D7 HMA SAFETY SHLD 2018-4
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Howell Paving, Inc. Low bidder | $1,984,352 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Howell Paving, … |
|---|---|---|---|---|---|---|
| 1 | X4404260 | PAVED SHLD REMOVAL SP | 15,653 | SQ YD | $7.14 | |
| 2 | X7015005 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $72.15 | |
| 3 | 20200600 | EXC & GR EX SHOULDER | 934 | UNIT | $204.70 | |
| 4 | 48102100 | AGG WEDGE SHLD TYPE B | 1,722 | TON | $41.84 | |
| 5 | 48203029 | HMA SHOULDERS 8 | 41,715 | SQ YD | $35.28 | |
| 6 | 64200108 | SHOULDER RUM STRIP 8 | 103,855 | FOOT | $0.1800 | |
| 7 | 67100100 | MOBILIZATION | 1 | L SUM | $75,161.18 | |
| 8 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $26,200.00 | |
| 9 | 70103815 | TR CONT SURVEILLANCE | 45 | CAL DA | $0.00 | |
| 10 | 78001110 | PAINT PVT MK LINE 4 | 155,706 | FOOT | $0.1000 |