D4 FIBER OPTIC 2019
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Oberlander Electric Co. Low bidder | $464,500 | ||
| 2 | Bodine Electric of Decatur | $570,249 | +22.8% | |
| 3 | Laser Electric, Inc. | $680,652 | +46.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Oberlander Elec… | #2 Bodine Electric… | #3 Laser Electric,… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $18,734.00 | $12,423.60 | $60,000.00 | |
| 2 | X8110456 | CON AT ST 1.5 SS | 40 | FOOT | $161.00 | $70.99 | $61.00 | |
| 3 | X8130110 | JUNCTION BOX SPL | 7 | EACH | $1,519.00 | $1,313.35 | $1,695.00 | |
| 4 | X8130115 | DRILL EX JUNCTION BOX | 1 | EACH | $248.36 | $709.92 | $250.00 | |
| 5 | X8710030 | FIB OPT CBL 48F SM | 75,102 | FOOT | $2.02 | $3.79 | $4.28 | |
| 6 | Z0033052 | COMMUNICATIONS VAULT | 24 | EACH | $1,792.00 | $2,768.69 | $1,475.00 | |
| 7 | 67100100 | MOBILIZATION | 1 | L SUM | $15,118.00 | $10,057.20 | $10,250.00 | |
| 8 | 81028340 | UNDRGRD C PVC 1 1/2 | 23,940 | FOOT | $8.75 | $7.10 | $9.56 | |
| 9 | 81028350 | UNDRGRD C PVC 2 | 210 | FOOT | $6.16 | $11.13 | $11.00 | |
| 10 | 81300550 | JUN BX SS AS 12X12X6 | 8 | EACH | $624.25 | $810.21 | $648.00 | |
| 11 | 87900200 | DRILL EX HANDHOLE | 10 | EACH | $285.00 | $514.69 | $265.00 |