16-09129-00-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Newell Construction Co., Inc. Low bidder | $284,521 | ||
| 2 | Big O Services, LLC | $286,275 | +0.6% | |
| 3 | Stark Excavating, Inc. | $296,739 | +4.3% | |
| 4 | White Construction, Inc. | $296,799 | +4.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Newell Construc… | #2 Big O Services,… | #3 Stark Excavatin… | #4 White Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | XX004566 | CONCRETE CUT-OFF WALL | 7.9 | CU YD | $575.00 | $300.00 | $425.00 | $500.00 | |
| 2 | X7011830 | TRAF CONT-PROT BLR 21 | 1 | EACH | $1,150.00 | $2,000.00 | $2,600.00 | $5,000.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $4,540.00 | $2,100.00 | $2,000.00 | $2,500.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 112 | CU YD | $17.50 | $49.00 | $50.00 | $30.00 | |
| 5 | 20300100 | CHANNEL EXCAVATION | 167 | CU YD | $8.00 | $49.00 | $17.00 | $20.00 | |
| 6 | 25000200 | SEEDING CL 2 | 0.25 | ACRE | $6,200.00 | $6,616.00 | $6,000.00 | $3,000.00 | |
| 7 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $1.15 | $3.00 | $2.00 | $1.20 | |
| 8 | 25000500 | PHOSPHORUS FERT NUTR | 23 | POUND | $1.15 | $3.00 | $2.00 | $1.20 | |
| 9 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $1.15 | $3.00 | $2.00 | $1.20 | |
| 10 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $6,200.00 | $6,616.00 | $6,000.00 | $3,000.00 | |
| 11 | 28000250 | TEMP EROS CONTR SEED | 25 | POUND | $5.00 | $5.00 | $3.50 | $50.00 | |
| 12 | 28000305 | TEMP DITCH CHECKS | 48 | FOOT | $12.50 | $6.00 | $10.50 | $7.25 | |
| 13 | 28000400 | PERIMETER EROS BAR | 699 | FOOT | $1.00 | $3.50 | $3.60 | $3.50 | |
| 14 | 28100807 | STONE DUMP RIP CL A4 | 240 | TON | $72.00 | $75.00 | $57.50 | $60.00 | |
| 15 | 28200200 | FILTER FABRIC | 290 | SQ YD | $0.0100 | $2.00 | $0.0100 | $5.00 | |
| 16 | 40200800 | AGG SURF CSE B | 384 | TON | $30.00 | $30.00 | $30.00 | $35.00 | |
| 17 | 50100100 | REM EXIST STRUCT | 1 | EACH | $12,000.00 | $10,000.00 | $18,000.00 | $15,000.00 | |
| 18 | 50200100 | STRUCTURE EXCAVATION | 133 | CU YD | $8.00 | $60.00 | $18.00 | $20.00 | |
| 19 | 50300225 | CONC STRUCT | 33.9 | CU YD | $775.00 | $800.00 | $850.00 | $900.00 | |
| 20 | 50400505 | P P CONC DK BM 27 DP | 1,718 | SQ FT | $75.00 | $73.00 | $73.00 | $68.00 | |
| 21 | 50800205 | REINF BARS, EPOXY CTD | 3,940 | POUND | $1.95 | $1.90 | $2.00 | $2.50 | |
| 22 | 50900205 | STEEL RAILING TY S1 | 128 | FOOT | $113.10 | $120.00 | $114.00 | $121.00 | |
| 23 | 51201600 | FUR STL PILE HP12X53 | 340 | FOOT | $42.00 | $28.00 | $55.00 | $55.00 | |
| 24 | 51202305 | DRIVING PILES | 340 | FOOT | $1.00 | $0.1000 | $0.0100 | $1.00 | |
| 25 | 51203600 | TEST PILE ST HP12X53 | 2 | EACH | $8,000.00 | $6,000.00 | $4,250.00 | $4,500.00 | |
| 26 | 51204650 | PILE SHOES | 12 | EACH | $100.00 | $180.00 | $150.00 | $150.00 | |
| 27 | 51500100 | NAME PLATES | 1 | EACH | $300.00 | $600.00 | $515.00 | $500.00 | |
| 28 | 59300100 | CONTR LOW-STRENG MATL | 45 | CU YD | $88.00 | $85.00 | $100.00 | $120.00 | |
| 29 | 67100100 | MOBILIZATION | 1 | L SUM | $11,000.00 | $8,000.00 | $17,500.00 | $17,500.00 | |
| 30 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $40.00 | $40.00 | $40.00 | $40.00 |