3056-RS-2
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | J. A. Johnson Paving Company Low bidder | $3,487,784 | ||
| 2 | Plote Construction, Inc. | $3,665,192 | +5.1% | |
| 3 | Arrow Road Construction Co. | $3,917,485 | +12.3% | |
| 4 | K-Five Construction Corporation | $3,926,948 | +12.6% | |
| 5 | R. W. Dunteman Company | $4,148,938 | +19.0% | |
| 6 | Builders Paving, LLC | $4,696,800 | +34.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J. A. Johnson P… | #2 Plote Construct… | #3 Arrow Road Cons… | #4 K-Five Construc… | #5 R. W. Dunteman … | #6 Builders Paving… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | K0029618 | WEED CONT BROADLF TRF | 0.5 | GALLON | $388.00 | $388.00 | $100.00 | $6.00 | $388.00 | $2,200.00 | |
| 2 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $7,600.00 | $7,600.00 | $4,000.00 | $6,000.00 | $7,600.00 | $9,000.00 | |
| 3 | X2010350 | TREE REMOV ACRES SPL | 0.2 | ACRE | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | |
| 4 | X4240800 | DETECTABLE WARN SPL | 694 | SQ FT | $33.00 | $32.00 | $35.00 | $32.00 | $35.00 | $27.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 1,184 | SQ YD | $2.75 | $10.00 | $4.50 | $2.50 | $12.45 | $24.00 | |
| 6 | X5537800 | SS CLEANED 12 | 1,525 | FOOT | $4.50 | $2.00 | $2.50 | $4.50 | $4.50 | $4.50 | |
| 7 | X6030310 | FR & LIDS ADJUST SPL | 164 | EACH | $780.00 | $595.00 | $825.00 | $600.00 | $780.00 | $600.00 | |
| 8 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $37,050.00 | $50,000.00 | $121,000.00 | $195,000.00 | $96,000.00 | $110,000.00 | |
| 9 | X7015005 | CHANGEABLE MESSAGE SN | 30 | CAL DA | $30.00 | $100.00 | $30.00 | $30.00 | $40.00 | $100.00 | |
| 10 | X7030005 | TEMP PAVT MKING REMOV | 24,324 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $1.55 | $1.55 | |
| 11 | Z0004562 | COMB C C&G REM & REPL | 6,627 | FOOT | $36.50 | $36.00 | $30.00 | $35.00 | $30.00 | $38.00 | |
| 12 | Z0018500 | DRAINAGE STR CLEANED | 305 | EACH | $305.00 | $230.00 | $238.00 | $305.00 | $305.00 | $305.00 | |
| 13 | Z0018600 | DRAINAGE STR RECONST | 10 | EACH | $1,300.00 | $1,100.00 | $1,500.00 | $1,200.00 | $1,300.00 | $1,200.00 | |
| 14 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $16.00 | $17.00 | $16.00 | $16.00 | $17.00 | $17.00 | |
| 15 | Z0037300 | PAVT GROOVING | 70,325 | SQ YD | $4.07 | $4.30 | $7.62 | $4.07 | $6.61 | $7.00 | |
| 16 | Z0038120 | PCC SUR REM 1 3/4 | 13 | SQ YD | $4.50 | $10.00 | $45.00 | $3.00 | $5.02 | $60.00 | |
| 17 | Z0038124 | PCC SUR REM 3 | 122 | SQ YD | $7.75 | $10.00 | $14.00 | $3.50 | $7.02 | $12.00 | |
| 18 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 19 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 20 | 20100110 | TREE REMOV 6-15 | 95 | UNIT | $30.00 | $30.00 | $20.00 | $30.00 | $30.00 | $30.00 | |
| 21 | 20100210 | TREE REMOV OVER 15 | 24 | UNIT | $40.00 | $40.00 | $65.00 | $40.00 | $40.00 | $40.00 | |
| 22 | 20101300 | TREE PRUN 1-10 | 12 | EACH | $40.00 | $40.00 | $30.00 | $40.00 | $40.00 | $40.00 | |
| 23 | 20101350 | TREE PRUN OVER 10 | 12 | EACH | $50.00 | $50.00 | $120.00 | $50.00 | $50.00 | $50.00 | |
| 24 | 20200100 | EARTH EXCAVATION | 95 | CU YD | $55.00 | $85.00 | $75.00 | $65.00 | $74.61 | $45.00 | |
| 25 | 21101615 | TOPSOIL F & P 4 | 1,312 | SQ YD | $7.00 | $7.00 | $5.00 | $5.00 | $7.00 | $7.50 | |
| 26 | 25000210 | SEEDING CL 2A | 0.3 | ACRE | $2,850.00 | $2,850.00 | $7,500.00 | $1,500.00 | $2,850.00 | $3,600.00 | |
| 27 | 25000400 | NITROGEN FERT NUTR | 27 | POUND | $3.00 | $3.00 | $5.00 | $4.00 | $3.00 | $3.00 | |
| 28 | 25000500 | PHOSPHORUS FERT NUTR | 27 | POUND | $3.00 | $3.00 | $5.00 | $4.00 | $3.00 | $3.00 | |
| 29 | 25000600 | POTASSIUM FERT NUTR | 27 | POUND | $3.00 | $3.00 | $5.00 | $4.00 | $3.00 | $3.00 | |
| 30 | 25000750 | MOWING | 0.9 | ACRE | $300.00 | $300.00 | $2,500.00 | $500.00 | $300.00 | $1,000.00 | |
| 31 | 25100115 | MULCH METHOD 2 | 0.2 | ACRE | $2,000.00 | $2,000.00 | $3,500.00 | $13,000.00 | $2,000.00 | $4,000.00 | |
| 32 | 25100630 | EROSION CONTR BLANKET | 317 | SQ YD | $0.7600 | $0.7600 | $5.00 | $4.00 | $0.7600 | $3.00 | |
| 33 | 25200110 | SODDING SALT TOLERANT | 995 | SQ YD | $8.00 | $8.00 | $10.00 | $5.00 | $8.00 | $14.00 | |
| 34 | 35501316 | HMA BASE CSE 8 | 17 | SQ YD | $150.00 | $130.00 | $102.00 | $75.00 | $101.59 | $135.00 | |
| 35 | 40600290 | BIT MATLS TACK CT | 59,583 | POUND | $0.0100 | $0.0100 | $1.45 | $0.0100 | $0.0100 | $0.0100 | |
| 36 | 40600400 | MIX CR JTS FLANGEWYS | 135 | TON | $10.00 | $50.00 | $85.00 | $75.00 | $10.00 | $250.00 | |
| 37 | 40600827 | P LB MM IL-4.75 N50 | 5,438 | TON | $80.00 | $80.00 | $83.60 | $115.00 | $90.72 | $95.00 | |
| 38 | 40600982 | HMA SURF REM BUTT JT | 579 | SQ YD | $3.00 | $13.00 | $7.50 | $5.00 | $12.59 | $24.00 | |
| 39 | 40603335 | HMA SC "D" N50 | 312 | TON | $78.50 | $82.00 | $92.75 | $110.00 | $101.12 | $120.00 | |
| 40 | 40603565 | P HMA SC "E" N70 | 8,485 | TON | $86.00 | $82.00 | $87.35 | $100.00 | $90.13 | $97.00 | |
| 41 | 40800029 | BIT MATLS TACK CT | 4 | POUND | $0.0100 | $5.00 | $55.00 | $0.0100 | $40.00 | $25.00 | |
| 42 | 42001300 | PROTECTIVE COAT | 2,503 | SQ YD | $1.00 | $1.50 | $1.00 | $1.50 | $1.00 | $0.7500 | |
| 43 | 42300200 | PCC DRIVEWAY PAVT 6 | 96 | SQ YD | $72.00 | $71.00 | $75.00 | $65.00 | $75.00 | $55.00 | |
| 44 | 42300400 | PCC DRIVEWAY PAVT 8 | 111 | SQ YD | $80.00 | $78.00 | $80.00 | $75.00 | $80.00 | $60.00 | |
| 45 | 42400200 | PC CONC SIDEWALK 5 | 5,851 | SQ FT | $11.00 | $6.50 | $6.00 | $6.50 | $6.00 | $6.00 | |
| 46 | 42400410 | PC CONC SIDEWALK 8 | 1,562 | SQ FT | $13.00 | $9.00 | $10.00 | $9.00 | $10.00 | $12.00 | |
| 47 | 44000156 | HMA SURF REM 1 3/4 | 3,141 | SQ YD | $2.50 | $4.50 | $2.85 | $2.10 | $3.71 | $5.50 | |
| 48 | 44000159 | HMA SURF REM 2 1/2 | 15,752 | SQ YD | $3.50 | $4.50 | $3.30 | $3.00 | $4.95 | $6.00 | |
| 49 | 44000161 | HMA SURF REM 3 | 69,504 | SQ YD | $4.00 | $4.75 | $3.65 | $3.75 | $6.71 | $7.00 | |
| 50 | 44000200 | DRIVE PAVEMENT REM | 224 | SQ YD | $23.00 | $15.00 | $15.00 | $22.00 | $17.01 | $16.00 | |
| 51 | 44000600 | SIDEWALK REM | 6,544 | SQ FT | $2.50 | $2.00 | $2.50 | $2.00 | $1.35 | $2.50 | |
| 52 | 44201765 | CL D PATCH T2 10 | 3,050 | SQ YD | $15.00 | $50.00 | $32.00 | $30.00 | $58.21 | $90.00 | |
| 53 | 44201769 | CL D PATCH T3 10 | 1,747 | SQ YD | $15.00 | $45.00 | $32.00 | $25.00 | $57.90 | $85.00 | |
| 54 | 44201771 | CL D PATCH T4 10 | 1,164 | SQ YD | $15.00 | $45.00 | $32.00 | $20.00 | $57.60 | $80.00 | |
| 55 | 44201803 | CL D PATCH T2 13 | 631 | SQ YD | $17.00 | $65.00 | $41.00 | $32.00 | $75.78 | $110.00 | |
| 56 | 44201807 | CL D PATCH T3 13 | 379 | SQ YD | $17.00 | $60.00 | $41.00 | $27.00 | $75.39 | $100.00 | |
| 57 | 44201809 | CL D PATCH T4 13 | 252 | SQ YD | $17.00 | $60.00 | $41.00 | $22.00 | $76.43 | $90.00 | |
| 58 | 60255500 | MAN ADJUST | 9 | EACH | $485.00 | $450.00 | $500.00 | $450.00 | $485.00 | $500.00 | |
| 59 | 60300105 | FR & GRATES ADJUST | 90 | EACH | $360.00 | $350.00 | $300.00 | $400.00 | $360.00 | $400.00 | |
| 60 | 60300305 | FR & LIDS ADJUST | 53 | EACH | $500.00 | $400.00 | $300.00 | $400.00 | $500.00 | $440.00 | |
| 61 | 60404800 | FR & GRATES T11 | 3 | EACH | $420.00 | $350.00 | $450.00 | $450.00 | $420.00 | $400.00 | |
| 62 | 60406000 | FR & LIDS T1 OL | 5 | EACH | $400.00 | $350.00 | $325.00 | $400.00 | $400.00 | $400.00 | |
| 63 | 60406100 | FR & LIDS T1 CL | 5 | EACH | $400.00 | $350.00 | $325.00 | $400.00 | $400.00 | $400.00 | |
| 64 | 60406530 | FR & LIDS CL (CHGO) | 3 | EACH | $450.00 | $350.00 | $350.00 | $400.00 | $450.00 | $400.00 | |
| 65 | 66900200 | NON SPL WASTE DISPOSL | 95 | CU YD | $115.00 | $131.00 | $122.00 | $43.75 | $88.74 | $135.00 | |
| 66 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $3,500.00 | $3,780.00 | $1,500.00 | $1,200.00 | $3,780.00 | $3,900.00 | |
| 67 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,380.00 | $2,040.00 | $1,700.00 | $825.00 | $2,040.00 | $1,500.00 | |
| 68 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,000.00 | $3,800.00 | $2,500.00 | $3,300.00 | $3,500.00 | $2,000.00 | |
| 69 | 67100100 | MOBILIZATION | 1 | L SUM | $209,000.00 | $219,000.00 | $216,000.00 | $460,000.00 | $244,485.48 | $280,000.00 | |
| 70 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $386,808.44 | $279,780.00 | $315,000.00 | $48,500.74 | $39,000.00 | $101,938.87 | |
| 71 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 | $500.00 | |
| 72 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 | $500.00 | |
| 73 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 | $500.00 | |
| 74 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $500.00 | $1.00 | $500.00 | $500.00 | $100.00 | $500.00 | |
| 75 | 70300100 | SHORT TERM PAVT MKING | 45,140 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.00 | $1.50 | $0.8000 | |
| 76 | 70300150 | SHRT TRM PAVT MK REM | 15,047 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $1.00 | $1.00 | $0.7000 | |
| 77 | 70300210 | TEMP PVT MK LTR & SYM | 623.9 | SQ FT | $0.0100 | $3.75 | $0.0100 | $0.0100 | $3.75 | $3.75 | |
| 78 | 70300220 | TEMP PVT MK LINE 4 | 42,231 | FOOT | $0.0100 | $0.2000 | $0.0100 | $0.0100 | $0.2000 | $0.2000 | |
| 79 | 70300240 | TEMP PVT MK LINE 6 | 5,125 | FOOT | $0.0100 | $0.3000 | $0.0100 | $0.0100 | $0.3000 | $0.3000 | |
| 80 | 70300250 | TEMP PVT MK LINE 8 | 185 | FOOT | $0.0100 | $0.4000 | $0.0100 | $0.0100 | $0.4000 | $0.4000 | |
| 81 | 70300260 | TEMP PVT MK LINE 12 | 560 | FOOT | $0.0100 | $0.6000 | $0.0100 | $0.0100 | $0.6000 | $0.6000 | |
| 82 | 70300280 | TEMP PVT MK LINE 24 | 1,308 | FOOT | $0.0100 | $1.20 | $0.0100 | $0.0100 | $1.20 | $1.20 | |
| 83 | 70300520 | PAVT MARK TAPE T3 4 | 11,285 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.00 | $1.00 | $1.00 | |
| 84 | 72400100 | REMOV SIN PAN ASSY TA | 1 | EACH | $150.00 | $45.00 | $150.00 | $150.00 | $45.00 | $45.00 | |
| 85 | 72400500 | RELOC SIN PAN ASSY TA | 1 | EACH | $150.00 | $75.00 | $150.00 | $150.00 | $75.00 | $75.00 | |
| 86 | 78000100 | THPL PVT MK LTR & SYM | 623.9 | SQ FT | $3.75 | $3.75 | $3.90 | $3.75 | $3.75 | $3.75 | |
| 87 | 78000200 | THPL PVT MK LINE 4 | 42,231 | FOOT | $0.5000 | $0.5000 | $0.6000 | $0.5000 | $0.5000 | $0.5000 | |
| 88 | 78000400 | THPL PVT MK LINE 6 | 5,125 | FOOT | $0.6800 | $0.6800 | $0.7500 | $0.6800 | $0.6800 | $0.6800 | |
| 89 | 78000500 | THPL PVT MK LINE 8 | 185 | FOOT | $0.9800 | $0.9800 | $1.00 | $0.9800 | $0.9800 | $0.9800 | |
| 90 | 78000600 | THPL PVT MK LINE 12 | 560 | FOOT | $1.38 | $1.38 | $1.70 | $1.38 | $1.38 | $1.38 | |
| 91 | 78000650 | THPL PVT MK LINE 24 | 1,308 | FOOT | $3.75 | $3.75 | $3.90 | $3.75 | $3.75 | $3.75 | |
| 92 | 78100100 | RAISED REFL PAVT MKR | 1,446 | EACH | $20.00 | $20.00 | $30.00 | $20.00 | $20.00 | $20.00 | |
| 93 | 78300200 | RAISED REF PVT MK REM | 1,105 | EACH | $2.00 | $14.00 | $9.00 | $7.00 | $9.80 | $23.00 | |
| 94 | 85000200 | MAIN EX TR SIG INSTAL | 2 | EACH | $880.00 | $880.00 | $880.00 | $880.00 | $880.00 | $3,900.00 | |
| 95 | 88600600 | DET LOOP REPL | 2,942 | FOOT | $15.30 | $15.30 | $15.30 | $15.30 | $15.30 | $17.00 | |
| 96 | 89500400 | RELOC EX PED PUSH-BUT | 6 | EACH | $342.00 | $342.00 | $342.00 | $342.00 | $342.00 | $480.00 | |
| 97 | 89502376 | REBUILD EX HANDHOLE | 6 | EACH | $2,335.00 | $2,335.00 | $2,335.00 | $2,335.00 | $2,335.00 | $2,400.00 | |
| 98 | 89502385 | REMOV EX CONC FDN | 1 | EACH | $880.00 | $880.00 | $880.00 | $880.00 | $880.00 | $800.00 |