D9 SCOUR REPAIR 2018-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Pinoy Construction Inc. Low bidder | $47,537 | ||
| 2 | CSD Environmental Services, Inc. | $56,244 | +18.3% | |
| 3 | Brewster Companies, Inc. | $67,617 | +42.2% | |
| 4 | K. D. Crain and Sons, Inc. | $73,319 | +54.2% | |
| 5 | Mayer Landscaping, Inc. | $79,670 | +67.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Pinoy Construct… | #2 CSD Environment… | #3 Brewster Compan… | #4 K. D. Crain and… | #5 Mayer Landscapi… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 20200100 | EARTH EXCAVATION | 15 | CU YD | $76.27 | $44.79 | $14.50 | $250.00 | $150.00 | |
| 2 | 28100107 | STONE RIPRAP CL A4 | 101 | SQ YD | $73.79 | $109.93 | $157.00 | $150.00 | $110.00 | |
| 3 | 28100111 | STONE RIPRAP CL A6 | 316 | SQ YD | $84.88 | $82.76 | $92.00 | $90.00 | $128.50 | |
| 4 | 28200200 | FILTER FABRIC | 382 | SQ YD | $2.29 | $1.78 | $2.75 | $9.50 | $4.20 | |
| 5 | 50104650 | SLOPE WALL REMOV | 30 | SQ YD | $30.51 | $49.79 | $32.00 | $60.00 | $85.00 | |
| 6 | 67100100 | MOBILIZATION | 1 | L SUM | $3,319.91 | $9,313.00 | $8,250.00 | $4,800.00 | $10,000.00 | |
| 7 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $5,726.40 | $5,500.00 | $7,800.00 | $10,500.00 | $8,750.00 | |
| 8 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $91.52 | $95.00 | $315.00 | $375.00 | $200.00 |