D7 BRIDGE REPAIRS 2024-8
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sangamo Construction Company Low bidder | $761,969 | ||
| 2 | Keeley & Sons, Inc. | $792,406 | +4.0% | |
| 3 | Samron Midwest Contracting, Inc. | $830,516 | +9.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sangamo Constru… | #2 Keeley & Sons, … | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | X5030250 | BR DECK GROOVING LONG | 992 | SQ YD | $14.03 | $13.45 | $17.00 | |
| 2 | Z0001800 | APPR SLAB REPAIR (PD) | 1 | SQ YD | $1,609.02 | $2,980.00 | $1,195.00 | |
| 3 | Z0012111 | BRD FLYASH/SLAG 2 1/2 | 1,271 | SQ YD | $138.16 | $119.80 | $90.00 | |
| 4 | Z0012130 | BR DECK SCAR 3/4 | 1,271 | SQ YD | $58.51 | $77.45 | $88.00 | |
| 5 | Z0016001 | DECK SLAB REP (FD-T1) | 26 | SQ YD | $2,713.07 | $2,870.00 | $3,000.00 | |
| 6 | Z0016002 | DECK SLAB REP (FD-T2) | 8 | SQ YD | $1,635.81 | $1,970.00 | $2,800.00 | |
| 7 | Z0029090 | DIAMOND GRIND BR SEC | 1,112 | SQ YD | $16.44 | $15.45 | $15.00 | |
| 8 | 35300500 | PCC BSE CSE 10 | 207 | SQ YD | $184.91 | $147.45 | $220.00 | |
| 9 | 40600290 | BIT MATLS TACK CT | 291 | POUND | $0.9500 | $0.9100 | $1.00 | |
| 10 | 40600982 | HMA SURF REM BUTT JT | 213 | SQ YD | $53.27 | $51.10 | $60.00 | |
| 11 | 40600990 | TEMPORARY RAMP | 41 | SQ YD | $106.61 | $65.00 | $0.0100 | |
| 12 | 40604052 | HMA SC IL-9.5 C N70 | 37 | TON | $641.97 | $615.73 | $750.00 | |
| 13 | 50102400 | CONC REM | 5.6 | CU YD | $3,457.54 | $2,990.00 | $4,200.00 | |
| 14 | 50300100 | FLOOR DRAINS | 56 | EACH | $922.65 | $1,390.00 | $750.00 | |
| 15 | 50300255 | CONC SUP-STR | 6.2 | CU YD | $4,260.34 | $3,495.00 | $5,200.00 | |
| 16 | 50300300 | PROTECTIVE COAT | 1,288 | SQ YD | $3.81 | $2.65 | $2.00 | |
| 17 | 50800205 | REINF BARS, EPOXY CTD | 960 | POUND | $7.84 | $4.90 | $5.00 | |
| 18 | 50800515 | BAR SPLICERS | 12 | EACH | $109.49 | $76.90 | $65.00 | |
| 19 | 52000110 | PREF JT STRIP SEAL | 68 | FOOT | $273.03 | $357.90 | $240.00 | |
| 20 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $3,552.83 | $3,670.00 | $2,000.00 | |
| 21 | 67100100 | MOBILIZATION | 1 | L SUM | $44,956.15 | $46,890.00 | $49,000.00 | |
| 22 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $34,563.42 | $33,890.00 | $69,000.00 | |
| 23 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1.00 | $790.00 | $48,500.00 | |
| 24 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $1.00 | $1,510.00 | $0.0100 | |
| 25 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $15,776.55 | $23,890.00 | $30,000.00 | |
| 26 | 70107005 | PAVT MK BLKOUT TAPE 5 | 1,168 | FOOT | $5.26 | $2.35 | $2.75 | |
| 27 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $160.66 | $118.94 | $150.00 | |
| 28 | 70300150 | SHRT TRM PAVT MK REM | 486 | SQ FT | $2.46 | $0.3100 | $0.7500 | |
| 29 | 70400100 | TEMP CONC BARRIER | 687.5 | FOOT | $52.99 | $67.45 | $35.00 | |
| 30 | 70400200 | REL TEMP CONC BARRIER | 625 | FOOT | $9.26 | $11.45 | $10.00 | |
| 31 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $6,398.78 | $4,760.00 | $5,500.00 | |
| 32 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $1,524.11 | $890.00 | $750.00 | |
| 33 | 78001110 | PAINT PVT MK LINE 4 | 2,302 | FOOT | $1.66 | $2.04 | $1.50 |