| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Nov 17, 2023 | 62R28 | WillDistrict 1 | The reconstruction of the existing I-80 mainline pavement from east of River Road to west of Houbolt Road and The project consists of the reconstruction of the existing I-80 mainline pavement from east of River Road to west of Houbolt Road and the partial reconstruction of the entrance and exit ramps at the I-80 and I-55 interchange and the W. Frontage Road. The work also includes reconstruction and widening of the EB/WB I-80 Bridges over DuPage River, EB/WB I-80 Bridges over Frontage Road, EB/WB I-80 Bridges over I-55, EB/WB I-80 Bridges over Rock Run Creek, and EB/WB I-80 Bridges over future Ramp AA. | — | Executed | D. Construction, Inc. $90,647,017 · | ||
| Nov 17, 2023 | 62R83 | CookDistrict 1 | Installation of new fiber optic cable, conduit, PTZ cameras, network switches along four different corridors. This project located in Cook County located primarily within Village of Worth, Blue Island, and Hazel Crest. | — | Executed | H & H Electric Co. $1,346,686 · | ||
| Nov 17, 2023 | 62R87 | WillDistrict 1 | (282-Ft) Bridge Preservation Project: bridge repair, joint replace/ repair and deck overlay on bridge carrying Old Chicago Road over Forked Creek (0.5 mi N of Manteno Rd) Located in Wesley Township in Will County. | — | Executed | Iroquois Paving Corporation $499,318 · | ||
| Nov 17, 2023 | 62T12 | DuPageDistrict 1 | Bridge deck overlay and joint replacement of IL 83 over BNSF RR (S of Bluff Road) in the Downers Grove Townshi The proposed improvement consists of bridge deck overlay and joint replacement of IL 83 over BNSF RR (S of Bluff Road) in the Downers Grove Township, DuPage County. Total gross length and net length= 5442.65 FT (1.031 Ml), and 4811.44FT (0.911 Ml) | — | Executed | Lorig Construction Company $1,355,097 · | ||
| Nov 17, 2023 | 62T18 | CookDistrict 1 | Overlay of SN 016-2598 bridge deck overlay, parapet and railing repairs, deck scarification, pavement markings The scope of work consists of overlay of SN 016-2598 bridge deck overlay, parapet and railing repairs, deck scarification, pavement markings, and traffic control and protection. The project is located over UPRR in the Village of Northbrook in Cook County. Gross Length= Net Length =2658 FT (0.50 Mile). | — | Executed | Lorig Construction Company $1,108,628 · | ||
| Nov 17, 2023 | 62T36 | CookDistrict 1 | Deck scarification, latex concrete overlay, joint replacement, approach slab and slope wall repairs on Tower R (392-Ft) Bridge rehabilitation project and the scope consists of deck scarification, latex concrete overlay, joint replacement, approach slab and slope wall repairs on Tower Road over I-94/US41 (Edens Expressway) in the Villages of Glencoe and Northfield in Cook County. (SN 016-0815). | — | Executed | Lorig Construction Company $889,123 · | ||
| Nov 17, 2023 | 62T52 | CookDistrict 1 | Length: 452 ft (0.09 mi); Bridge Preservation Project: Bridge deck overlay and joint repair of SN 016-2038 carrying Wilson Avenue over I-94 (Edens Expwy) and ADA improvements in Cook County. | — | Executed | Lorig Construction Company $1,112,856 · | ||
| Nov 17, 2023 | 62T57 | CookDistrict 1 | (3.54-Mile) SMART Overlay and ADA Improvements on US 6 from Carol Avenue to IL 83 (Torrence Avenune). This project is located in the City of Harvey, Calumet City and the Village of South Holland in Cook County. | — | Executed | D. Construction, Inc. $4,811,131 · | ||
| Nov 17, 2023 | 62T65 | DuPageDistrict 1 | (2.09-Mile) SMART Overlay and pedestrian ramps (ADA) project. The scope included pavement patching, HMA surface removal and resurfacing, pedestrian ramp improvements, drainage structure adjustments, cleaning and placement of permanent pavement markings. This project begins on Beaumont Dr./ Shandrew Dr. at Ogden Ave. (US 34) and extends southwest of Aurora Rd. and is located within the City of Naperville in DuPage County. | — | Executed | Plote Construction, Inc. $1,874,899 · | ||
| Nov 17, 2023 | 62T74 | CookDistrict 1 | Pavement patching, PCC curb and gutter removal and replacement, pedestrian curb ramps improvements (ADA), hot- (2.33-Mile) Smart Overlay, crack and joint seal, ADA Improvements project consists of pavement patching, PCC curb and gutter removal and replacement, pedestrian curb ramps improvements (ADA), hot-mix asphalt surface removal and resurfacing and sealing of existing longitudinal joints and cracks. This project begins at IL-59 (FAP 338) at Dundee/Old Dundee Rd and extends northerly to Lake Cook Rd/Main St. The project is located within Barrington Township in Cook Co. | — | Executed | Builders Paving, LLC $978,000 · | ||
| Nov 17, 2023 | 62V23 | CookDistrict 1 | This improvement is a Bridge Painting on I-57 Under 175th St in the City of Country Club Hills in Cook County. (SN 016-1095) | — | Executed | Capital Industrial Services, LLC $683,300 · | ||
| Nov 17, 2023 | 62W13 | VariousDistrict 1 | Upgrading existing pedestrian push buttons to APS push buttons at various D1 ADA compliant intersections. | — | Executed | Meade Inc. $472,427 · | ||
| Nov 17, 2023 | 62W14 | CookDistrict 1 | Removing trees, as well as all incidental and collateral work necessary to complete the project as shown on th The project consists of removing trees, as well as all incidental and collateral work necessary to complete the project as shown on the plans and as described herein. 3,360 ft. (0.64 mi.) along IL 43, and 2,970 ft. (0.56 mi.) along 95th Street, tree removal, in Bridgeview, Oak Lawn, and Chicago Ridge, Cook County, IL. | — | Executed | Clean Cut Tree Service, Inc. $551,977 · | ||
| Nov 17, 2023 | 64918 | CarrollDistrict 2 | Patching, Resurfacing and ADA improvements on IL 78 from 0.2 mile N. of US 52/IL 64 to Carroll Creek in Mt. Carroll. | — | Executed | Martin & Company Excavating $1,429,025 · | ||
| Nov 17, 2023 | 64K73 | WinnebagoDistrict 2 | Removal and replacement of twin structures carrying IL Route 2 over the Rock River in Rockton. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $25,360,046 · | ||
| Nov 17, 2023 | 64S39 | WhitesideDistrict 2 | Bridge deck overlay, joint replacement and miscellaneous repairs on SN 098-0086, carrying IL 40 over I-88, 1 mile south of US 30. | — | Executed | Martin & Company Excavating $1,375,082 · | ||
| Nov 17, 2023 | 64S40 | WhitesideDistrict 2 | Bridge deck overlay, joint replacement, and miscellaneous repairs on SN 098-0091, carrying US 30 over I-88, 3 miles east of Rock Falls. | — | Executed | Martin & Company Excavating $1,248,487 · | ||
| Nov 17, 2023 | 64S43 | Rock IslandDistrict 2 | Bridge washing of SN 081-0011 over the Mississippi River in Rock Island County. | — | Executed | Interstate Maintenance, Incorporated $149,550 · | ||
| Nov 17, 2023 | 64S44 | Rock IslandDistrict 2 | Bridge washing of SN 081-0106 over the Mississippi River in Rock Island County. | — | Executed | Interstate Maintenance, Incorporated $59,340 · | ||
| Nov 17, 2023 | 64S45 | VariousDistrict 2 | Bridge washing of SN 008-0052, 098-6003 and 081-9905 over the Mississippi River in various counties. | — | Executed | Interstate Maintenance, Incorporated $123,440 · | ||
| Nov 17, 2023 | 66N39 | VariousDistrict 3 | This project consists on performing Bridge Deck Concrete Sealing with the parapets/curbs on various routes at various locations throughout Ford, Iroquois, and Kankakee Counties. | — | Executed | All States Painting, Inc. $196,144 · | ||
| Nov 17, 2023 | 66N83 | VariousDistrict 3 | Tree Removal located within Bureau, DeKalb, Ford, Grundy, La Salle, and Livings on counties. | — | Executed | Clean Cut Tree Service, Inc. $210,216 · | ||
| Nov 17, 2023 | 66N99 | VariousDistrict 3 | Repairing and maintaining traffic signals, flashing beacons, and roadway lighting in Ford, Iroquois, and Livin This project consists of repairing and maintaining traffic signals, flashing beacons, and roadway lighting in Ford, Iroquois, and Livingston Counties. | — | Executed | Leo P. Kelly Electric, Incorporated $350,818 · | ||
| Nov 17, 2023 | 68C00 | TazewellDistrict 4 | 3R project has a length of 0.58 miles extending from the east end of the Cedar St Bridge over the Illinois River to just east of Center St, including the Edmund St interchange. Work includes pavement patching, milling, resurfacing, and bridge rehabilitation. | — | Executed | ICC Group Inc. $14,978,000 · | ||
| Nov 17, 2023 | 68D36 | McDonoughDistrict 4 | Stream stabilization with riprap placement at various locations along Spring Creek, northwest of Macomb bypass. | — | Executed | Laverdiere Construction, Inc. $355,897 · | ||
| Nov 17, 2023 | 68G39 | MarshallDistrict 4 | Bridge repair and bridge deck overlay to S.N. 062-0056 over Thenius Creek 1/4 mi. N. of Sparland; S.N. 062-0057 over Gimlet Creek at the IL 29/IL 17 junction and S.N. 062-0059 over Senachwine Creek, 4 mi. W. of Sparland. | — | Executed | Stark Excavating, Inc. $2,030,255 · | ||
| Nov 17, 2023 | 68H77 | VariousDistrict 4 | District-wide replacement of pedestrian pushbuttons with APS push buttons. | — | Executed | Laser Electric, Inc. $1,741,480 · | ||
| Nov 17, 2023 | 68H79 | VariousDistrict 4 | Bridge painting: S.N. 072-0106 SB IL 6, S.N. 072-0107 NB I-474 Ramp 109, S.N. 072-0108 SB I-474 Ramp, 072-0109 NB I-474 Ramp 109, S.N. 048-0078 W. Knox Rd., S.N. 094-0028 Cameron Rd., S.N. 055-0021 CH 8, S.N. 048-0080 IL 180, S.N. 090-0043 US 150, S.N. 072-0228 US 24/IL 9. | — | Executed | Eagle Painting & Maintenance Company, Inc. $1,961,212 · | ||
| Nov 17, 2023 | 70G12 | McLeanDistrict 5 | Bridge painting of 3 structures on FAI 55 (I-55) and FAP 704 (I-55 Busn). | — | Executed | Eagle Painting & Maintenance Company, Inc. $1,273,331 · | ||
| Nov 17, 2023 | 72717 | BrownPikeDistrict 6 | Spray-applied pipe liner on IL 107 in Brown and Pike Counties. | — | Executed | Hoerr Construction, Inc. $567,640 · | ||
| Nov 17, 2023 | 72719 | SangamonDistrict 6 | Lot improvements to the Riverton Maintenance Yard. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $160,583 · | ||
| Nov 17, 2023 | 72807 | MontgomeryDistrict 6 | Tree removal at the Coalfield Rest Area. | — | Executed | Clean Cut Tree Service, Inc. $97,200 · | ||
| Nov 17, 2023 | 72F14 | SchuylerDistrict 6 | 7.3 miles of milling, resurfacing, bridge overlay (SN 085-0004), slope stabilization and guardrail replacement on IL 103 from 0.1 miles east of US 24 to 1.7 miles west of US 67. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $11,920,700 · | ||
| Nov 17, 2023 | 72F26 | AdamsDistrict 6 | Culvert replacement on IL 96 over a ditch, 1 mile north of Kochs Lane, north of Qunicy. | — | Executed | Laverdiere Construction, Inc. $1,932,532 · | ||
| Nov 17, 2023 | 72F59 | CassDistrict 6 | Culvert replacement (SN 009-7002) carrying IL 125 over a ditch 0.6 miles east of Warrior Hill Road. | — | Executed | Otto Baum Company, Inc. $1,524,200 · | ||
| Nov 17, 2023 | 72H57 | HancockDistrict 6 | Hydro-scarification, microsilica concrete overlay, expansion joint replacement and steel repairs on SN 034-0062 carrying US 136 over the Mississippi River from Hamilton, IL to Keokuk, IA. | — | Executed | Freesen, a div of UCM, Inc. $8,876,670 · | ||
| Nov 17, 2023 | 72K83 | SangamonDistrict 6 | Culvert replacement on IL 104 at Little Panther Creek, 1.9 miles west of IL 4 (SN 084-7061). | — | Executed | Kinney Contractors, Inc. $952,366 · | ||
| Nov 17, 2023 | 72K96 | MorganDistrict 6 | 5.2 miles of resurfacing on IL 78 from the Cass County line to just north of Snake Creek. | — | Executed | K. E. Vas Company $5,770,272 · | ||
| Nov 17, 2023 | 72M34 | MorganDistrict 6 | Painting portions of 7 bridges near Jacksonville. | — | Executed | Eagle Painting & Maintenance Company, Inc. $1,103,400 · | ||
| Nov 17, 2023 | 72M71 | BrownDistrict 6 | 4.8 miles of milling, patching, resurfacing and shoulders on US 24 from 0.5 miles east of Timewell Road to 0.3 miles west of Buckhorn / Damon Road in Mount Sterling. | — | Executed | Diamond Construction Company $4,650,700 · | ||
| Nov 17, 2023 | 74471 | FayetteDistrict 7 | 3.4 miles of resurfacing on US 40 from 0.5 miles west of the I-70 interchange to IL 185 in Vandalia, resurfacing the I-70 / US 40 ramps at the Vandalia Vandalia interchange and joint repairs and overlay to SN 026-0087. | — | Executed | Howell Paving, Inc. $5,506,589 · | ||
| Nov 17, 2023 | 74B29 | MaconDistrict 7 | Bridge deck overlay, joint replacement / repair and other bridge deck repairs on 3 structures: 1) SN 058-0060 carrying TR 4 (South Acom Road) over I-72; 2) SN 058-0062 carrying CH 27 (Lincoln Memorial Parkway) over I-72; 3) SN 058-0065 carrying Twin Lakes Road over I-72 just west of Decatur. | — | Executed | Freesen, a div of UCM, Inc. $1,224,997 · | ||
| Nov 17, 2023 | 74B30 | MaconDistrict 7 | Bridge deck overlay, joint repair and approach pavement on I-72 over Spring Creek, 1.3 miles east of Forsyth. | — | Executed | Freesen, a div of UCM, Inc. $1,953,030 · | ||
| Nov 17, 2023 | 74B31 | FayetteDistrict 7 | Bridge repairs on SN 026-0071 carrying IL 185 over I-57 in Farina. | — | Executed | Samron Midwest Contracting, Inc. $1,077,997 · | ||
| Nov 17, 2023 | 74B33 | MaconDistrict 7 | Bridge deck repair and overlay on SN 058-0129 carrying IL 121 over South Fork Creek, 0.7 miles east of the Logan County line. | — | Executed | Freesen, a div of UCM, Inc. $498,028 · | ||
| Nov 17, 2023 | 74B34 | EffinghamDistrict 7 | Bridge deck overlay, bridge joint replacement, deck drain replacement, bridge deck patching on SN 025-0089 carrying IL 37 over the Little Wabash River, 0.5 miles south of I-57. | — | Executed | Sangamo Construction Company $761,969 · | ||
| Nov 17, 2023 | 74B35 | ClarkDistrict 7 | Bridge deck overlay and joint replacement and repairs on SN 012-0025 carrying US 40 over I-70. | — | Executed | Sangamo Construction Company $1,282,944 · | ||
| Nov 17, 2023 | 74B37 | WabashDistrict 7 | Washing the bridge deck on SN 093-0021 carrying IL 15 over the Wabash River in Mt. Carmel. | — | Executed | |||
| Nov 17, 2023 | 74B39 | MaconDistrict 7 | Bridge deck overlay, joint replacement, deck patching, structural concrete repair, crashwall extensions and HMA approaches on SN 058-0087 carrying Kirby Road over I-72, northeast of Decatur. | — | Executed | Freesen, a div of UCM, Inc. $638,193 · | ||
| Nov 17, 2023 | 74C65 | CumberlandDistrict 7 | Bridge joint replacement / repair, bridge deck repairs and bridge deck overlay on SN 018-0003 and 018-0004 carrying I-57 over US 45 and SN 018-0001 and 018-0002 carrying I-57 over the Decatur and Eastern Illinois Railroad, all located northeast of Neoga. | — | Executed | Path Construction Company, Inc. $1,994,773 · | ||
| Nov 17, 2023 | 76M88 | WashingtonDistrict 8 | Culvert replacement on IL 127 at South Middle Tributary of Locust Creek, 6.7 miles south of IL 15 and the town of Nashville. (SN 095-2496) | — | Executed | E. T. Simonds Construction Company $747,934 · | ||
| Nov 17, 2023 | 76M90 | WashingtonDistrict 8 | Culvert replacement on IL 177 at West Tributary to Grand Point, 0.5 miles east of Hoyleton. (SN 095-2496) | — | Executed | Guinzy Construction,Inc. $490,747 · | ||
| Nov 17, 2023 | 76N16 | MadisonDistrict 8 | Bridge repairs, flood wall work and pavement reconstruction on IL 11 over Cahokia Diversion Channel (SN 060-0121), 3 miles north of I-270. | — | Executed | The Kilian Corporation $1,832,257 · | ||
| Nov 17, 2023 | 76N43 | MadisonDistrict 8 | Intersection reconstruction and ADA upgrades on IL 3 at 20th Street in Granite City. | — | Executed | Baxmeyer Construction, Inc. $7,285,268 · | ||
| Nov 17, 2023 | 76T01 | VariousDistrict 8 | Traffic signal modernization at various locations within District 8. | — | Executed | Gerstner Electric, Inc. $1,564,128 · | ||
| Nov 17, 2023 | 76T39 | St. ClairDistrict 8 | 1.96 miles of patching and a standard overlay on I-55/64/US 40 from 0.9 miles east of the Mississippi River to I-64 (Tri-Level) Interchange in East St. Louis | — | Executed | The Kilian Corporation $5,220,980 · | ||
| Nov 17, 2023 | 78199 | PerryDistrict 9 | Replacement of a bridge with a double reinforced concrete box culvert on US 51 north of Tamaroa. (SN 073-0002) | — | Executed | E. T. Simonds Construction Company $924,177 · | ||
| Nov 17, 2023 | 78771 | SalineDistrict 9 | Intersection reconstruction at the intersection of US 45 and Poplar (Old IL 13) in Harrisburg. | — | Executed | E. T. Simonds Construction Company $1,369,045 · | ||
| Nov 17, 2023 | 78809 | GallatinDistrict 9 | Slope stabilization at SN 030-0021 carrying IL 1 over the Saline River, 2.5 miles south of IL 13, southeast of Equality. | — | Executed | E. T. Simonds Construction Company $399,347 · | ||
| Nov 17, 2023 | 78929 | JacksonDistrict 9 | 0.75 miles of resurfacing on North 6th Street in Murphysboro. | — | Executed | Samron Midwest Contracting, Inc. $339,339 · | ||
| Nov 17, 2023 | 78A02 | AlexanderJacksonUnionDistrict 9 | 25.4 miles of patching, milling, resurfacing and shoulders on IL 3 from Howardton Road, near Grand Tower, to the Cape T intersection. | — | Executed | E. T. Simonds Construction Company $11,663,246 · | ||
| Nov 17, 2023 | 85727 | WinnebagoDistrict 2 | Sidewalk construction along Parkview Avenue from Spring Creek Road to Birchwood Drive in Rockford. | — | Executed | N-Trak Group LLC $489,794 · | ||
| Nov 17, 2023 | 89815 | PeoriaDistrict 4 | Structure rehabilitation with replacement of approach slabs, bridge deck, parapets, beams, expansion joints, bearings, concrete slope walls. Also included will be PCC pavement with curb and gutter, and storm sewers on Maxwell Road over the Union Pacific Railroad, 0.2 miles south of IL 116. | — | Executed | Stark Excavating, Inc. $4,569,990 · | ||
| Nov 17, 2023 | 89824 | TazewellDistrict 4 | Resurfacing Fischer Road from IL 29 to Creve Coeur Avenue in Creve Coeur. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $408,195 · | ||
| Nov 17, 2023 | 93775 | MenardDistrict 6 | Widening and HMA resurfacing with aggregate shoulders and pipe culverts on Athens Blacktop from Cantrall Road to Kent Street. | — | Executed | K. E. Vas Company $3,709,353 · | ||
| Nov 17, 2023 | 93812 | SangamonDistrict 6 | HMA resurfacing with pavement markings on Cardinal Hill Road from New City Road to north of IL 104. | — | Executed | P. H. Broughton & Sons, Inc. $1,082,697 · | ||
| Nov 17, 2023 | 95941 | MoultrieDistrict 7 | Sidewalk Construction on various routes within the City of Sullivan. | — | Executed | A & R Mechanical Service, Inc. $288,741 · | ||
| Nov 17, 2023 | 97790 | MadisonDistrict 8 | Reconstruction of Lebanon Road on new alignment to facilitate closure of two underpass structures. Work includes structure removal, construction of a 6-span steel plate girder bridge, construction of a 1-span PC slabl bridge, box culverts, pavement removal, building removal, processing lime modified soil, PPC Pavement, HMA Pavement, HMA shoulders, combination curb and gutter, and storm sewer. Located 0.19 miles east of Clay School Road to 0.16 miles of Locmann Road over the CSX Railroad. | — | Executed | Keller Construction, Inc. $17,444,384 · | ||
| Nov 17, 2023 | 97793 | MadisonDistrict 8 | Reconstruction of the IL 159 and Glen Carbon Road intersection to establish north bound and east bound right turn lanes. Includes, HMA resurfacing, sidewalks, ADA ramps, traffic signal modifications, and drainage improvements. Located in Glen Carbon. | — | Rejected | Keller Construction, Inc. $1,439,471 · | ||
| Nov 17, 2023 | 97815 | St. ClairDistrict 8 | Resurfacing Jerome Lane from Nash Street to Range Lane in Cahokia. | — | Executed | Christ Bros. Asphalt, Inc. $897,940 · | ||
| Nov 17, 2023 | 97817 | St. ClairDistrict 8 | Construction of a PCC sidewalk from the Boul Avenue Trailhead entrance to the intersection of Boul Avenue and IL 159 in Swansea. | — | Rejected | |||
| Nov 17, 2023 | 97822 | MadisonDistrict 8 | Resurfacing West Airline Drive from Main Street to 9th Street in East Alton. | — | Executed | Charles E. Mahoney Co. $858,985 · | ||
| Nov 17, 2023 | 99673 | WilliamsonDistrict 9 | Resurfacing East Grand Avenue from Hurricane Road to IL 148. | — | Executed | Samron Midwest Contracting, Inc. $402,402 · | ||
| Nov 17, 2023 | 99711 | JacksonDistrict 9 | Resurfacing North Marion Street from East Fischer Street to Dillinger Road. | — | Executed | E. T. Simonds Construction Company $658,507 · | ||
| Nov 17, 2023 | 99713 | JacksonDistrict 9 | Replace existing structure with a precast concrete box culvert with pre-cast box culvert end sections, PCC pavement, sidewalk, curb and gutter, on East College Street over Piles Fork Creek in Carbondale. | — | Executed | E. T. Simonds Construction Company $553,288 · | ||
| Nov 17, 2023 | 99716 | WilliamsonDistrict 9 | Remove and replace sidewalks, ADA ramps and crosswalks along North 18 Street from East Herrin Street to West Monroe Street in Herrin. | — | Executed | E. T. Simonds Construction Company $290,697 · | ||
| Nov 17, 2023 | 99720 | WilliamsonDistrict 9 | HMA resurfacing on Lake of Egypt Road from IL 37 to South Market Road, and on Power Plant Road from Lake of Egypt Road to County Club Road. Includes HMA and aggregate shoulders, guardrail adjustments and replacements, and raised pavement markers. | — | Executed | Samron Midwest Contracting, Inc. $1,664,664 · | ||
| Jan 19, 2024 | 46638 | St. ClairDistrict 8 | Pavement marking replacement at various locations in St. Clair County. | — | Active | ROADSAFE TRAFFIC SYSTEMS, INC. $894,895 · | ||
| Jan 19, 2024 | 46640 | VariousDistrict 2 | Removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and p This work consists of removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and placing new raised reflective pavement marker castings within the limits shown on each individual work order. | — | Executed | P & P Construction Co. $1,104,220 · | ||
| Jan 19, 2024 | 46933 | MarionDistrict 8 | Resurfacing main and secondary park roads and parking lots, as well as culvert and bridge replacement, signage and lighting at the Stephen A. Forbes Recreation Area in Marion County. | — | Executed | DMS Contracting, Inc. $8,455,395 · | ||
| Jan 19, 2024 | 61H98 | WillDistrict 1 | Pavement widening and reconstruction, storm sewer, sidewalk replacment, curb and gutter replacement, concrete box culvert, pavement markings, traffic signals, and water main replacement on IL 7 from Lincoln Street to Summit Drive in Lockport. | — | Executed | Austin Tyler Construction, Inc. $10,458,102 · | ||
| Jan 19, 2024 | 61J53 | CookDistrict 1 | Sidewalk construction, drainage improvements, and traffic signal modifications on Wolf Road from Palatine Frontage Road to Edward Road/Metra Station in Prospect Heights. | — | Executed | Acura Inc. $2,725,444 · | ||
| Jan 19, 2024 | 61J70 | CookDistrict 1 | HMA resurfacing, patching, driveway replacement, curb and gutter, sidewalks, drainage and utility structure adjustments, pavement markings, signage, traffic signal ADA improvements and all other necessary work on Bernice Road from Torrence Avenue to Wentwork Avenue in the Village of Lansing. | — | Executed | Iroquois Paving Corporation $1,794,008 · | ||
| Jan 19, 2024 | 61J73 | CookDistrict 1 | HMA resurfacing with patching, bike path, pedestrian push buttons, ADA ramps, and landscaping on Wilke Road from US 14 to IL 62 in Arlington Heights. | — | Executed | Builders Paving, LLC $4,487,708 · | ||
| Jan 19, 2024 | 61J74 | CookDistrict 1 | Sidewalk replacement with curb and gutter, pavement marking, signage, and landscaping along various routes in the Village of Niles. | — | Rejected | Alliance Contractors, Inc. $4,584,998 · | ||
| Jan 19, 2024 | 61J82 | LakeDistrict 1 | Sidewalk reconstruction and traffic signal modifications at the intersection of Central Avenue and Hickory Street in Highland Park. | — | Executed | Alliance Contractors, Inc. $318,100 · | ||
| Jan 19, 2024 | 61J95 | DuPageDistrict 1 | Resurfacing Central Avenue from Thomdale Avenue to Foster Avenue in Wood Dale. | — | Executed | Builders Paving, LLC $726,808 · | ||
| Jan 19, 2024 | 61J96 | McHenryDistrict 1 | Resurfacing Bull Valley Road from Curran Road to Crystal Lake Road in McHenry. | — | Executed | Geske and Sons, Inc. $255,964 · | ||
| Jan 19, 2024 | 61J97 | WillDistrict 1 | Resurfacing on St. Francis Road from US 45 to 88th Avenue in Frankfort | — | Executed | P. T. Ferro Construction Co. $856,758 · | ||
| Jan 19, 2024 | 61J98 | McHenryDistrict 1 | HMA resurfacing with aggregate shoulders on Winn Road from IL 173 to Main Street in Spring Grove. | — | Executed | Payne & Dolan, Inc. $1,194,568 · | ||
| Jan 19, 2024 | 61K02 | DuPageDistrict 1 | Roadway reconstruction on Janes Avenue from 7th Street to Spring Street in Woodridge. | — | Executed | K-Five Construction Corporation $2,045,192 · | ||
| Jan 19, 2024 | 61K05 | LakeDistrict 1 | HMA resurfacing, widening, storm sewers, drainage structures, PCC sidewalks, HMA multi-use patch, and traffic signal improvements at the intersection of Wadsworth Road and Lewis Avenue in Waukegan and Beach Park. | — | Executed | Campanella and Sons, Inc. $4,199,910 · | ||
| Jan 19, 2024 | 61K06 | CookDistrict 1 | Pavement widening, full-depth HMA reconstruction, storm sewer, sidewalk replacement, curb and gutter Replacement, guardrail and roadway lighting on Irving Park Road from Schaumburg Road to IL 59 in Streamwood. | — | Rejected | Martam Construction Incorporated $10,716,009 · | ||
| Jan 19, 2024 | 61K08 | CookDistrict 1 | HMA resurfacing with ADA improvements, curb and gutter, multi-use path, landscaping, patching drainage adjustments, and striping on Illinois Avenue from Quentin Road to Plum Grove Road in Palatine. | — | Executed | A Lamp Concrete Contractors, Inc. $1,540,000 · | ||
| Jan 19, 2024 | 61K09 | CookDistrict 1 | Resurfacing Central Road from Westgate Road to Wolf Road in Mount Prospect. | — | Executed | Builders Paving, LLC $986,318 · | ||
| Jan 19, 2024 | 62H58 | WillDistrict 1 | Parking lot improvement. Full depth removal and replacement of existing pavement. Location: Movable Bridge Maintenance Yard (105 Bridge Street) in the City of Joliet, Will County. | — | Executed | Austin Tyler Construction, Inc. $211,505 · | ||
| Jan 19, 2024 | 62K60 | CookDistrict 1 | 2,408 feet (0.456 mile) bridge replacement of US 12/20/45 (La Grange Road) at IL 171 (Archer Ave/19th Street), SN 016-0518, in the Village of Willow Springs, Cook County. | — | Executed | Dunnet Bay Construction Company $7,746,876 · | ||
| Jan 19, 2024 | 62M52 | CookDistrict 1 | 1,185-feet (0.22-mile) Bridge rehabilitation project includes deck scarification, latex concrete overlay, joint replacement and approach slab repairs on Roosevelt Road over I-90/94 (Dan Ryan Expressway) (SN 016-0478) within the City of Chicago in Cook County. | — | Executed | Martam Construction Incorporated $1,269,651 · | ||
| Jan 19, 2024 | 62R40 | DuPageDistrict 1 | Earth excavation, removal and construction of a pipe culvert and drainages structure, pavement removal and ful (803-Ft) Curve correction project consists of earth excavation, removal and construction of a pipe culvert and drainages structure, pavement removal and full-depth HMA pavement, located along I-55 North Frontage Road at Cass Avenue in the City of Darien in DuPage County. | — | Executed | Martam Construction Incorporated $673,990 · | ||
| Jan 19, 2024 | 62R89 | WillDistrict 1 | The reconstruction of I-80 mainline pavement from west of Joliet Junction Trail to Wheeler Avenue The project consists of the reconstruction of I-80 mainline pavement from west of Joliet Junction Trail to Wheeler Avenue. The work also includes reconstruction of the I-80 EB Bridge over Joliet Junction Trail, the l-80 WB Bridge over Joliet Junction Trail, I-80 EB Bridge over Midland Avenue, and the I-80 WB Bridge over Midland Avenue. Other work includes drainage system improvements, signing, lighting, temporary traffic signals, ITS improvements, and noise abatement walls. The project is in the | — | Executed | Walsh Construction Company II, LLC $94,772,970 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.