10-04106-00-BR
- Let date
- Friday, November 17, 2023
- Contract
- 97790 · job page
- District
- District 8
- County
- Madison
- Highway
- Limits
- Reconstruction of Lebanon Road on new alignment to facilitate closure of two underpass structures. Work includes structure removal, construction of a 6-span steel plate girder bridge, construction of a 1-span PC slabl bridge, box culverts, pavement removal, building removal, processing lime modified soil, PPC Pavement, HMA Pavement, HMA shoulders, combination curb and gutter, and storm sewer. Located 0.19 miles east of Clay School Road to 0.16 miles of Locmann Road over the CSX Railroad.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Keller Construction, Inc. Low bidder | $17,444,384 | ||
| 2 | Keeley & Sons, Inc. | $18,748,426 | +7.5% | |
| 3 | Plocher Construction Company, Inc. | $19,797,000 | +13.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Keller Construc… | #2 Keeley & Sons, … | #3 Plocher Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | XX009603 | P CUL CL A 3 EQRS 84 | 243 | FOOT | $1,507.00 | $1,196.09 | $1,781.53 | |
| 2 | X0326275 | RR ROW ENTRY PERMIT | 1 | EACH | $2,282.00 | $9,390.00 | $200,000.00 | |
| 3 | X2800400 | PERIMETER EROS BAR SP | 19,564 | FOOT | $14.17 | $6.63 | $13.50 | |
| 4 | X4400110 | TEMP PAVT REMOVAL | 718 | SQ YD | $15.25 | $8.16 | $9.76 | |
| 5 | X5030305 | CONC WEARING SURF 5 | 283 | SQ YD | $106.00 | $109.65 | $140.00 | |
| 6 | X5040100 | PREC BRIDGE APP SLAB | 2,340 | SQ FT | $67.44 | $69.80 | $45.00 | |
| 7 | X6024242 | INLETS SPL N1 | 3 | EACH | $6,024.00 | $5,828.28 | $5,714.00 | |
| 8 | X6024875 | TEMPORARY INLET | 1 | EACH | $3,495.00 | $3,779.10 | $3,705.00 | |
| 9 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $36,700.00 | $82,977.00 | $250,000.00 | |
| 10 | Z0004542 | HMA REMOVAL SPL | 2,105 | SQ YD | $16.00 | $7.55 | $12.72 | |
| 11 | Z0004544 | HMA DRIVWY PAVT REM | 1,633 | SQ YD | $14.00 | $8.00 | $11.21 | |
| 12 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $22,335.00 | $13,890.00 | $25,000.00 | |
| 13 | Z0007602 | BLDG REMOV NO 2 | 1 | L SUM | $14,432.00 | $13,890.00 | $18,000.00 | |
| 14 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $66,000.00 | $121,450.00 | $100,000.00 | |
| 15 | Z0018002 | DRAINAGE SCUPPR DS-11 | 1 | EACH | $2,959.00 | $2,390.00 | $2,100.00 | |
| 16 | Z0022800 | FENCE REMOVAL | 307 | FOOT | $8.35 | $5.00 | $5.97 | |
| 17 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $102,000.00 | $67,890.00 | $13,000.00 | |
| 18 | Z0049801 | R&D FRIABL ASB BLD 1 | 1 | L SUM | $3,675.00 | $25,500.00 | $3,500.00 | |
| 19 | Z0049902 | R&D NON-FR ASB BLD 2 | 1 | L SUM | $3,675.00 | $25,500.00 | $2,000.00 | |
| 20 | Z0062456 | TEMP PAVEMENT | 718 | SQ YD | $77.66 | $97.85 | $108.50 | |
| 21 | Z0076600 | TRAINEES | 2,500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 22 | Z0076604 | TRAINEES TPG | 2,500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 23 | 20100110 | TREE REMOV 6-15 | 1,673 | UNIT | $52.50 | $34.68 | $41.00 | |
| 24 | 20100210 | TREE REMOV OVER 15 | 772 | UNIT | $78.75 | $49.98 | $56.51 | |
| 25 | 20100500 | TREE REMOV ACRES | 10 | ACRE | $19,575.00 | $14,790.00 | $34,062.00 | |
| 26 | 20200100 | EARTH EXCAVATION | 125,105 | CU YD | $14.35 | $8.02 | $7.86 | |
| 27 | 20700110 | POROUS GRAN EMBANK | 1,602 | TON | $79.00 | $33.92 | $33.25 | |
| 28 | 20800150 | TRENCH BACKFILL | 819 | CU YD | $75.00 | $53.01 | $51.97 | |
| 29 | 20900110 | POROUS GRAN BACKFILL | 180 | CU YD | $93.00 | $125.26 | $80.00 | |
| 30 | 25000200 | SEEDING CL 2 | 12 | ACRE | $1,863.00 | $2,040.00 | $2,000.00 | |
| 31 | 25000400 | NITROGEN FERT NUTR | 1,080 | POUND | $3.15 | $3.06 | $3.00 | |
| 32 | 25000500 | PHOSPHORUS FERT NUTR | 1,080 | POUND | $3.15 | $3.06 | $3.00 | |
| 33 | 25000600 | POTASSIUM FERT NUTR | 1,080 | POUND | $3.15 | $3.06 | $3.00 | |
| 34 | 25100115 | MULCH METHOD 2 | 12 | ACRE | $2,730.00 | $1,836.00 | $1,800.00 | |
| 35 | 25100127 | MULCH METHOD 3A | 12 | ACRE | $7,297.50 | $3,060.00 | $3,000.00 | |
| 36 | 25100630 | EROSION CONTR BLANKET | 5,473 | SQ YD | $3.99 | $1.28 | $1.25 | |
| 37 | 25100635 | HD EROS CONTR BLANKET | 3,046 | SQ YD | $5.25 | $2.04 | $2.00 | |
| 38 | 28000200 | EARTH EXC - EROS CONT | 101 | CU YD | $75.00 | $17.45 | $27.19 | |
| 39 | 28000250 | TEMP EROS CONTR SEED | 1,303 | POUND | $3.70 | $3.06 | $3.25 | |
| 40 | 28000305 | TEMP DITCH CHECKS | 719 | FOOT | $23.99 | $20.40 | $22.85 | |
| 41 | 28000315 | AGG DITCH CHECKS | 408 | TON | $115.50 | $96.90 | $110.00 | |
| 42 | 28000400 | PERIMETER EROS BAR | 7,288 | FOOT | $4.73 | $1.79 | $4.50 | |
| 43 | 28000500 | INLET & PIPE PROTECT | 70 | EACH | $194.25 | $204.00 | $185.00 | |
| 44 | 28001000 | AGGREGATE - EROS CONT | 244 | TON | $80.97 | $53.45 | $62.00 | |
| 45 | 28100107 | STONE RIPRAP CL A4 | 2,817 | SQ YD | $64.14 | $30.17 | $29.57 | |
| 46 | 28100807 | STONE DUMP RIP CL A4 | 197 | TON | $81.71 | $88.74 | $87.00 | |
| 47 | 28200200 | FILTER FABRIC | 4,328 | SQ YD | $5.24 | $3.83 | $3.75 | |
| 48 | 28300400 | AGGREGATE DITCH | 336 | TON | $74.06 | $49.85 | $293.64 | |
| 49 | 30200650 | PROCESS MOD SOIL 12 | 17,896 | SQ YD | $4.35 | $3.22 | $3.15 | |
| 50 | 30201500 | LIME | 345 | TON | $226.00 | $251.11 | $246.18 | |
| 51 | 31100300 | SUB GRAN MAT A 4 | 6,145 | SQ YD | $9.00 | $7.60 | $15.00 | |
| 52 | 31101900 | SUB GRAN MAT C | 1,004 | TON | $83.00 | $80.93 | $89.13 | |
| 53 | 31200500 | STAB SUBBASE HMA 4 | 7,975 | SQ YD | $37.00 | $36.04 | $35.33 | |
| 54 | 35101100 | AGG BASE CSE A 12 | 2,784 | SQ YD | $28.00 | $25.65 | $28.00 | |
| 55 | 35102100 | AGG BASE CSE B 9 | 615 | SQ YD | $28.00 | $26.00 | $20.00 | |
| 56 | 40200800 | AGG SURF COURSE TY B | 679 | TON | $47.00 | $43.85 | $59.00 | |
| 57 | 40201000 | AGGREGATE-TEMP ACCESS | 810 | TON | $37.00 | $69.16 | $49.28 | |
| 58 | 40600275 | BIT MATLS PR CT | 39,319.3 | POUND | $0.6900 | $0.6800 | $0.6600 | |
| 59 | 40600290 | BIT MATLS TACK CT | 7,833.1 | POUND | $7.00 | $6.81 | $6.67 | |
| 60 | 40701841 | HMA PAVT FD 8 | 8,674 | SQ YD | $65.46 | $63.60 | $62.35 | |
| 61 | 40701881 | HMA PAVT FD 10 | 6,260 | SQ YD | $79.48 | $77.22 | $75.70 | |
| 62 | 40800025 | BIT MATLS PR CT | 6,725.6 | POUND | $0.6900 | $0.6800 | $0.6600 | |
| 63 | 40800050 | INCIDENTAL HMA SURF | 582 | TON | $186.92 | $181.59 | $178.02 | |
| 64 | 42000080 | PVT CON PCC BR APP SL | 889 | SQ YD | $151.00 | $159.80 | $160.00 | |
| 65 | 42001300 | PROTECTIVE COAT | 3,666 | SQ YD | $1.22 | $3.85 | $3.75 | |
| 66 | 42300200 | PCC DRIVEWAY PAVT 6 | 468 | SQ YD | $156.70 | $93.85 | $150.00 | |
| 67 | 44000100 | PAVEMENT REM | 6,304 | SQ YD | $12.80 | $12.85 | $14.15 | |
| 68 | 44000200 | DRIVE PAVEMENT REM | 185 | SQ YD | $15.50 | $23.80 | $37.75 | |
| 69 | 44000400 | GUTTER REM | 90 | FOOT | $12.50 | $13.95 | $3.01 | |
| 70 | 44004000 | PAVED DITCH REMOVAL | 210 | FOOT | $10.00 | $19.65 | $20.71 | |
| 71 | 48101500 | AGGREGATE SHLDS B 6 | 1,061 | SQ YD | $42.74 | $19.80 | $28.50 | |
| 72 | 48102100 | AGG WEDGE SHLD TYPE B | 48 | TON | $75.92 | $47.90 | $190.60 | |
| 73 | 48203029 | HMA SHOULDERS 8 | 3,519 | SQ YD | $65.63 | $63.77 | $62.51 | |
| 74 | 50100100 | REM EXIST STRUCT | 1 | EACH | $8,000.00 | $3,990.00 | $3,800.00 | |
| 75 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $28,000.00 | $23,890.00 | $40,000.00 | |
| 76 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $8,000.00 | $9,870.00 | $9,300.00 | |
| 77 | 50100500 | REM EXIST STRUCT N3 | 1 | EACH | $9,600.00 | $9,870.00 | $10,000.00 | |
| 78 | 50104400 | CONC HEADWALL REMOVAL | 2 | EACH | $500.00 | $670.00 | $1,200.00 | |
| 79 | 50105220 | PIPE CULVERT REMOV | 586 | FOOT | $29.50 | $17.90 | $27.10 | |
| 80 | 50200100 | STRUCTURE EXCAVATION | 3,579 | CU YD | $27.30 | $29.85 | $35.00 | |
| 81 | 50200450 | REM/DISP UNS MATL-STR | 321 | CU YD | $25.00 | $51.80 | $55.00 | |
| 82 | 50300100 | FLOOR DRAINS | 8 | EACH | $575.00 | $937.80 | $1,000.00 | |
| 83 | 50300225 | CONC STRUCT | 1,578.8 | CU YD | $680.00 | $967.80 | $1,000.00 | |
| 84 | 50300255 | CONC SUP-STR | 1,043 | CU YD | $931.50 | $1,487.90 | $1,400.00 | |
| 85 | 50300260 | BR DECK GROOVING | 3,149 | SQ YD | $7.22 | $6.63 | $7.00 | |
| 86 | 50300280 | CONCRETE ENCASEMENT | 3 | CU YD | $1,265.00 | $987.15 | $3,000.00 | |
| 87 | 50300300 | PROTECTIVE COAT | 3,968 | SQ YD | $1.75 | $3.80 | $4.25 | |
| 88 | 50400105 | PREC CONC BR SLAB | 1,166 | SQ FT | $99.75 | $139.80 | $100.00 | |
| 89 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $2,984,450.00 | $3,705,890.00 | $3,566,000.00 | |
| 90 | 50500505 | STUD SHEAR CONNECTORS | 10,854 | EACH | $4.04 | $4.19 | $4.11 | |
| 91 | 50800105 | REINFORCEMENT BARS | 68,590 | POUND | $0.0100 | $1.80 | $1.60 | |
| 92 | 50800205 | REINF BARS, EPOXY CTD | 613,900 | POUND | $1.41 | $1.85 | $1.70 | |
| 93 | 50901050 | STEEL RAILING TY SM | 102 | FOOT | $257.00 | $261.63 | $245.00 | |
| 94 | 50901730 | BRIDGE FENCE RAILING | 240 | FOOT | $309.00 | $235.11 | $295.00 | |
| 95 | 51100100 | SLOPE WALL 4 | 577 | SQ YD | $125.00 | $97.85 | $190.00 | |
| 96 | 51201600 | FUR STL PILE HP12X53 | 1,871 | FOOT | $79.14 | $76.80 | $80.00 | |
| 97 | 51201900 | FUR STL PILE HP14X89 | 6,260 | FOOT | $85.00 | $97.80 | $98.00 | |
| 98 | 51202305 | DRIVING PILES | 8,131 | FOOT | $0.0100 | $0.0100 | $0.1000 | |
| 99 | 51203600 | TEST PILE ST HP12X53 | 4 | EACH | $18,600.00 | $9,780.00 | $15,000.00 | |
| 100 | 51203900 | TEST PILE ST HP14X89 | 6 | EACH | $7,000.00 | $11,650.00 | $32,500.00 | |
| 101 | 51204650 | PILE SHOES | 244 | EACH | $140.75 | $135.00 | $150.00 | |
| 102 | 51500100 | NAME PLATES | 5 | EACH | $794.00 | $985.00 | $775.00 | |
| 103 | 52000110 | PREF JT STRIP SEAL | 97 | FOOT | $330.00 | $367.80 | $140.00 | |
| 104 | 52100010 | ELAST BEARING ASSY T1 | 30 | EACH | $6,550.00 | $4,990.15 | $6,000.00 | |
| 105 | 52100530 | ANCHOR BOLTS 1 1/4 | 84 | EACH | $200.00 | $137.85 | $200.00 | |
| 106 | 52200020 | TEMP SOIL RETEN SYSTM | 1,696 | SQ FT | $0.0100 | $89.65 | $91.50 | |
| 107 | 52318802 | DRAINAGE SYSTEM FOR STRUCTURES | 1 | L SUM | $40,400.00 | $33,890.00 | $60,000.00 | |
| 108 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $24,450.00 | $50,663.40 | $49,670.00 | |
| 109 | 54001002 | BOX CUL END SEC C2 | 2 | EACH | $20,000.00 | $35,650.00 | $34,520.00 | |
| 110 | 54003000 | CONC BOX CUL | 318 | CU YD | $950.00 | $1,130.90 | $1,200.00 | |
| 111 | 54010707 | PCBC 7X7 | 58 | FOOT | $1,222.00 | $1,483.71 | $1,454.61 | |
| 112 | 54010808 | PCBC 8X8 | 87 | FOOT | $1,333.00 | $1,504.12 | $1,474.62 | |
| 113 | 542A0220 | P CUL CL A 1 15 | 60 | FOOT | $66.00 | $70.13 | $68.75 | |
| 114 | 542A1081 | P CUL CL A 2 36 | 64 | FOOT | $147.00 | $127.91 | $125.40 | |
| 115 | 542A1903 | P CUL CL A 3 18 | 121 | FOOT | $74.00 | $78.39 | $76.85 | |
| 116 | 542A1915 | P CUL CL A 3 30 | 162 | FOOT | $110.00 | $96.57 | $94.67 | |
| 117 | 542C0217 | P CUL CL C 1 12 | 314 | FOOT | $57.87 | $59.54 | $58.37 | |
| 118 | 542C1057 | P CUL CL C 2 12 | 63 | FOOT | $57.82 | $103.87 | $101.83 | |
| 119 | 5421C012 | P CUL CL C 1 12 TEMP | 104 | FOOT | $54.85 | $84.17 | $82.51 | |
| 120 | 5421C030 | P CUL CL C 1 30 TEMP | 183 | FOOT | $101.50 | $131.37 | $128.79 | |
| 121 | 5421C048 | P CUL CL C 1 48 TEMP | 75 | FOOT | $200.00 | $241.13 | $236.40 | |
| 122 | 54213657 | PRC FLAR END SEC 12 | 5 | EACH | $920.00 | $1,009.80 | $990.00 | |
| 123 | 54213660 | PRC FLAR END SEC 15 | 4 | EACH | $1,115.00 | $1,251.54 | $1,227.00 | |
| 124 | 54213663 | PRC FLAR END SEC 18 | 6 | EACH | $1,240.00 | $1,492.77 | $1,463.50 | |
| 125 | 54213669 | PRC FLAR END SEC 24 | 2 | EACH | $1,865.00 | $1,674.19 | $1,641.36 | |
| 126 | 54213675 | PRC FLAR END SEC 30 | 1 | EACH | $3,220.00 | $1,982.63 | $1,943.75 | |
| 127 | 54213681 | PRC FLAR END SEC 36 | 2 | EACH | $3,860.00 | $2,959.96 | $2,901.92 | |
| 128 | 54215430 | CIP RC END SEC 30 | 1 | EACH | $33,700.00 | $19,815.00 | $15,000.00 | |
| 129 | 54262712 | METAL FL END SEC 12" | 18 | EACH | $550.00 | $183.27 | $179.67 | |
| 130 | 550A0050 | STORM SEW CL A 1 12 | 1,344 | FOOT | $58.69 | $51.78 | $50.76 | |
| 131 | 550A0090 | STORM SEW CL A 1 18 | 377 | FOOT | $71.97 | $81.09 | $79.50 | |
| 132 | 550A0120 | STORM SEW CL A 1 24 | 242 | FOOT | $95.24 | $86.83 | $85.15 | |
| 133 | 550A0140 | STORM SEW CL A 1 30 | 127 | FOOT | $118.69 | $106.44 | $104.35 | |
| 134 | 550A0380 | STORM SEW CL A 2 18 | 314 | FOOT | $69.25 | $78.39 | $76.85 | |
| 135 | 550A0410 | STORM SEW CL A 2 24 | 38 | FOOT | $104.00 | $86.83 | $85.12 | |
| 136 | 58300100 | PC MORTAR FAIRING CSE | 341 | FOOT | $0.0100 | $13.85 | $0.0100 | |
| 137 | 58600101 | GRANULAR BACKFILL STR | 260 | CU YD | $74.00 | $83.65 | $90.00 | |
| 138 | 58700300 | CONCRETE SEALER | 423 | SQ FT | $1.30 | $3.95 | $2.00 | |
| 139 | 59100100 | GEOCOMPOSITE WALL DR | 124 | SQ YD | $33.00 | $49.80 | $26.00 | |
| 140 | 59300100 | CONTR LOW-STRENG MATL | 1,803 | CU YD | $220.00 | $267.80 | $257.49 | |
| 141 | 60146304 | P UNDR FOR STRUCT 4 | 194 | FOOT | $32.00 | $53.70 | $55.00 | |
| 142 | 60218500 | MAN TA 4 DIA T3F&G | 5 | EACH | $4,044.00 | $5,606.94 | $5,497.00 | |
| 143 | 60219570 | MAN TA 4 DIA T3V F&G | 2 | EACH | $4,044.00 | $5,606.94 | $5,497.00 | |
| 144 | 60221200 | MAN TA 5 DIA T3F&G | 1 | EACH | $5,400.00 | $6,104.70 | $5,985.00 | |
| 145 | 60222270 | MAN TA 5 DIA T3V F&G | 1 | EACH | $5,400.00 | $6,104.70 | $5,985.00 | |
| 146 | 60235700 | INLETS TA T3F&G | 7 | EACH | $2,300.00 | $2,986.56 | $2,928.00 | |
| 147 | 60235705 | INLETS TA T3V F&G | 5 | EACH | $2,300.00 | $2,986.56 | $2,928.00 | |
| 148 | 60236200 | INLETS TA T8G | 2 | EACH | $2,300.00 | $2,695.86 | $2,643.00 | |
| 149 | 60237000 | INLETS TA T15F&L | 1 | EACH | $2,300.00 | $2,924.34 | $2,867.00 | |
| 150 | 60240220 | INLETS TB T3F&G | 8 | EACH | $3,100.00 | $3,432.30 | $3,365.00 | |
| 151 | 60240222 | INLETS TB T3V F&G | 9 | EACH | $3,000.00 | $3,432.30 | $3,365.00 | |
| 152 | 60240301 | INLETS TB T8G | 1 | EACH | $3,400.00 | $3,783.18 | $3,709.00 | |
| 153 | 60240320 | INLETS TB T15F&L | 1 | EACH | $3,400.00 | $3,369.06 | $3,303.00 | |
| 154 | 60240324 | INLETS TB T20F&G | 1 | EACH | $3,400.00 | $3,381.30 | $3,315.00 | |
| 155 | 60263000 | INL RECON NEW T1F CL | 1 | EACH | $2,000.00 | $2,050.20 | $2,010.00 | |
| 156 | 60500060 | REMOV INLETS | 1 | EACH | $850.00 | $939.42 | $921.00 | |
| 157 | 60600095 | CLASS SI CONC OUTLET | 15 | CU YD | $445.00 | $1,320.15 | $700.00 | |
| 158 | 60602800 | CONCRETE GUTTER TY B | 528 | FOOT | $36.40 | $67.80 | $73.00 | |
| 159 | 60605000 | COMB CC&G TY B-6.24 | 6,149 | FOOT | $34.25 | $59.75 | $65.00 | |
| 160 | 63000001 | SPBGR TY A 6FT POSTS | 413 | FOOT | $31.50 | $28.05 | $30.00 | |
| 161 | 63100045 | TRAF BAR TERM T2 | 2 | EACH | $1,785.00 | $1,861.50 | $1,700.00 | |
| 162 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $4,725.00 | $3,493.50 | $4,500.00 | |
| 163 | 63100087 | TRAF BAR TERM T6A | 4 | EACH | $5,040.00 | $4,233.00 | $4,800.00 | |
| 164 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,570.00 | $2,932.50 | $3,400.00 | |
| 165 | 63100169 | TR BAR TRM T1 SPL FLR | 2 | EACH | $3,570.00 | $3,391.50 | $3,400.00 | |
| 166 | 63200310 | GUARDRAIL REMOV | 109 | FOOT | $4.75 | $15.05 | $7.50 | |
| 167 | 67000400 | ENGR FIELD OFFICE A | 28 | CAL MO | $2,360.00 | $3,260.00 | $650.00 | |
| 168 | 67100100 | MOBILIZATION | 1 | L SUM | $1,185,000.00 | $1,100,000.00 | $1,385,366.16 | |
| 169 | 70107025 | CHANGEABLE MESSAGE SN | 20 | CAL DA | $57.75 | $122.40 | $120.00 | |
| 170 | 70300100 | SHORT TERM PAVT MKING | 1,179 | FOOT | $2.62 | $2.55 | $2.50 | |
| 171 | 70300150 | SHRT TRM PAVT MK REM | 394 | SQ FT | $2.96 | $1.02 | $3.71 | |
| 172 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 20,052 | FOOT | $1.00 | $0.2600 | $0.2700 | |
| 173 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 13 | FOOT | $6.00 | $1.53 | $5.00 | |
| 174 | 72000100 | SIGN PANEL T1 | 55 | SQ FT | $63.40 | $31.11 | $30.50 | |
| 175 | 72501000 | TERMINAL MARKER - DA | 6 | EACH | $52.50 | $42.84 | $50.00 | |
| 176 | 73000100 | WOOD SIN SUPPORT | 119 | FOOT | $32.00 | $29.84 | $28.25 | |
| 177 | 78001110 | PAINT PVT MK LINE 4 | 20,080 | FOOT | $0.2300 | $0.3400 | $0.2200 | |
| 178 | 78001180 | PAINT PVT MK LINE 24 | 13 | FOOT | $5.25 | $15.99 | $5.00 | |
| 179 | 78200005 | GRDRAIL REF TYPE A | 32 | EACH | $10.50 | $8.16 | $11.00 | |
| 180 | 78300202 | PVT MKG REM WTR BLAST | 852 | SQ FT | $5.83 | $11.15 | $5.55 |