Let date Contract / PPS County / Division Highway Description Estimate Status Added Low bidder
Nov 17, 2023 62R28 WillDistrict 1 The reconstruction of the existing I-80 mainline pavement from east of River Road to west of Houbolt Road and The project consists of the reconstruction of the existing I-80 mainline pavement from east of River Road to west of Houbolt Road and the partial reconstruction of the entrance and exit ramps at the I-80 and I-55 interchange and the W. Frontage Road. The work also includes reconstruction and widening of the EB/WB I-80 Bridges over DuPage River, EB/WB I-80 Bridges over Frontage Road, EB/WB I-80 Bridges over I-55, EB/WB I-80 Bridges over Rock Run Creek, and EB/WB I-80 Bridges over future Ramp AA. — Executed Nov 26 New D. Construction, Inc. $90,647,017 ·
Nov 17, 2023 62R83 CookDistrict 1 Installation of new fiber optic cable, conduit, PTZ cameras, network switches along four different corridors. This project located in Cook County located primarily within Village of Worth, Blue Island, and Hazel Crest. — Executed Nov 26 New H & H Electric Co. $1,346,686 ·
Nov 17, 2023 62R87 WillDistrict 1 (282-Ft) Bridge Preservation Project: bridge repair, joint replace/ repair and deck overlay on bridge carrying Old Chicago Road over Forked Creek (0.5 mi N of Manteno Rd) Located in Wesley Township in Will County. — Executed Nov 26 New Iroquois Paving Corporation $499,318 ·
Nov 17, 2023 62T12 DuPageDistrict 1 Bridge deck overlay and joint replacement of IL 83 over BNSF RR (S of Bluff Road) in the Downers Grove Townshi The proposed improvement consists of bridge deck overlay and joint replacement of IL 83 over BNSF RR (S of Bluff Road) in the Downers Grove Township, DuPage County. Total gross length and net length= 5442.65 FT (1.031 Ml), and 4811.44FT (0.911 Ml) — Executed Nov 26 New Lorig Construction Company $1,355,097 ·
Nov 17, 2023 62T18 CookDistrict 1 Overlay of SN 016-2598 bridge deck overlay, parapet and railing repairs, deck scarification, pavement markings The scope of work consists of overlay of SN 016-2598 bridge deck overlay, parapet and railing repairs, deck scarification, pavement markings, and traffic control and protection. The project is located over UPRR in the Village of Northbrook in Cook County. Gross Length= Net Length =2658 FT (0.50 Mile). — Executed Nov 26 New Lorig Construction Company $1,108,628 ·
Nov 17, 2023 62T36 CookDistrict 1 Deck scarification, latex concrete overlay, joint replacement, approach slab and slope wall repairs on Tower R (392-Ft) Bridge rehabilitation project and the scope consists of deck scarification, latex concrete overlay, joint replacement, approach slab and slope wall repairs on Tower Road over I-94/US41 (Edens Expressway) in the Villages of Glencoe and Northfield in Cook County. (SN 016-0815). — Executed Nov 26 New Lorig Construction Company $889,123 ·
Nov 17, 2023 62T52 CookDistrict 1 Length: 452 ft (0.09 mi); Bridge Preservation Project: Bridge deck overlay and joint repair of SN 016-2038 carrying Wilson Avenue over I-94 (Edens Expwy) and ADA improvements in Cook County. — Executed Nov 26 New Lorig Construction Company $1,112,856 ·
Nov 17, 2023 62T57 CookDistrict 1 (3.54-Mile) SMART Overlay and ADA Improvements on US 6 from Carol Avenue to IL 83 (Torrence Avenune). This project is located in the City of Harvey, Calumet City and the Village of South Holland in Cook County. — Executed Nov 26 New D. Construction, Inc. $4,811,131 ·
Nov 17, 2023 62T65 DuPageDistrict 1 (2.09-Mile) SMART Overlay and pedestrian ramps (ADA) project. The scope included pavement patching, HMA surface removal and resurfacing, pedestrian ramp improvements, drainage structure adjustments, cleaning and placement of permanent pavement markings. This project begins on Beaumont Dr./ Shandrew Dr. at Ogden Ave. (US 34) and extends southwest of Aurora Rd. and is located within the City of Naperville in DuPage County. — Executed Nov 26 New Plote Construction, Inc. $1,874,899 ·
Nov 17, 2023 62T74 CookDistrict 1 Pavement patching, PCC curb and gutter removal and replacement, pedestrian curb ramps improvements (ADA), hot- (2.33-Mile) Smart Overlay, crack and joint seal, ADA Improvements project consists of pavement patching, PCC curb and gutter removal and replacement, pedestrian curb ramps improvements (ADA), hot-mix asphalt surface removal and resurfacing and sealing of existing longitudinal joints and cracks. This project begins at IL-59 (FAP 338) at Dundee/Old Dundee Rd and extends northerly to Lake Cook Rd/Main St. The project is located within Barrington Township in Cook Co. — Executed Nov 26 New Builders Paving, LLC $978,000 ·
Nov 17, 2023 62V23 CookDistrict 1 This improvement is a Bridge Painting on I-57 Under 175th St in the City of Country Club Hills in Cook County. (SN 016-1095) — Executed Nov 26 New Capital Industrial Services, LLC $683,300 ·
Nov 17, 2023 62W13 VariousDistrict 1 Upgrading existing pedestrian push buttons to APS push buttons at various D1 ADA compliant intersections. — Executed Nov 26 New Meade Inc. $472,427 ·
Nov 17, 2023 62W14 CookDistrict 1 Removing trees, as well as all incidental and collateral work necessary to complete the project as shown on th The project consists of removing trees, as well as all incidental and collateral work necessary to complete the project as shown on the plans and as described herein. 3,360 ft. (0.64 mi.) along IL 43, and 2,970 ft. (0.56 mi.) along 95th Street, tree removal, in Bridgeview, Oak Lawn, and Chicago Ridge, Cook County, IL. — Executed Nov 26 New Clean Cut Tree Service, Inc. $551,977 ·
Nov 17, 2023 64918 CarrollDistrict 2 Patching, Resurfacing and ADA improvements on IL 78 from 0.2 mile N. of US 52/IL 64 to Carroll Creek in Mt. Carroll. — Executed Nov 26 New Martin & Company Excavating $1,429,025 ·
Nov 17, 2023 64K73 WinnebagoDistrict 2 Removal and replacement of twin structures carrying IL Route 2 over the Rock River in Rockton. — Executed Nov 26 New Civil Constructors, Inc. d/b/a/ Helm Civil $25,360,046 ·
Nov 17, 2023 64S39 WhitesideDistrict 2 Bridge deck overlay, joint replacement and miscellaneous repairs on SN 098-0086, carrying IL 40 over I-88, 1 mile south of US 30. — Executed Nov 26 New Martin & Company Excavating $1,375,082 ·
Nov 17, 2023 64S40 WhitesideDistrict 2 Bridge deck overlay, joint replacement, and miscellaneous repairs on SN 098-0091, carrying US 30 over I-88, 3 miles east of Rock Falls. — Executed Nov 26 New Martin & Company Excavating $1,248,487 ·
Nov 17, 2023 64S43 Rock IslandDistrict 2 Bridge washing of SN 081-0011 over the Mississippi River in Rock Island County. — Executed Nov 26 New Interstate Maintenance, Incorporated $149,550 ·
Nov 17, 2023 64S44 Rock IslandDistrict 2 Bridge washing of SN 081-0106 over the Mississippi River in Rock Island County. — Executed Nov 26 New Interstate Maintenance, Incorporated $59,340 ·
Nov 17, 2023 64S45 VariousDistrict 2 Bridge washing of SN 008-0052, 098-6003 and 081-9905 over the Mississippi River in various counties. — Executed Nov 26 New Interstate Maintenance, Incorporated $123,440 ·
Nov 17, 2023 66N39 VariousDistrict 3 This project consists on performing Bridge Deck Concrete Sealing with the parapets/curbs on various routes at various locations throughout Ford, Iroquois, and Kankakee Counties. — Executed Nov 26 New All States Painting, Inc. $196,144 ·
Nov 17, 2023 66N83 VariousDistrict 3 Tree Removal located within Bureau, DeKalb, Ford, Grundy, La Salle, and Livings on counties. — Executed Nov 26 New Clean Cut Tree Service, Inc. $210,216 ·
Nov 17, 2023 66N99 VariousDistrict 3 Repairing and maintaining traffic signals, flashing beacons, and roadway lighting in Ford, Iroquois, and Livin This project consists of repairing and maintaining traffic signals, flashing beacons, and roadway lighting in Ford, Iroquois, and Livingston Counties. — Executed Nov 26 New Leo P. Kelly Electric, Incorporated $350,818 ·
Nov 17, 2023 68C00 TazewellDistrict 4 3R project has a length of 0.58 miles extending from the east end of the Cedar St Bridge over the Illinois River to just east of Center St, including the Edmund St interchange. Work includes pavement patching, milling, resurfacing, and bridge rehabilitation. — Executed Nov 26 New ICC Group Inc. $14,978,000 ·
Nov 17, 2023 68D36 McDonoughDistrict 4 Stream stabilization with riprap placement at various locations along Spring Creek, northwest of Macomb bypass. — Executed Nov 26 New Laverdiere Construction, Inc. $355,897 ·
Nov 17, 2023 68G39 MarshallDistrict 4 Bridge repair and bridge deck overlay to S.N. 062-0056 over Thenius Creek 1/4 mi. N. of Sparland; S.N. 062-0057 over Gimlet Creek at the IL 29/IL 17 junction and S.N. 062-0059 over Senachwine Creek, 4 mi. W. of Sparland. — Executed Nov 26 New Stark Excavating, Inc. $2,030,255 ·
Nov 17, 2023 68H77 VariousDistrict 4 District-wide replacement of pedestrian pushbuttons with APS push buttons. — Executed Nov 26 New Laser Electric, Inc. $1,741,480 ·
Nov 17, 2023 68H79 VariousDistrict 4 Bridge painting: S.N. 072-0106 SB IL 6, S.N. 072-0107 NB I-474 Ramp 109, S.N. 072-0108 SB I-474 Ramp, 072-0109 NB I-474 Ramp 109, S.N. 048-0078 W. Knox Rd., S.N. 094-0028 Cameron Rd., S.N. 055-0021 CH 8, S.N. 048-0080 IL 180, S.N. 090-0043 US 150, S.N. 072-0228 US 24/IL 9. — Executed Nov 26 New Eagle Painting & Maintenance Company, Inc. $1,961,212 ·
Nov 17, 2023 70G12 McLeanDistrict 5 Bridge painting of 3 structures on FAI 55 (I-55) and FAP 704 (I-55 Busn). — Executed Nov 26 New Eagle Painting & Maintenance Company, Inc. $1,273,331 ·
Nov 17, 2023 72717 BrownPikeDistrict 6 Spray-applied pipe liner on IL 107 in Brown and Pike Counties. — Executed Nov 26 New Hoerr Construction, Inc. $567,640 ·
Nov 17, 2023 72719 SangamonDistrict 6 Lot improvements to the Riverton Maintenance Yard. — Executed Nov 26 New Illinois Valley Paving, a div of UCM, Inc. $160,583 ·
Nov 17, 2023 72807 MontgomeryDistrict 6 Tree removal at the Coalfield Rest Area. — Executed Nov 26 New Clean Cut Tree Service, Inc. $97,200 ·
Nov 17, 2023 72F14 SchuylerDistrict 6 7.3 miles of milling, resurfacing, bridge overlay (SN 085-0004), slope stabilization and guardrail replacement on IL 103 from 0.1 miles east of US 24 to 1.7 miles west of US 67. — Executed Nov 26 New Illinois Valley Paving, a div of UCM, Inc. $11,920,700 ·
Nov 17, 2023 72F26 AdamsDistrict 6 Culvert replacement on IL 96 over a ditch, 1 mile north of Kochs Lane, north of Qunicy. — Executed Nov 26 New Laverdiere Construction, Inc. $1,932,532 ·
Nov 17, 2023 72F59 CassDistrict 6 Culvert replacement (SN 009-7002) carrying IL 125 over a ditch 0.6 miles east of Warrior Hill Road. — Executed Nov 26 New Otto Baum Company, Inc. $1,524,200 ·
Nov 17, 2023 72H57 HancockDistrict 6 Hydro-scarification, microsilica concrete overlay, expansion joint replacement and steel repairs on SN 034-0062 carrying US 136 over the Mississippi River from Hamilton, IL to Keokuk, IA. — Executed Nov 26 New Freesen, a div of UCM, Inc. $8,876,670 ·
Nov 17, 2023 72K83 SangamonDistrict 6 Culvert replacement on IL 104 at Little Panther Creek, 1.9 miles west of IL 4 (SN 084-7061). — Executed Nov 26 New Kinney Contractors, Inc. $952,366 ·
Nov 17, 2023 72K96 MorganDistrict 6 5.2 miles of resurfacing on IL 78 from the Cass County line to just north of Snake Creek. — Executed Nov 26 New K. E. Vas Company $5,770,272 ·
Nov 17, 2023 72M34 MorganDistrict 6 Painting portions of 7 bridges near Jacksonville. — Executed Nov 26 New Eagle Painting & Maintenance Company, Inc. $1,103,400 ·
Nov 17, 2023 72M71 BrownDistrict 6 4.8 miles of milling, patching, resurfacing and shoulders on US 24 from 0.5 miles east of Timewell Road to 0.3 miles west of Buckhorn / Damon Road in Mount Sterling. — Executed Nov 26 New Diamond Construction Company $4,650,700 ·
Nov 17, 2023 74471 FayetteDistrict 7 3.4 miles of resurfacing on US 40 from 0.5 miles west of the I-70 interchange to IL 185 in Vandalia, resurfacing the I-70 / US 40 ramps at the Vandalia Vandalia interchange and joint repairs and overlay to SN 026-0087. — Executed Nov 26 New Howell Paving, Inc. $5,506,589 ·
Nov 17, 2023 74B29 MaconDistrict 7 Bridge deck overlay, joint replacement / repair and other bridge deck repairs on 3 structures: 1) SN 058-0060 carrying TR 4 (South Acom Road) over I-72; 2) SN 058-0062 carrying CH 27 (Lincoln Memorial Parkway) over I-72; 3) SN 058-0065 carrying Twin Lakes Road over I-72 just west of Decatur. — Executed Nov 26 New Freesen, a div of UCM, Inc. $1,224,997 ·
Nov 17, 2023 74B30 MaconDistrict 7 Bridge deck overlay, joint repair and approach pavement on I-72 over Spring Creek, 1.3 miles east of Forsyth. — Executed Nov 26 New Freesen, a div of UCM, Inc. $1,953,030 ·
Nov 17, 2023 74B31 FayetteDistrict 7 Bridge repairs on SN 026-0071 carrying IL 185 over I-57 in Farina. — Executed Nov 26 New Samron Midwest Contracting, Inc. $1,077,997 ·
Nov 17, 2023 74B33 MaconDistrict 7 Bridge deck repair and overlay on SN 058-0129 carrying IL 121 over South Fork Creek, 0.7 miles east of the Logan County line. — Executed Nov 26 New Freesen, a div of UCM, Inc. $498,028 ·
Nov 17, 2023 74B34 EffinghamDistrict 7 Bridge deck overlay, bridge joint replacement, deck drain replacement, bridge deck patching on SN 025-0089 carrying IL 37 over the Little Wabash River, 0.5 miles south of I-57. — Executed Nov 26 New Sangamo Construction Company $761,969 ·
Nov 17, 2023 74B35 ClarkDistrict 7 Bridge deck overlay and joint replacement and repairs on SN 012-0025 carrying US 40 over I-70. — Executed Nov 26 New Sangamo Construction Company $1,282,944 ·
Nov 17, 2023 74B37 WabashDistrict 7 Washing the bridge deck on SN 093-0021 carrying IL 15 over the Wabash River in Mt. Carmel. — Executed Nov 26 New
Nov 17, 2023 74B39 MaconDistrict 7 Bridge deck overlay, joint replacement, deck patching, structural concrete repair, crashwall extensions and HMA approaches on SN 058-0087 carrying Kirby Road over I-72, northeast of Decatur. — Executed Nov 26 New Freesen, a div of UCM, Inc. $638,193 ·
Nov 17, 2023 74C65 CumberlandDistrict 7 Bridge joint replacement / repair, bridge deck repairs and bridge deck overlay on SN 018-0003 and 018-0004 carrying I-57 over US 45 and SN 018-0001 and 018-0002 carrying I-57 over the Decatur and Eastern Illinois Railroad, all located northeast of Neoga. — Executed Nov 26 New Path Construction Company, Inc. $1,994,773 ·
Nov 17, 2023 76M88 WashingtonDistrict 8 Culvert replacement on IL 127 at South Middle Tributary of Locust Creek, 6.7 miles south of IL 15 and the town of Nashville. (SN 095-2496) — Executed Nov 26 New E. T. Simonds Construction Company $747,934 ·
Nov 17, 2023 76M90 WashingtonDistrict 8 Culvert replacement on IL 177 at West Tributary to Grand Point, 0.5 miles east of Hoyleton. (SN 095-2496) — Executed Nov 26 New Guinzy Construction,Inc. $490,747 ·
Nov 17, 2023 76N16 MadisonDistrict 8 Bridge repairs, flood wall work and pavement reconstruction on IL 11 over Cahokia Diversion Channel (SN 060-0121), 3 miles north of I-270. — Executed Nov 26 New The Kilian Corporation $1,832,257 ·
Nov 17, 2023 76N43 MadisonDistrict 8 Intersection reconstruction and ADA upgrades on IL 3 at 20th Street in Granite City. — Executed Nov 26 New Baxmeyer Construction, Inc. $7,285,268 ·
Nov 17, 2023 76T01 VariousDistrict 8 Traffic signal modernization at various locations within District 8. — Executed Nov 26 New Gerstner Electric, Inc. $1,564,128 ·
Nov 17, 2023 76T39 St. ClairDistrict 8 1.96 miles of patching and a standard overlay on I-55/64/US 40 from 0.9 miles east of the Mississippi River to I-64 (Tri-Level) Interchange in East St. Louis — Executed Nov 26 New The Kilian Corporation $5,220,980 ·
Nov 17, 2023 78199 PerryDistrict 9 Replacement of a bridge with a double reinforced concrete box culvert on US 51 north of Tamaroa. (SN 073-0002) — Executed Nov 26 New E. T. Simonds Construction Company $924,177 ·
Nov 17, 2023 78771 SalineDistrict 9 Intersection reconstruction at the intersection of US 45 and Poplar (Old IL 13) in Harrisburg. — Executed Nov 26 New E. T. Simonds Construction Company $1,369,045 ·
Nov 17, 2023 78809 GallatinDistrict 9 Slope stabilization at SN 030-0021 carrying IL 1 over the Saline River, 2.5 miles south of IL 13, southeast of Equality. — Executed Nov 26 New E. T. Simonds Construction Company $399,347 ·
Nov 17, 2023 78929 JacksonDistrict 9 0.75 miles of resurfacing on North 6th Street in Murphysboro. — Executed Nov 26 New Samron Midwest Contracting, Inc. $339,339 ·
Nov 17, 2023 78A02 AlexanderJacksonUnionDistrict 9 25.4 miles of patching, milling, resurfacing and shoulders on IL 3 from Howardton Road, near Grand Tower, to the Cape T intersection. — Executed Nov 26 New E. T. Simonds Construction Company $11,663,246 ·
Nov 17, 2023 85727 WinnebagoDistrict 2 Sidewalk construction along Parkview Avenue from Spring Creek Road to Birchwood Drive in Rockford. — Executed Nov 26 New N-Trak Group LLC $489,794 ·
Nov 17, 2023 89815 PeoriaDistrict 4 Structure rehabilitation with replacement of approach slabs, bridge deck, parapets, beams, expansion joints, bearings, concrete slope walls. Also included will be PCC pavement with curb and gutter, and storm sewers on Maxwell Road over the Union Pacific Railroad, 0.2 miles south of IL 116. — Executed Nov 26 New Stark Excavating, Inc. $4,569,990 ·
Nov 17, 2023 89824 TazewellDistrict 4 Resurfacing Fischer Road from IL 29 to Creve Coeur Avenue in Creve Coeur. — Executed Nov 26 New R. A. Cullinan and Son, a div of UCM, Inc. $408,195 ·
Nov 17, 2023 93775 MenardDistrict 6 Widening and HMA resurfacing with aggregate shoulders and pipe culverts on Athens Blacktop from Cantrall Road to Kent Street. — Executed Nov 26 New K. E. Vas Company $3,709,353 ·
Nov 17, 2023 93812 SangamonDistrict 6 HMA resurfacing with pavement markings on Cardinal Hill Road from New City Road to north of IL 104. — Executed Nov 26 New P. H. Broughton & Sons, Inc. $1,082,697 ·
Nov 17, 2023 95941 MoultrieDistrict 7 Sidewalk Construction on various routes within the City of Sullivan. — Executed Nov 26 New A & R Mechanical Service, Inc. $288,741 ·
Nov 17, 2023 97790 MadisonDistrict 8 Reconstruction of Lebanon Road on new alignment to facilitate closure of two underpass structures. Work includes structure removal, construction of a 6-span steel plate girder bridge, construction of a 1-span PC slabl bridge, box culverts, pavement removal, building removal, processing lime modified soil, PPC Pavement, HMA Pavement, HMA shoulders, combination curb and gutter, and storm sewer. Located 0.19 miles east of Clay School Road to 0.16 miles of Locmann Road over the CSX Railroad. — Executed Nov 26 New Keller Construction, Inc. $17,444,384 ·
Nov 17, 2023 97793 MadisonDistrict 8 Reconstruction of the IL 159 and Glen Carbon Road intersection to establish north bound and east bound right turn lanes. Includes, HMA resurfacing, sidewalks, ADA ramps, traffic signal modifications, and drainage improvements. Located in Glen Carbon. — Rejected Nov 25 New Keller Construction, Inc. $1,439,471 ·
Nov 17, 2023 97815 St. ClairDistrict 8 Resurfacing Jerome Lane from Nash Street to Range Lane in Cahokia. — Executed Nov 26 New Christ Bros. Asphalt, Inc. $897,940 ·
Nov 17, 2023 97817 St. ClairDistrict 8 Construction of a PCC sidewalk from the Boul Avenue Trailhead entrance to the intersection of Boul Avenue and IL 159 in Swansea. — Rejected Nov 26 New
Nov 17, 2023 97822 MadisonDistrict 8 Resurfacing West Airline Drive from Main Street to 9th Street in East Alton. — Executed Nov 26 New Charles E. Mahoney Co. $858,985 ·
Nov 17, 2023 99673 WilliamsonDistrict 9 Resurfacing East Grand Avenue from Hurricane Road to IL 148. — Executed Nov 26 New Samron Midwest Contracting, Inc. $402,402 ·
Nov 17, 2023 99711 JacksonDistrict 9 Resurfacing North Marion Street from East Fischer Street to Dillinger Road. — Executed Nov 26 New E. T. Simonds Construction Company $658,507 ·
Nov 17, 2023 99713 JacksonDistrict 9 Replace existing structure with a precast concrete box culvert with pre-cast box culvert end sections, PCC pavement, sidewalk, curb and gutter, on East College Street over Piles Fork Creek in Carbondale. — Executed Nov 26 New E. T. Simonds Construction Company $553,288 ·
Nov 17, 2023 99716 WilliamsonDistrict 9 Remove and replace sidewalks, ADA ramps and crosswalks along North 18 Street from East Herrin Street to West Monroe Street in Herrin. — Executed Nov 26 New E. T. Simonds Construction Company $290,697 ·
Nov 17, 2023 99720 WilliamsonDistrict 9 HMA resurfacing on Lake of Egypt Road from IL 37 to South Market Road, and on Power Plant Road from Lake of Egypt Road to County Club Road. Includes HMA and aggregate shoulders, guardrail adjustments and replacements, and raised pavement markers. — Executed Nov 26 New Samron Midwest Contracting, Inc. $1,664,664 ·
Jan 19, 2024 46638 St. ClairDistrict 8 Pavement marking replacement at various locations in St. Clair County. — Active Nov 26 New ROADSAFE TRAFFIC SYSTEMS, INC. $894,895 ·
Jan 19, 2024 46640 VariousDistrict 2 Removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and p This work consists of removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and placing new raised reflective pavement marker castings within the limits shown on each individual work order. — Executed Nov 26 New P & P Construction Co. $1,104,220 ·
Jan 19, 2024 46933 MarionDistrict 8 Resurfacing main and secondary park roads and parking lots, as well as culvert and bridge replacement, signage and lighting at the Stephen A. Forbes Recreation Area in Marion County. — Executed Nov 26 New DMS Contracting, Inc. $8,455,395 ·
Jan 19, 2024 61H98 WillDistrict 1 Pavement widening and reconstruction, storm sewer, sidewalk replacment, curb and gutter replacement, concrete box culvert, pavement markings, traffic signals, and water main replacement on IL 7 from Lincoln Street to Summit Drive in Lockport. — Executed Nov 26 New Austin Tyler Construction, Inc. $10,458,102 ·
Jan 19, 2024 61J53 CookDistrict 1 Sidewalk construction, drainage improvements, and traffic signal modifications on Wolf Road from Palatine Frontage Road to Edward Road/Metra Station in Prospect Heights. — Executed Nov 26 New Acura Inc. $2,725,444 ·
Jan 19, 2024 61J70 CookDistrict 1 HMA resurfacing, patching, driveway replacement, curb and gutter, sidewalks, drainage and utility structure adjustments, pavement markings, signage, traffic signal ADA improvements and all other necessary work on Bernice Road from Torrence Avenue to Wentwork Avenue in the Village of Lansing. — Executed Nov 26 New Iroquois Paving Corporation $1,794,008 ·
Jan 19, 2024 61J73 CookDistrict 1 HMA resurfacing with patching, bike path, pedestrian push buttons, ADA ramps, and landscaping on Wilke Road from US 14 to IL 62 in Arlington Heights. — Executed Nov 26 New Builders Paving, LLC $4,487,708 ·
Jan 19, 2024 61J74 CookDistrict 1 Sidewalk replacement with curb and gutter, pavement marking, signage, and landscaping along various routes in the Village of Niles. — Rejected Nov 26 New Alliance Contractors, Inc. $4,584,998 ·
Jan 19, 2024 61J82 LakeDistrict 1 Sidewalk reconstruction and traffic signal modifications at the intersection of Central Avenue and Hickory Street in Highland Park. — Executed Nov 26 New Alliance Contractors, Inc. $318,100 ·
Jan 19, 2024 61J95 DuPageDistrict 1 Resurfacing Central Avenue from Thomdale Avenue to Foster Avenue in Wood Dale. — Executed Nov 26 New Builders Paving, LLC $726,808 ·
Jan 19, 2024 61J96 McHenryDistrict 1 Resurfacing Bull Valley Road from Curran Road to Crystal Lake Road in McHenry. — Executed Nov 26 New Geske and Sons, Inc. $255,964 ·
Jan 19, 2024 61J97 WillDistrict 1 Resurfacing on St. Francis Road from US 45 to 88th Avenue in Frankfort — Executed Nov 26 New P. T. Ferro Construction Co. $856,758 ·
Jan 19, 2024 61J98 McHenryDistrict 1 HMA resurfacing with aggregate shoulders on Winn Road from IL 173 to Main Street in Spring Grove. — Executed Nov 26 New Payne & Dolan, Inc. $1,194,568 ·
Jan 19, 2024 61K02 DuPageDistrict 1 Roadway reconstruction on Janes Avenue from 7th Street to Spring Street in Woodridge. — Executed Nov 26 New K-Five Construction Corporation $2,045,192 ·
Jan 19, 2024 61K05 LakeDistrict 1 HMA resurfacing, widening, storm sewers, drainage structures, PCC sidewalks, HMA multi-use patch, and traffic signal improvements at the intersection of Wadsworth Road and Lewis Avenue in Waukegan and Beach Park. — Executed Nov 26 New Campanella and Sons, Inc. $4,199,910 ·
Jan 19, 2024 61K06 CookDistrict 1 Pavement widening, full-depth HMA reconstruction, storm sewer, sidewalk replacement, curb and gutter Replacement, guardrail and roadway lighting on Irving Park Road from Schaumburg Road to IL 59 in Streamwood. — Rejected Nov 26 New Martam Construction Incorporated $10,716,009 ·
Jan 19, 2024 61K08 CookDistrict 1 HMA resurfacing with ADA improvements, curb and gutter, multi-use path, landscaping, patching drainage adjustments, and striping on Illinois Avenue from Quentin Road to Plum Grove Road in Palatine. — Executed Nov 26 New A Lamp Concrete Contractors, Inc. $1,540,000 ·
Jan 19, 2024 61K09 CookDistrict 1 Resurfacing Central Road from Westgate Road to Wolf Road in Mount Prospect. — Executed Nov 26 New Builders Paving, LLC $986,318 ·
Jan 19, 2024 62H58 WillDistrict 1 Parking lot improvement. Full depth removal and replacement of existing pavement. Location: Movable Bridge Maintenance Yard (105 Bridge Street) in the City of Joliet, Will County. — Executed Nov 26 New Austin Tyler Construction, Inc. $211,505 ·
Jan 19, 2024 62K60 CookDistrict 1 2,408 feet (0.456 mile) bridge replacement of US 12/20/45 (La Grange Road) at IL 171 (Archer Ave/19th Street), SN 016-0518, in the Village of Willow Springs, Cook County. — Executed Nov 26 New Dunnet Bay Construction Company $7,746,876 ·
Jan 19, 2024 62M52 CookDistrict 1 1,185-feet (0.22-mile) Bridge rehabilitation project includes deck scarification, latex concrete overlay, joint replacement and approach slab repairs on Roosevelt Road over I-90/94 (Dan Ryan Expressway) (SN 016-0478) within the City of Chicago in Cook County. — Executed Nov 26 New Martam Construction Incorporated $1,269,651 ·
Jan 19, 2024 62R40 DuPageDistrict 1 Earth excavation, removal and construction of a pipe culvert and drainages structure, pavement removal and ful (803-Ft) Curve correction project consists of earth excavation, removal and construction of a pipe culvert and drainages structure, pavement removal and full-depth HMA pavement, located along I-55 North Frontage Road at Cass Avenue in the City of Darien in DuPage County. — Executed Nov 26 New Martam Construction Incorporated $673,990 ·
Jan 19, 2024 62R89 WillDistrict 1 The reconstruction of I-80 mainline pavement from west of Joliet Junction Trail to Wheeler Avenue The project consists of the reconstruction of I-80 mainline pavement from west of Joliet Junction Trail to Wheeler Avenue. The work also includes reconstruction of the I-80 EB Bridge over Joliet Junction Trail, the l-80 WB Bridge over Joliet Junction Trail, I-80 EB Bridge over Midland Avenue, and the I-80 WB Bridge over Midland Avenue. Other work includes drainage system improvements, signing, lighting, temporary traffic signals, ITS improvements, and noise abatement walls. The project is in the — Executed Nov 26 New Walsh Construction Company II, LLC $94,772,970 ·
5,401–5,500 of 10,653‹ PrevNext ›

Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.