D2 RS 2019-3
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martin & Company Excavating Low bidder | $210,983 | ||
| 2 | Civil Constructors, Inc. | $211,494 | +0.2% | |
| 3 | Valley Construction Co. | $230,491 | +9.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martin & Compan… | #2 Civil Construct… | #3 Valley Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | 40600295 | P BIT MATLS TACK CT | 2,710 | POUND | $2.00 | $3.00 | $0.5000 | |
| 2 | 40603545 | P HMA SC "D" N90 | 676 | TON | $156.00 | $168.00 | $180.00 | |
| 3 | 44000157 | HMA SURF REM 2 | 6,023 | SQ YD | $5.66 | $6.50 | $6.00 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $11,000.00 | $12,600.00 | $21,300.00 | |
| 5 | 70100420 | TRAF CONT-PROT 701411 | 3 | EACH | $1,500.00 | $150.00 | $1,000.00 | |
| 6 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $12,000.00 | $1.00 | $100.00 | |
| 7 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $25,000.00 | $27,200.00 | $24,800.00 | |
| 8 | 70300100 | SHORT TERM PAVT MKING | 422 | FOOT | $1.50 | $1.00 | $3.00 | |
| 9 | 70300150 | SHRT TRM PAVT MK REM | 141 | SQ FT | $5.00 | $5.00 | $10.00 | |
| 10 | 78000200 | THPL PVT MK LINE 4 | 4,358 | FOOT | $1.80 | $1.35 | $2.00 | |
| 11 | 78000500 | THPL PVT MK LINE 8 | 141 | FOOT | $4.00 | $2.80 | $6.00 | |
| 12 | 78100100 | RAISED REFL PAVT MKR | 26 | EACH | $125.00 | $65.00 | $300.00 | |
| 13 | 78300200 | RAISED REF PVT MK REM | 26 | EACH | $20.00 | $50.00 | $80.00 |