(147)RS-8,DR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K. E. Vas Company Low bidder | $5,770,272 | ||
| 2 | Illinois Valley Paving, a div of UCM, Inc. | $6,510,133 | +12.8% | |
| 3 | P. H. Broughton & Sons, Inc. | $7,398,040 | +28.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K. E. Vas Compa… | #2 Illinois Valley… | #3 P. H. Broughton… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4404400 | PAVT REMOVAL SPL | 4,648 | SQ YD | $25.00 | $40.56 | $27.07 | |
| 2 | X5015225 | PIPE CULVERT REM SPL | 596 | FOOT | $28.00 | $42.83 | $54.69 | |
| 3 | X5220005 | PERM ST SHT PILE SPL | 3,760 | SQ FT | $52.00 | $41.52 | $64.97 | |
| 4 | X6062700 | CONC GUTTER TA SPL | 10,247 | FOOT | $41.00 | $66.51 | $58.48 | |
| 5 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $5,000.00 | $1,555.50 | $2,707.24 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $100,000.00 | $39,617.33 | $52,574.57 | |
| 7 | Z0034105 | MATL TRANSFER DEVICE | 5,980 | TON | $5.00 | $3.03 | $4.63 | |
| 8 | Z0076600 | TRAINEES | 2,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 2,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 10 | 20100110 | TREE REMOV 6-15 | 294 | UNIT | $120.00 | $91.80 | $129.95 | |
| 11 | 20100210 | TREE REMOV OVER 15 | 68 | UNIT | $190.00 | $137.70 | $205.75 | |
| 12 | 20100500 | TREE REMOV ACRES | 1.25 | ACRE | $38,500.00 | $35,700.00 | $41,691.47 | |
| 13 | 20200100 | EARTH EXCAVATION | 5,260 | CU YD | $28.00 | $65.15 | $69.67 | |
| 14 | 20400800 | FURNISHED EXCAVATION | 1,345 | CU YD | $28.00 | $73.14 | $242.48 | |
| 15 | 20700110 | POROUS GRAN EMBANK | 148 | TON | $88.00 | $73.26 | $183.02 | |
| 16 | 20800150 | TRENCH BACKFILL | 18 | CU YD | $80.00 | $97.11 | $81.22 | |
| 17 | 21400100 | GRADING & SHAP DITCH | 2,349 | FOOT | $11.00 | $8.35 | $14.76 | |
| 18 | 25000200 | SEEDING CL 2 | 5.75 | ACRE | $2,500.00 | $1,836.00 | $4,472.36 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 498 | POUND | $5.00 | $1.02 | $3.36 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 498 | POUND | $5.00 | $1.02 | $3.36 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 498 | POUND | $5.00 | $1.02 | $3.36 | |
| 22 | 25000700 | AGR GROUND LIMESTONE | 11.1 | TON | $200.00 | $51.00 | $108.29 | |
| 23 | 25100115 | MULCH METHOD 2 | 5 | ACRE | $2,500.00 | $1,530.00 | $2,030.43 | |
| 24 | 25100635 | HD EROS CONTR BLANKET | 3,486 | SQ YD | $5.00 | $2.04 | $2.17 | |
| 25 | 28000250 | TEMP EROS CONTR SEED | 554 | POUND | $10.00 | $7.81 | $4.33 | |
| 26 | 28000305 | TEMP DITCH CHECKS | 836 | FOOT | $10.00 | $54.82 | $16.24 | |
| 27 | 28000400 | PERIMETER EROS BAR | 450 | FOOT | $4.00 | $12.57 | $2.60 | |
| 28 | 28000500 | INLET & PIPE PROTECT | 27 | EACH | $200.00 | $834.72 | $194.92 | |
| 29 | 28100107 | STONE RIPRAP CL A4 | 384 | SQ YD | $171.00 | $117.71 | $97.81 | |
| 30 | 28200200 | FILTER FABRIC | 384 | SQ YD | $5.50 | $3.38 | $10.54 | |
| 31 | 31100300 | SUB GRAN MAT A 4 | 7,970 | SQ YD | $13.25 | $23.66 | $16.24 | |
| 32 | 35101400 | AGG BASE CSE B | 235 | TON | $40.00 | $152.59 | $48.21 | |
| 33 | 35501310 | HMA BASE CSE 6 1/2 | 826 | SQ YD | $63.00 | $118.38 | $69.34 | |
| 34 | 35650400 | BASE CSE WIDENING 9 | 3,416 | SQ YD | $85.00 | $100.39 | $101.00 | |
| 35 | 40600290 | BIT MATLS TACK CT | 48,729 | POUND | $1.70 | $0.8200 | $1.05 | |
| 36 | 40600370 | LONG JOINT SEALANT | 27,821 | FOOT | $3.00 | $2.87 | $2.83 | |
| 37 | 40600982 | HMA SURF REM BUTT JT | 411 | SQ YD | $25.00 | $16.69 | $37.65 | |
| 38 | 40600990 | TEMPORARY RAMP | 213 | SQ YD | $20.00 | $16.58 | $16.52 | |
| 39 | 40603080 | HMA BC IL-19.0 N50 | 7,785 | TON | $123.00 | $118.74 | $139.34 | |
| 40 | 40604050 | HMA SC IL-9.5 C N50 | 5,980 | TON | $138.00 | $128.66 | $150.32 | |
| 41 | 40800029 | BIT MATLS TACK CT | 745 | POUND | $2.00 | $1.37 | $5.00 | |
| 42 | 40800050 | INCIDENTAL HMA SURF | 330 | TON | $380.00 | $291.06 | $337.49 | |
| 43 | 44000100 | PAVEMENT REM | 873 | SQ YD | $18.00 | $57.78 | $26.42 | |
| 44 | 44000155 | HMA SURF REM 1 1/2 | 71,983 | SQ YD | $3.00 | $2.42 | $3.99 | |
| 45 | 44000164 | HMA SURF REM 3 3/4 | 3,818 | SQ YD | $3.50 | $8.76 | $6.16 | |
| 46 | 44000200 | DRIVE PAVEMENT REM | 457 | SQ YD | $25.00 | $41.20 | $12.45 | |
| 47 | 44200094 | PAVT PATCH T2 8 | 23 | SQ YD | $380.00 | $398.86 | $514.38 | |
| 48 | 48102100 | AGG WEDGE SHLD TYPE B | 2,065 | TON | $38.00 | $42.61 | $52.65 | |
| 49 | 48203100 | HMA SHOULDERS | 758 | TON | $158.00 | $143.75 | $141.25 | |
| 50 | 50102400 | CONC REM | 33 | CU YD | $288.00 | $313.76 | $568.52 | |
| 51 | 50800105 | REINFORCEMENT BARS | 30 | POUND | $12.00 | $56.47 | $8.12 | |
| 52 | 54002020 | EXPAN BOLTS 3/4 | 4 | EACH | $500.00 | $197.89 | $69.31 | |
| 53 | 542A0220 | P CUL CL A 1 15 | 120 | FOOT | $85.00 | $93.85 | $113.70 | |
| 54 | 542A0229 | P CUL CL A 1 24 | 92 | FOOT | $150.00 | $183.42 | $140.78 | |
| 55 | 542A1075 | P CUL CL A 2 30 | 25 | FOOT | $235.00 | $257.73 | $216.58 | |
| 56 | 542D0220 | P CUL CL D 1 15 | 864 | FOOT | $43.00 | $49.95 | $92.59 | |
| 57 | 54213660 | PRC FLAR END SEC 15 | 1 | EACH | $1,300.00 | $1,683.16 | $2,111.65 | |
| 58 | 54213669 | PRC FLAR END SEC 24 | 2 | EACH | $2,500.00 | $2,114.33 | $2,707.24 | |
| 59 | 54213675 | PRC FLAR END SEC 30 | 1 | EACH | $2,900.00 | $2,398.68 | $2,977.96 | |
| 60 | 54248510 | CONCRETE COLLAR | 0.4 | CU YD | $9,500.00 | $11,802.08 | $4,196.23 | |
| 61 | 54262715 | METAL FL END SEC 15" | 42 | EACH | $350.00 | $817.35 | $460.23 | |
| 62 | 60100060 | CONC HDWL FOR P DRAIN | 12 | EACH | $900.00 | $542.09 | $866.32 | |
| 63 | 60108106 | PIPE UNDERDR T 1 6 | 6,908 | FOOT | $19.00 | $22.44 | $29.24 | |
| 64 | 60108200 | PIPE UNDERDRAIN 6 SP | 351 | FOOT | $32.00 | $30.05 | $46.02 | |
| 65 | 60240366 | INLET TB M INL 604106 | 1 | EACH | $6,800.00 | $6,550.22 | $7,471.98 | |
| 66 | 60600095 | CLASS SI CONC OUTLET | 155 | CU YD | $675.00 | $1,771.38 | $2,111.65 | |
| 67 | 63000001 | SPBGR TY A 6FT POSTS | 1,881 | FOOT | $28.40 | $28.97 | $30.75 | |
| 68 | 63000003 | SPBGR TY A 9FT POSTS | 925 | FOOT | $39.35 | $40.14 | $42.61 | |
| 69 | 63100085 | TRAF BAR TERM T6 | 8 | EACH | $4,160.00 | $4,243.20 | $4,504.85 | |
| 70 | 63100167 | TR BAR TRM T1 SPL TAN | 16 | EACH | $3,755.00 | $3,830.10 | $4,066.27 | |
| 71 | 63200310 | GUARDRAIL REMOV | 3,975 | FOOT | $8.80 | $8.98 | $9.53 | |
| 72 | 66700205 | PERM SURV MKRS T1 | 7 | EACH | $800.00 | $679.62 | $1,570.20 | |
| 73 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $4,000.00 | $3,496.07 | $4,322.12 | |
| 74 | 67100100 | MOBILIZATION | 1 | L SUM | $180,000.00 | $335,220.33 | $299,331.42 | |
| 75 | 70100100 | TRAF CONT-PROT 701316 | 6 | EACH | $15,000.00 | $20,935.50 | $12,390.13 | |
| 76 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $25,000.00 | $4,655.12 | $227,408.04 | |
| 77 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $150,000.00 | $13,387.50 | $14,510.80 | |
| 78 | 70106500 | TEMP BR TRAF SIGNALS | 6 | EACH | $32,000.00 | $29,415.85 | $36,845.52 | |
| 79 | 70107025 | CHANGEABLE MESSAGE SN | 440 | CAL DA | $100.00 | $41.57 | $64.97 | |
| 80 | 70300100 | SHORT TERM PAVT MKING | 8,540 | FOOT | $1.00 | $1.28 | $1.08 | |
| 81 | 70300150 | SHRT TRM PAVT MK REM | 949 | SQ FT | $5.00 | $4.81 | $6.03 | |
| 82 | 72501000 | TERMINAL MARKER - DA | 16 | EACH | $50.00 | $51.00 | $54.15 | |
| 83 | 78001120 | PAINT PVT MK LINE 5 | 88,451 | FOOT | $0.1500 | $0.1500 | $0.1600 | |
| 84 | 78001180 | PAINT PVT MK LINE 24 | 55 | FOOT | $18.00 | $18.36 | $19.49 | |
| 85 | 78100100 | RAISED REFL PAVT MKR | 336 | EACH | $42.00 | $42.08 | $44.67 | |
| 86 | 78200005 | GRDRAIL REF TYPE A | 77 | EACH | $10.00 | $10.20 | $10.83 | |
| 87 | 78300200 | RAISED REF PVT MK REM | 336 | EACH | $15.00 | $14.80 | $14.47 | |
| 88 | 78300201 | PVT MKG REM GRINDING | 5,701 | SQ FT | $1.25 | $1.28 | $1.35 |