23-00178-00-RS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Builders Paving, LLC Low bidder | $986,318 | ||
| 2 | Peter Baker & Son Co. | $1,031,478 | +4.6% | |
| 3 | R. W. Dunteman Company | $1,064,600 | +7.9% | |
| 4 | Plote Construction, Inc. | $1,089,498 | +10.5% | |
| 5 | J. A. Johnson Paving Company | $1,130,000 | +14.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Builders Paving… | #2 Peter Baker & S… | #3 R. W. Dunteman … | #4 Plote Construct… | #5 J. A. Johnson P… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $2,250.00 | $5,995.00 | $13,300.00 | $13,300.00 | $5,995.00 | |
| 2 | X6026050 | SANITARY MANHOLE ADJ | 4 | EACH | $1,850.00 | $1,135.00 | $1,850.00 | $1,850.00 | $1,850.00 | |
| 3 | X6030310 | FR & LIDS ADJUST SPL | 22 | EACH | $1,150.00 | $1,125.00 | $1,150.00 | $1,150.00 | $1,150.00 | |
| 4 | X7810301 | RCSD REFL PVT MKR HMA | 210 | EACH | $31.50 | $31.50 | $31.50 | $21.25 | $31.50 | |
| 5 | X8860105 | DETECTOR LOOP REPLACE | 200 | FOOT | $16.14 | $21.66 | $21.66 | $16.14 | $16.14 | |
| 6 | Z0004510 | HMA DRIVEWAY PAVT 3 | 180 | SQ YD | $35.00 | $50.00 | $34.50 | $49.00 | $70.00 | |
| 7 | Z0017400 | DRAIN UTIL STR ADJ | 33 | EACH | $450.00 | $350.00 | $450.00 | $450.00 | $450.00 | |
| 8 | Z0017700 | DRAIN UTIL STR RECON | 5 | EACH | $1,850.00 | $3,500.00 | $1,850.00 | $1,850.00 | $1,850.00 | |
| 9 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 | |
| 10 | 20101000 | TEMPORARY FENCE | 200 | FOOT | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | |
| 11 | 20101200 | TREE ROOT PRUNING | 1 | EACH | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 | |
| 12 | 20101400 | NITROGEN FERT NUTR | 7 | POUND | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | |
| 13 | 20101500 | PHOSPHORUS FERT NUTR | 7 | POUND | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | |
| 14 | 20101600 | POTASSIUM FERT NUTR | 7 | POUND | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | |
| 15 | 20200100 | EARTH EXCAVATION | 10 | CU YD | $75.00 | $110.00 | $97.30 | $188.00 | $110.00 | |
| 16 | 21101615 | TOPSOIL F & P 4 | 151 | SQ YD | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | |
| 17 | 25000110 | SEEDING CL 1A | 0.031 | ACRE | $100,099.00 | $100,099.00 | $96,870.00 | $100,099.00 | $100,099.00 | |
| 18 | 25200200 | SUPPLE WATERING | 2 | UNIT | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | |
| 19 | 28000510 | INLET FILTERS | 48 | EACH | $190.00 | $300.00 | $190.00 | $190.00 | $190.00 | |
| 20 | 35101600 | AGG BASE CSE B 4 | 20 | SQ YD | $100.00 | $45.00 | $49.25 | $12.00 | $45.00 | |
| 21 | 35101800 | AGG BASE CSE B 6 | 10 | SQ YD | $100.00 | $45.00 | $91.90 | $22.00 | $45.00 | |
| 22 | 40600290 | BIT MATLS TACK CT | 12,500 | POUND | $0.0100 | $0.0100 | $0.7000 | $0.0100 | $0.0100 | |
| 23 | 40600370 | LONG JOINT SEALANT | 10,220 | FOOT | $0.1000 | $3.55 | $3.00 | $2.95 | $2.72 | |
| 24 | 40600400 | MIX CR JTS FLANGEWYS | 20 | TON | $625.00 | $710.00 | $413.50 | $1,340.00 | $375.00 | |
| 25 | 40600982 | HMA SURF REM BUTT JT | 179 | SQ YD | $23.00 | $1.00 | $25.75 | $26.00 | $1.00 | |
| 26 | 40600990 | TEMPORARY RAMP | 54 | SQ YD | $70.00 | $20.00 | $21.05 | $45.00 | $2.00 | |
| 27 | 40603085 | HMA BC IL-19.0 N70 | 2,643 | TON | $73.50 | $78.00 | $96.30 | $80.00 | $89.00 | |
| 28 | 40604172 | P HMA SC IL-9.5 E N70 | 1,866 | TON | $104.00 | $102.00 | $111.65 | $124.00 | $122.00 | |
| 29 | 42001300 | PROTECTIVE COAT | 819 | SQ YD | $1.00 | $0.1000 | $1.05 | $4.50 | $0.1000 | |
| 30 | 42300400 | PCC DRIVEWAY PAVT 8 | 111 | SQ YD | $108.00 | $140.00 | $85.35 | $125.00 | $155.00 | |
| 31 | 42400200 | PC CONC SIDEWALK 5 | 3,250 | SQ FT | $15.00 | $12.50 | $7.85 | $15.00 | $13.00 | |
| 32 | 42400410 | PC CONC SIDEWALK 8 | 380 | SQ FT | $20.00 | $15.00 | $10.00 | $16.00 | $15.00 | |
| 33 | 42400800 | DETECTABLE WARNINGS | 200 | SQ FT | $40.00 | $45.00 | $34.65 | $38.00 | $45.00 | |
| 34 | 44000165 | HMA SURF REM 4 | 18,500 | SQ YD | $5.00 | $4.88 | $5.65 | $6.00 | $5.25 | |
| 35 | 44000200 | DRIVE PAVEMENT REM | 334 | SQ YD | $27.00 | $15.00 | $20.00 | $30.00 | $1.00 | |
| 36 | 44000500 | COMB CURB GUTTER REM | 1,095 | FOOT | $15.00 | $10.00 | $13.50 | $7.00 | $10.00 | |
| 37 | 44000600 | SIDEWALK REM | 3,250 | SQ FT | $5.00 | $4.50 | $2.50 | $3.00 | $4.50 | |
| 38 | 44200934 | CL B PATCH T2 8 | 179 | SQ YD | $220.00 | $270.00 | $167.50 | $165.00 | $270.00 | |
| 39 | 44200942 | CL B PATCH T3 8 | 179 | SQ YD | $220.00 | $270.00 | $167.50 | $165.00 | $270.00 | |
| 40 | 44201297 | DOWEL BARS 1 | 800 | EACH | $25.00 | $15.00 | $21.30 | $14.00 | $15.00 | |
| 41 | 60200405 | CB TA 4 DIA T4F&G | 1 | EACH | $8,950.00 | $4,000.00 | $8,950.00 | $8,950.00 | $8,950.00 | |
| 42 | 60235800 | INLETS TA T4F&G | 5 | EACH | $3,150.00 | $4,000.00 | $3,150.00 | $3,150.00 | $3,150.00 | |
| 43 | 60404400 | FR & GRATES T4 | 2 | EACH | $650.00 | $1,500.00 | $650.00 | $650.00 | $650.00 | |
| 44 | 60406100 | FR & LIDS T1 CL | 2 | EACH | $450.00 | $1,500.00 | $450.00 | $450.00 | $450.00 | |
| 45 | 60500050 | REMOV CATCH BAS | 1 | EACH | $350.00 | $1,500.00 | $350.00 | $350.00 | $350.00 | |
| 46 | 60500060 | REMOV INLETS | 5 | EACH | $215.00 | $1,500.00 | $215.00 | $215.00 | $215.00 | |
| 47 | 60604400 | COMB CC&G TB6.18 | 1,095 | FOOT | $40.00 | $50.00 | $37.60 | $50.00 | $50.00 | |
| 48 | 66900200 | NON SPL WASTE DISPOSL | 10 | CU YD | $185.00 | $120.00 | $103.00 | $155.00 | $170.00 | |
| 49 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,725.00 | $1,550.00 | $1,900.00 | $1,550.00 | $1,550.00 | |
| 50 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,300.00 | $3,000.00 | $2,300.00 | $3,000.00 | $3,000.00 | |
| 51 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $500.00 | $1,900.00 | $500.00 | $500.00 | |
| 52 | 66901006 | REG SUB MON | 2 | CAL DA | $800.00 | $950.00 | $940.00 | $950.00 | $950.00 | |
| 53 | 67100100 | MOBILIZATION | 1 | L SUM | $47,000.00 | $48,510.66 | $58,500.44 | $65,000.00 | $60,842.25 | |
| 54 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $30,000.00 | $12,000.00 | $26,000.00 | $16,300.00 | $60,000.00 | |
| 55 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $8,800.00 | $1.00 | $1.00 | |
| 56 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 57 | 70300100 | SHORT TERM PAVT MKING | 2,733 | FOOT | $1.50 | $1.00 | $1.08 | $1.65 | $0.0100 | |
| 58 | 70300150 | SHRT TRM PAVT MK REM | 305 | SQ FT | $0.0100 | $1.00 | $2.08 | $5.75 | $0.0100 | |
| 59 | 78000100 | THPL PVT MK LTR & SYM | 406 | SQ FT | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | |
| 60 | 78000200 | THPL PVT MK LINE 4 | 5,200 | FOOT | $0.8000 | $0.8000 | $0.8000 | $0.7500 | $0.8000 | |
| 61 | 78000400 | THPL PVT MK LINE 6 | 2,510 | FOOT | $1.00 | $1.00 | $1.00 | $1.30 | $1.00 | |
| 62 | 78000600 | THPL PVT MK LINE 12 | 90 | FOOT | $2.00 | $2.00 | $2.00 | $2.50 | $2.00 | |
| 63 | 78000650 | THPL PVT MK LINE 24 | 130 | FOOT | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |