2024-01 TREE REMOVAL
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Clean Cut Tree Service, Inc. Low bidder | $210,216 | ||
| 2 | JIMAX Landscape LLC | $384,995 | +83.1% | |
| 3 | Mosley Construction 1, LLC | $447,417 | +112.8% | |
| 4 | CSD Environmental Services, Inc. | $528,028 | +151.2% | |
| 5 | Endrizzi Contracting, Inc | $699,550 | +232.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Clean Cut Tree … | #2 JIMAX Landscape… | #3 Mosley Construc… | #4 CSD Environment… | #5 Endrizzi Contra… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X2010106 | TREE REM < 6 UNIT DIA | 59 | UNIT | $25.00 | $101.70 | $10.00 | $10.00 | $95.00 | |
| 2 | 20100110 | TREE REMOV 6-15 | 912 | UNIT | $45.00 | $101.70 | $75.00 | $92.00 | $125.00 | |
| 3 | 20100210 | TREE REMOV OVER 15 | 2,139 | UNIT | $59.00 | $121.90 | $75.00 | $150.00 | $255.00 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $25,000.00 | $12,500.00 | $25,000.00 | $18,684.00 | $20,000.00 | |
| 5 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $5,500.00 | $3,000.00 | $193,000.00 | $80,000.00 | $4,500.00 | |
| 6 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $5,500.00 | $7,500.00 | $1.00 | $12,000.00 | $5,000.00 | |
| 7 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $5,500.00 | $2,500.00 | $1.00 | $12,000.00 | $5,000.00 |