D2 RS 2019-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martin & Company Excavating Low bidder | $149,653 | ||
| 2 | William Charles Construction Company, LLC | $169,205 | +13.1% | |
| 3 | Rock Road Companies, Inc. | $212,296 | +41.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martin & Compan… | #2 William Charles… | #3 Rock Road Compa… |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0028415 | GEOTECHNICAL REINF | 287 | SQ YD | $4.50 | $1.80 | $5.00 | |
| 2 | 30300106 | AGG SUBGRADE IMPR 6 | 287 | SQ YD | $19.00 | $3.31 | $18.50 | |
| 3 | 40600290 | BIT MATLS TACK CT | 2,780 | POUND | $1.00 | $0.9200 | $1.25 | |
| 4 | 40600525 | LEV BIND HM N50 | 5 | TON | $150.00 | $531.98 | $275.00 | |
| 5 | 40603335 | HMA SC "D" N50 | 692 | TON | $73.30 | $83.62 | $110.00 | |
| 6 | 44000157 | HMA SURF REM 2 | 6,178 | SQ YD | $4.78 | $2.75 | $3.75 | |
| 7 | 44201794 | CL D PATCH T3 12 | 17 | SQ YD | $123.00 | $272.00 | $350.00 | |
| 8 | 44201796 | CL D PATCH T4 12 | 270 | SQ YD | $104.00 | $150.03 | $195.00 | |
| 9 | 60255500 | MAN ADJUST | 4 | EACH | $710.00 | $2,174.86 | $1,150.00 | |
| 10 | 60260100 | INLETS ADJUST | 6 | EACH | $1,000.00 | $1,300.81 | $1,400.00 | |
| 11 | 60265700 | VV ADJUST | 6 | EACH | $500.00 | $2,078.03 | $1,200.00 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $7,533.00 | $3,136.18 | $12,500.00 | |
| 13 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $2,600.00 | $2,200.25 | $2,200.00 | |
| 14 | 70300100 | SHORT TERM PAVT MKING | 300 | FOOT | $1.50 | $1.13 | $5.26 | |
| 15 | 70300150 | SHRT TRM PAVT MK REM | 50 | SQ FT | $4.75 | $4.20 | $4.20 | |
| 16 | 78001110 | PAINT PVT MK LINE 4 | 6,406 | FOOT | $0.4000 | $0.3500 | $0.3500 | |
| 17 | 78001150 | PAINT PVT MK LINE 12 | 40 | FOOT | $3.00 | $2.10 | $2.10 | |
| 18 | 78100100 | RAISED REFL PAVT MKR | 38 | EACH | $80.00 | $75.01 | $75.00 | |
| 19 | 78300200 | RAISED REF PVT MK REM | 38 | EACH | $15.00 | $65.78 | $25.00 |