14-00001-00-SW
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $284,602 | ||
| 2 | Scanlon Excavating & Concrete, Inc. | $292,830 | +2.9% | |
| 3 | Davis Concrete Construction Co. | $317,326 | +11.5% | |
| 4 | P. T. Ferro Construction Co. | $355,108 | +24.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Scanlon Excavat… | #3 Davis Concrete … | #4 P. T. Ferro Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0326862 | STRUCTURE ADJ | 20 | EACH | $350.00 | $400.00 | $325.00 | $250.00 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $7,500.00 | $6,000.00 | $5,800.00 | $7,500.00 | |
| 3 | 20101200 | TREE ROOT PRUNING | 25 | EACH | $110.00 | $30.00 | $100.00 | $150.00 | |
| 4 | 21101615 | TOPSOIL F & P 4 | 1,775 | SQ YD | $8.00 | $5.00 | $4.00 | $4.50 | |
| 5 | 25000110 | SEEDING CL 1A | 0.37 | ACRE | $3,000.00 | $3,500.00 | $3,000.00 | $2,420.00 | |
| 6 | 25000400 | NITROGEN FERT NUTR | 33 | POUND | $5.50 | $5.00 | $5.00 | $2.00 | |
| 7 | 25000500 | PHOSPHORUS FERT NUTR | 33 | POUND | $5.50 | $5.00 | $5.00 | $2.00 | |
| 8 | 25000600 | POTASSIUM FERT NUTR | 33 | POUND | $5.50 | $5.00 | $5.00 | $2.00 | |
| 9 | 25100630 | EROSION CONTR BLANKET | 1,775 | SQ YD | $2.00 | $4.00 | $1.25 | $8.00 | |
| 10 | 28000400 | PERIMETER EROS BAR | 400 | FOOT | $3.85 | $4.00 | $2.00 | $8.00 | |
| 11 | 28000510 | INLET FILTERS | 10 | EACH | $250.00 | $150.00 | $50.00 | $1.00 | |
| 12 | 42400200 | PC CONC SIDEWALK 5 | 27,200 | SQ FT | $7.00 | $6.50 | $8.20 | $8.50 | |
| 13 | 42400800 | DETECTABLE WARNINGS | 550 | SQ FT | $25.00 | $35.00 | $21.50 | $12.00 | |
| 14 | 44000200 | DRIVE PAVEMENT REM | 95 | SQ YD | $8.00 | $10.00 | $25.00 | $20.00 | |
| 15 | 44000500 | COMB CURB GUTTER REM | 45 | FOOT | $8.00 | $20.00 | $15.00 | $20.00 | |
| 16 | 44000600 | SIDEWALK REM | 12,300 | SQ FT | $1.50 | $1.80 | $1.85 | $2.20 | |
| 17 | 60603800 | COMB CC&G TB6.12 | 45 | FOOT | $35.00 | $75.00 | $45.00 | $100.00 | |
| 18 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $16,500.00 | $13,800.00 | $21,000.00 | |
| 19 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $5,000.00 | $7,500.00 | $2,500.00 | $14,800.00 | |
| 20 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $0.0100 | $2,500.00 | $7,000.00 | $100.00 | |
| 21 | 78000400 | THPL PVT MK LINE 6 | 1,200 | FOOT | $2.10 | $5.00 | $2.30 | $2.30 | |
| 22 | 78000600 | THPL PVT MK LINE 12 | 260 | FOOT | $4.20 | $5.00 | $5.95 | $5.95 |