Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Aug 3, 2018 | 60Y22 | Lake, Mchenry District 1 |
145N-4(14) · | — | $1,138,109 | Alliance Contractors, Inc. | 4 | |
| Aug 3, 2018 | PA061 | Cook District 1 |
CHICAGO EXECUTIVE · | — | $1,120,202 | Plote Construction, Inc. | 2 | |
| Aug 3, 2018 | 66E24 | Iroquois District 3 |
(136BR-1)BR · | — | $1,085,786 | Iroquois Paving Corporation | 1 | |
| Aug 3, 2018 | 72J96 | Various District 6 |
D6 CABLE/GUARDRAIL 2017-4 · | — | $1,012,115 | COLLINS & HERMANN, INC. | 1 | |
| Aug 3, 2018 | 87642 | Grundy District 3 |
16-00158-00-BR · | — | $984,309 | D. Construction, Inc. | 2 | |
| Aug 3, 2018 | 76L64 | Washington District 8 |
95-(3,4)PP-1 · | — | $984,001 | Keeley & Sons, Inc. | 2 | |
| Aug 3, 2018 | KE016 | Henry District 2 |
KEWANEE MUNICIPAL · | — | $846,629 | Brandt Construction Co. | 2 | |
| Aug 3, 2018 | 87643 | Grundy District 3 |
16-00159-00-BR · | — | $793,264 | Riber Construction, Inc. | 3 | |
| Aug 3, 2018 | 76L63 | Monroe, St. Clair District 8 |
67-(1,2,3)PP-1,82-(6,7,8)PP-1 · | — | $785,252 | Keeley & Sons, Inc. | 1 | |
| Aug 3, 2018 | MS009 | Brown District 6 |
MT. STERLING MUNICIPAL · | — | $777,778 | COLLINS & HERMANN, INC. | 3 | |
| Aug 3, 2018 | 78663 | Alexander District 9 |
D-9 APPROACH PAVEMENT 2018-1 · | — | $775,259 | E. T. Simonds Construction Company | 1 | |
| Aug 3, 2018 | 62G15 | Cook District 1 |
2018-009-BP · | — | $693,300 | Capital Industrial Services | 4 | |
| Aug 3, 2018 | GR009 | Bond District 8 |
GREENVILLE · | — | $685,251 | Howell Paving, Inc. | 2 | |
| Aug 3, 2018 | 61E95 | Cook District 1 |
13-F3000-24-BT · | — | $607,080 | Iroquois Paving Corporation | 3 | |
| Aug 3, 2018 | 66J40 | Bureau, Putnam District 3 |
(06-3,078-1)MBPM-6 · | — | $556,692 | D. Construction, Inc. | 2 | |
| Aug 3, 2018 | 66H27 | Bureau District 3 |
(06-2HB)BRR · | — | $535,864 | D. Construction, Inc. | 3 | |
| Aug 3, 2018 | SA033 | Marion District 8 |
SALEM-LECKRONE · | — | $493,953 | Howell Paving, Inc. | 1 | |
| Aug 3, 2018 | 62G49 | Various District 1 |
2018-FNC-1 · | — | $475,477 | Fence Masters, Inc. | 2 | |
| Aug 3, 2018 | 68E59 | Various District 4 |
D4 FIBER OPTIC 2019 · | — | $464,500 | Oberlander Electric Co. | 3 | |
| Aug 3, 2018 | 61E78 | Cook District 1 |
15-00115-00-BT · | — | $448,663 | A Lamp Concrete Contractors, Inc. | 8 | |
| Aug 3, 2018 | 64M37 | Henry District 2 |
(37-2)M-1 · | — | $428,582 | Electrico, Inc. | 1 | |
| Aug 3, 2018 | 61E92 | Dupage District 1 |
18-00113-00-RS · | — | $415,550 | A Lamp Concrete Contractors, Inc. | 5 | |
| Aug 3, 2018 | 68C49 | Marshall District 4 |
123-CR · | — | $389,628 | Stark Excavating, Inc. | 5 | |
| Aug 3, 2018 | 89746 | Tazewell District 4 |
16-00119-00-BT · | — | $359,285 | Stark Excavating, Inc. | 7 | |
| Aug 3, 2018 | 61E84 | Cook District 1 |
14-00154-00-BT · | — | $355,260 | Iroquois Paving Corporation | 4 | |
| Aug 3, 2018 | 46904 | Clinton District 8 |
ELDON HAZLET 2018 · | — | $348,980 | Keeley & Sons, Inc. | 4 | |
| Aug 3, 2018 | 74834 | Lawrence District 7 |
D7 BRIDGE REPAIRS 2018-5 · | — | $348,595 | Keeley & Sons, Inc. | 3 | |
| Aug 3, 2018 | 68E09 | Fulton District 4 |
(127)CR · | — | $342,404 | Lee Hood d/b/a Hood Demolition & Excavation | 3 | |
| Aug 3, 2018 | 70D45 | Various District 5 |
D5 LIGHTING REPAIRS 2019-2 · | — | $322,470 | Egizii Electric, Inc., A Division of EEI Holding Corporation | 3 | |
| Aug 3, 2018 | 62G44 | Lake District 1 |
24-I-1 · | — | $311,742 | Copenhaver Construction, Inc. | 8 | |
| Aug 3, 2018 | 68E55 | Marshall District 4 |
(3)I-1,DR · | — | $297,057 | Advanced Asphalt Company | 1 | |
| Aug 3, 2018 | 93718 | Logan District 6 |
15-00066-03-BR · | — | $295,457 | Otto Baum Company, Inc. | 6 | |
| Aug 3, 2018 | 61E85 | Dupage District 1 |
17-00078-00-BR · | — | $289,477 | Areatha Construction Co., Inc. | 7 | |
| Aug 3, 2018 | 87611 | Grundy District 3 |
14-00001-00-SW · | — | $284,602 | D. Construction, Inc. | 4 | |
| Aug 3, 2018 | 68088 | Tazewell District 4 |
(L-15D-LBR)I · | — | $262,717 | Lee Hood d/b/a Hood Demolition & Excavation | 5 | |
| Aug 3, 2018 | 70D44 | Various District 5 |
D5 LIGHTING REPAIRS 2019-1 · | — | $252,092 | Bodine Electric of Decatur | 3 | |
| Aug 3, 2018 | KE015 | Henry District 2 |
KEWANEE MUNICIPAL · | — | $244,140 | Brandt Construction Co. | 2 | |
| Aug 3, 2018 | 78661 | Saline, Jefferson District 9 |
124CR-1;109CR-1 · | — | $191,911 | Haier Plumbing and Heating, Inc. | 3 | |
| Aug 3, 2018 | 99602 | White District 9 |
10-06129-00-BR · | — | $171,534 | Dees, Inc. | 2 | |
| Aug 3, 2018 | MB030 | Mcdonough District 4 |
MACOMB MUNICIPAL · | — | $165,804 | J.H. Moore, Inc. | 4 | |
| Aug 3, 2018 | 91556 | Vermilion District 5 |
17-00016-00-SW · | — | $157,300 | Duce Construction Company | 7 | |
| Aug 3, 2018 | 66J33 | Grundy District 3 |
(32-3)K & PP · | — | $136,744 | D. Construction, Inc. | 3 | |
| Aug 3, 2018 | 78657 | Gallatin District 9 |
D9 PATCH 2018-4 · | — | $128,569 | G. M. Sipes Construction, Inc. | 3 | |
| Aug 3, 2018 | 70D42 | Various District 5 |
D5 WEED SPRAYING 2019-1 · | — | $127,723 | The Daltons Inc. | 1 | |
| Aug 3, 2018 | 78666 | Various District 9 |
D9 DECK SEAL 2019-1 · | — | $95,200 | All States Painting, Inc. | 3 | |
| Aug 3, 2018 | 66J35 | Livingston District 3 |
(15Z)PP · | — | $94,034 | G. M. Sipes Construction, Inc. | 4 | |
| Aug 3, 2018 | 62F85 | Will District 1 |
2017-050DTR · | — | $92,279 | Clean Cut Tree Service, Inc. | 2 | |
| Aug 3, 2018 | 61E39 | Cook District 1 |
15-00063-00-BT · | — | $89,900 | Chicagoland Paving Contractors, Inc. | 10 | |
| Aug 3, 2018 | 68E46 | Knox District 4 |
48-29RA(L-1) · | — | $81,493 | Laser Electric, Inc. | 3 | |
| Aug 3, 2018 | 78665 | Johnson District 9 |
D9 WEED SPRAY 2019-1 · | — | $54,842 | The Daltons Inc. | 3 | |
| Aug 3, 2018 | 76J69 | St. Clair District 8 |
1-BR,DS-2 · | — | $36,999 | Keeley & Sons, Inc. | 3 | |
| Aug 3, 2018 | 78649 | Pope District 9 |
D9 RIPRAP 2019-1 · | — | $36,232 | Roadworks, LLC | 7 | |
| Aug 3, 2018 | 66J39 | Lasalle District 3 |
2019-1 WEED SPRAY · | — | $35,624 | Endrizzi Contracting, Inc | 2 | |
| Aug 3, 2018 | 78634 | Alexander District 9 |
D9 DECK SEAL 2018-2 · | — | $23,649 | E. T. Simonds Construction Company | 2 | |
| Jun 15, 2018 | 61E53 | Mchenry District 1 |
06-00329-01-PW · | — | $45,891,419 | Plote Construction, Inc. | 4 | |
| Jun 15, 2018 | 66B64 | Livingston District 3 |
(53-5)R&I · | — | $40,969,992 | Kankakee Valley Construction Company, Inc. | 2 | |
| Jun 15, 2018 | 60Y39 | Cook District 1 |
(1517&1415)R-2 · | — | $39,458,694 | Kenny Construction Company | 4 | |
| Jun 15, 2018 | 76G39 | St. Clair District 8 |
1BR-1-1 · | — | $24,340,042 | Millstone Weber LLC DO NOT USE | 2 | |
| Jun 15, 2018 | 60P55 | Will District 1 |
2011-045-I · | — | $21,260,736 | Meade Inc. | 4 | |
| Jun 15, 2018 | 60V55 | Lake District 1 |
A-WRS-2 · | — | $14,793,279 | Berger Excavating Contractors, Inc. | 2 | |
| Jun 15, 2018 | 66D24 | Kendall District 3 |
(1)R,I · | — | $12,531,371 | D. Construction, Inc. | 3 | |
| Jun 15, 2018 | 78295 | Jackson District 9 |
(5-3)R-1,N-1,B-5,BR-1,B-6,BR-2 · | — | $11,957,202 | E. T. Simonds Construction Company | 2 | |
| Jun 15, 2018 | 60Y40 | Cook District 1 |
(1517&1415)I-14 · | — | $10,742,877 | Herlihy Mid-Continent Company | 5 | |
| Jun 15, 2018 | 62C84 | Mchenry District 1 |
(23&24)RS-2 · | — | $7,663,587 | Peter Baker & Son Co. | 1 | |
| Jun 15, 2018 | 64H61 | Ogle District 2 |
(106,107)RS-5 · | — | $5,745,379 | Rock Road Companies, Inc. | 3 | |
| Jun 15, 2018 | 62F58 | Cook District 1 |
2017-036RS · | — | $5,720,330 | K-Five Construction Corporation | 1 | |
| Jun 15, 2018 | 68663 | Mercer District 4 |
(123B)BR-1 · | — | $5,354,351 | General Constructors Inc. of the Quad Cities | 5 | |
| Jun 15, 2018 | 60T01 | Mchenry District 1 |
11-N · | — | $5,110,204 | Berger Excavating Contractors, Inc. | 9 | |
| Jun 15, 2018 | 62D12 | Cook District 1 |
7Y-RS-8 · | — | $4,797,229 | Arrow Road Construction Co. | 2 | |
| Jun 15, 2018 | 68825 | Mcdonough District 4 |
118RS-3;119RS-4 · | — | $4,722,460 | Gunther Construction, a div of UCM, Inc. | 1 | |
| Jun 15, 2018 | 78522 | Union District 9 |
(91-4)B-1 · | — | $4,604,795 | E. T. Simonds Construction Company | 2 | |
| Jun 15, 2018 | 66D75 | Lasalle District 3 |
(1Z,1,1R,2)RS-4 · | — | $4,570,417 | Advanced Asphalt Company | 1 | |
| Jun 15, 2018 | 76H45 | St. Clair District 8 |
146RS-4,122RS-2 · | — | $4,452,979 | Christ Bros. Asphalt, Inc. | 2 | |
| Jun 15, 2018 | 62C74 | Lake District 1 |
2016-021RS · | — | $4,377,353 | Peter Baker & Son Co. | 2 | |
| Jun 15, 2018 | 62D16 | Dupage District 1 |
(CY,C&J)RS-6 · | — | $4,186,352 | K-Five Construction Corporation | 3 | |
| Jun 15, 2018 | 76K18 | St. Clair District 8 |
(29-1,28-1)RS-5 · | — | $4,174,426 | Christ Bros. Asphalt, Inc. | 2 | |
| Jun 15, 2018 | 62F74 | Cook District 1 |
(78-1&78-3)RS-2 · | — | $4,072,377 | R. W. Dunteman Company | 5 | |
| Jun 15, 2018 | 62D65 | Cook District 1 |
3056-RS-2 · | — | $3,487,784 | J. A. Johnson Paving Company | 6 | |
| Jun 15, 2018 | 72H54 | Schuyler District 6 |
(47,111)RS-3,BDR(112)RS-2,N · | — | $3,369,826 | Illinois Valley Paving, a div of UCM, Inc. | 1 | |
| Jun 15, 2018 | 70D21 | Mclean District 5 |
(1,2)RS-3 · | — | $3,312,391 | Rowe Construction, a div of UCM, Inc. | 1 | |
| Jun 15, 2018 | 62G08 | Cook District 1 |
2017-065BR · | — | $2,894,607 | Lorig Construction Company | 4 | |
| Jun 15, 2018 | 62D64 | Cook District 1 |
2016-084RS · | — | $2,888,000 | K-Five Construction Corporation | 3 | |
| Jun 15, 2018 | 76H01 | St. Clair District 8 |
124,125RS-1 · | — | $2,790,507 | The Kilian Corporation | 2 | |
| Jun 15, 2018 | 91553 | Champaign District 5 |
17-00445-00-RS · | — | $2,588,530 | Open Road Paving Company LLC | 2 | |
| Jun 15, 2018 | 85668 | Rock Island District 2 |
15-00190-00-RS · | — | $2,563,526 | Valley Construction Co. | 4 | |
| Jun 15, 2018 | 87654 | Bureau District 3 |
12-00075-00-RP · | — | $2,350,963 | Advanced Asphalt Company | 1 | |
| Jun 15, 2018 | 62G12 | Cook, Kane District 1 |
2018-001-TS · | — | $2,323,187 | H & H Electric Co. | 3 | |
| Jun 15, 2018 | 66J21 | Kankakee District 3 |
D3 INTERMITTENT RS 2018-3 · | — | $2,078,000 | Gallagher Asphalt Corporation | 2 | |
| Jun 15, 2018 | 46499 | Various District 7 |
D-7 OVD SIN STR REPL 19-04 · | — | $2,068,925 | Kujo, Inc. | 3 | |
| Jun 15, 2018 | 74852 | Wayne District 7 |
D7 HMA SAFETY SHLD 2018-4 · | — | $1,984,352 | Howell Paving, Inc. | 1 | |
| Jun 15, 2018 | 70786 | Douglas District 5 |
(20 RS-4)(21X)RS-2,21 RS-5 · | — | $1,928,991 | Howell Paving, Inc. | 2 | |
| Jun 15, 2018 | 76L50 | Various District 8 |
DIST 8 GUARDRAIL 2019-1 · | — | $1,920,462 | Illini Excavation & Reclamation, Inc. | 1 | |
| Jun 15, 2018 | 68D69 | Tazewell District 4 |
11RS-12 · | — | $1,885,690 | Advanced Asphalt Company | 1 | |
| Jun 15, 2018 | 76J29 | Monroe, St. Clair District 8 |
67-(1,2,3)-I,82-(7,8)-I · | — | $1,831,998 | Christ Bros. Asphalt, Inc. | 2 | |
| Jun 15, 2018 | 76K77 | St. Clair District 8 |
(119,59,118,117)RS-3 · | — | $1,824,894 | The Kilian Corporation | 2 | |
| Jun 15, 2018 | 62G16 | Cook District 1 |
2018-008-BJR · | — | $1,808,950 | D. Construction, Inc. | 3 | |
| Jun 15, 2018 | 62B61 | Lake District 1 |
530N-3 · | — | $1,800,000 | Berger Excavating Contractors, Inc. | 4 | |
| Jun 15, 2018 | 76J98 | Madison District 8 |
31,37,32RS-3,T-2B-R-2 · | — | $1,799,014 | The Kilian Corporation | 2 | |
| Jun 15, 2018 | 91560 | Mclean District 5 |
14-00024-06-RS · | — | $1,787,868 | H. J. Eppel & Co. | 2 | |
| Jun 15, 2018 | 95835 | Cumberland District 7 |
16-00081-00-GR · | — | $1,666,951 | COLLINS & HERMANN, INC. | 1 |
Source: IDOT Transportation Bulletin "Unit Price Tabulation of Bids" for each letting. Totals are as read; IDOT does not publish an engineer's estimate there, so estimate columns stay blank. Bid Potato backfills the last two years. Confirm against IDOT's As Accepted tabulation.