 | FranklinDistrict 9 | 5.6 miles of replacing aggregate shoulder with a 2' safety shoulder consisting of 8" HMA on IL 14 from Mt. Zion Road to Ewing Road. | — | Executed | E. T. Simonds Construction Company $534,970 · | ||
| Jan 18, 2019 | 78667 | WilliamsonDistrict 9 | Bridge repairs and approach work on SN 100-0062 carrying Cambria Rd. over Big Muddy River, 1 mile south of Hurst. | — | Executed | E. T. Simonds Construction Company $299,154 · | ||
| Jan 18, 2019 | 78677 | VariousDistrict 9 | Cleaning and painting portions of 14 structures: 1 in Alexander County, 2 in Franklin County, 1 in Hamilton County, 8 in Jefferson County, 1 in Massac County, and 2 in White County. (SN 041-0039, 0040, 0041, 0042, 0077, 0078, 0087, 0088, 002-0032, 028-0038, 0041, 033-0012, 064-0003, 097-0024) | — | Executed | Venus Painting Co. $1,130,680 · | ||
| Jan 18, 2019 | 78693 | UnionDistrict 9 | 2.4 miles of milling and resurfacing of I-57 southbound from 0.5 miles south of IL 146 to 0.5 miles north of the rest area near the Cache River. | — | Executed | Southern Illinois Asphalt Co., Inc. $1,121,786 · | ||
| Jan 18, 2019 | 87710 | GrundyDistrict 3 | Pavement reconstruction, storm sewers, curb and gutter, sidewalk and roadway lighting, on Broadway Street from IL 113 to Park Street in Coal City. | — | Executed | D. Construction, Inc. $4,631,410 · | ||
| Jan 18, 2019 | 89712 | PeoriaDistrict 4 | Pavement reconstruction, PCC pavement, curb and gutter, storm sewers, PCC multi-use path, street lighting and pedestrian signals, on Dirksen Parkway from Middle Road to Airport Road. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $5,449,818 · | ||
| Jan 18, 2019 | 89732 | PeoriaDistrict 4 | Construction of 4' HMA shoulders with rumble strips, 2' aggregate shoulders and the reconstruction of ditches on Kickapoo-Edwards Road from Shamrock Lane to Countryside Lane. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $1,175,654 · | ||
| Jan 18, 2019 | 91568 | ChampaignDistrict 5 | Construct 7" PCC pavement, aggregate shoulder and culvert replacment on Sunny Acres Road from South Mahomet Road to US 150 in the Village of Mahomet. | — | Executed | Beniach Construction Co., Inc. $796,767 · | ||
| Jan 18, 2019 | 91569 | ChampaignDistrict 5 | Pavement reconstruction, PCC pavement, curb and gutter, storm sewer, street lighting and traffic signals on Prospect Avenue from Curtis Road to Windsor Rd. in the City of Champaign. | — | Executed | Feutz Contractors, Inc. $4,531,726 · | ||
| Jan 18, 2019 | 91575 | VermilionDistrict 5 | Replace the bridge carrying TR 54 over Baum Branch, 3 miles southwest of Jamaica. | — | Executed | Newell Construction Co., Inc. $284,521 · | ||
| Jan 18, 2019 | 93722 | BrownDistrict 6 | Resurfacing, lighting, and sidewalk improvements on Main Street, from Cross Street to Capitol Street in Mt. Sterling. | — | Executed | Rees Construction Company of Quincy $1,965,321 · | ||
| Jan 18, 2019 | 95841 | MaconDistrict 7 | Rehabilitate 058-3035 and 058-3036 carrying Mound Road over Spring Creek in the City of Decatur. | — | Executed | Sangamo Construction Company $2,504,685 · | ||
| Jan 18, 2019 | 95842 | FayetteDistrict 7 | Resurfacing on CH 28 from IL 37 to the Effingham County line. | — | Executed | Howell Paving, Inc. $1,613,463 · | ||
| Jan 18, 2019 | 97682 | JerseyDistrict 8 | County-wide guardrail replacement and/or repair at various locations in Jersey County. | — | Executed | Clevenger Contractors, Inc. $884,774 · | ||
| Jan 18, 2019 | 97686 | MadisonDistrict 8 | Construction of roundabouts at Broadway/St. Rose Road, and at Iberg Road/ Veterans Honor Parkway, in the City of Highland. | — | Executed | Stutz Excavating, Inc. $1,070,995 · | ||
| Jan 18, 2019 | 99584 | UnionDistrict 9 | Replace the bridge carrying TR 203 (Nash Road) over Big Creek, located 3 miles southeast of Anna. | — | Executed | Samron Midwest Contracting, Inc. $254,345 · | ||
| Jan 18, 2019 | 99610 | WilliamsonDistrict 9 | Pavement widening, resurfacing, and water main improvements on East Grand Avenue, from Hofer Road to Hurricane Road in Crainville. | — | Executed | Samron Midwest Contracting, Inc. $872,797 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.