MACOMB MUNICIPAL
- Let date
- Friday, August 3, 2018
- Contract
- MB030
- District
- District 4
- County
- Mcdonough
- Highway
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | J.H. Moore, Inc. Low bidder | $165,804 | ||
| 2 | Oberlander Electric Co. | $189,500 | +14.3% | |
| 3 | Laser Electric, Inc. | $227,270 | +37.1% | |
| 4 | Egizii Electric, Inc., A Division of EEI Holding Corporation | $376,074 | +126.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J.H. Moore, Inc. | #2 Oberlander Elec… | #3 Laser Electric,… | #4 Egizii Electric… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | AR108656 | 3/C #6 600 V UG CABLE IN UD | 5,515 | L.F. | $6.27 | $9.00 | $12.00 | $8.68 | |
| 2 | AR110014 | 4" DIRECTIONAL BORE | 80 | L.F. | $20.00 | $61.00 | $95.00 | $41.31 | |
| 3 | AR125565 | SPLICE CAN | 1 | EACH | $900.00 | $1,457.00 | $1,500.00 | $1,263.36 | |
| 4 | AR125615 | PAPI (L-880 SYSTEM) | 2 | EACH | $42,700.00 | $19,431.00 | $44,020.00 | $32,816.00 | |
| 5 | AR125909 | REMOVE VASI | 2 | EACH | $2,500.00 | $6,200.00 | $5,940.00 | $3,180.80 | |
| 6 | AR150510 | ENGINEER'S FIELD OFFICE | 1 | L.S. | $4,000.00 | $16,500.00 | $5,500.00 | $4,771.20 | |
| 7 | AR150520 | MOBILIZATION | 1 | L.S. | $4,800.00 | $35,500.00 | $11,500.00 | $24,192.00 | |
| 8 | AR152442 | OFFSITE BORROW EXCAVATION | 60 | C.Y. | $60.00 | $131.50 | $225.00 | $3,136.00 | |
| 9 | AR156511 | DITCH CHECK | 1 | EACH | $125.00 | $946.00 | $2,500.00 | $235.20 | |
| 10 | AR156531 | EROSION CONTROL BLANKET | 200 | S.Y. | $6.00 | $8.25 | $6.00 | $17.92 | |
| 11 | AR701521 | 21" RCP, CLASS IV | 48 | L.F. | $300.00 | $185.00 | $200.00 | $336.00 | |
| 12 | AR752421 | PRECAST REINFORCED CONC. FES 21" | 4 | EACH | $1,800.00 | $1,850.00 | $1,500.00 | $2,788.80 | |
| 13 | AR901510 | SEEDING | 0.1 | ACRE | $30,000.00 | $35,000.00 | $22,700.00 | $34,160.00 |