(13-1, 27)RS-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $339,339 | ||
| 2 | E. T. Simonds Construction Company | $414,024 | +22.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|
| 1 | 40600290 | BIT MATLS TACK CT | 9,014 | POUND | $0.0100 | $0.0100 | |
| 2 | 40600370 | LONG JOINT SEALANT | 4,479 | FOOT | $3.90 | $4.31 | |
| 3 | 40600982 | HMA SURF REM BUTT JT | 958 | SQ YD | $2.50 | $8.59 | |
| 4 | 40600990 | TEMPORARY RAMP | 366 | SQ YD | $15.00 | $39.58 | |
| 5 | 40602970 | HMA BC IL-9.5FG N70 | 860 | TON | $100.00 | $110.52 | |
| 6 | 40604052 | HMA SC IL-9.5 C N70 | 932 | TON | $95.00 | $104.68 | |
| 7 | 40800050 | INCIDENTAL HMA SURF | 139 | TON | $215.00 | $180.33 | |
| 8 | 44000155 | HMA SURF REM 1 1/2 | 7,196 | SQ YD | $2.00 | $2.04 | |
| 9 | 44000161 | HMA SURF REM 3 | 3,963 | SQ YD | $3.50 | $3.62 | |
| 10 | 48102100 | AGG WEDGE SHLD TYPE B | 129 | TON | $63.00 | $116.95 | |
| 11 | 48203100 | HMA SHOULDERS | 127 | TON | $78.00 | $196.88 | |
| 12 | 67000400 | ENGR FIELD OFFICE A | 2 | CAL MO | $1,200.00 | $1,500.00 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $14,086.05 | $30,485.32 | |
| 14 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $5,000.00 | $1,430.00 | |
| 15 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $4,000.00 | $13,409.14 | |
| 16 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1,000.00 | $0.0100 | |
| 17 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $75.00 | $41.25 | |
| 18 | 70300100 | SHORT TERM PAVT MKING | 1,968 | FOOT | $2.00 | $0.5500 | |
| 19 | 70300150 | SHRT TRM PAVT MK REM | 219 | SQ FT | $8.00 | $20.21 | |
| 20 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 73 | SQ FT | $0.0100 | $0.0100 | |
| 21 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 13,494 | FOOT | $0.0100 | $0.0100 | |
| 22 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 324 | FOOT | $0.0100 | $0.0100 | |
| 23 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 46 | FOOT | $0.0100 | $0.0100 | |
| 24 | 78001100 | PT PVT MK LTRS & SYMB | 73 | SQ FT | $15.25 | $3.30 | |
| 25 | 78001110 | PAINT PVT MK LINE 4 | 13,494 | FOOT | $0.3500 | $0.7200 | |
| 26 | 78001150 | PAINT PVT MK LINE 12 | 324 | FOOT | $12.00 | $2.04 | |
| 27 | 78001180 | PAINT PVT MK LINE 24 | 46 | FOOT | $22.25 | $3.30 | |
| 28 | 78100100 | RAISED REFL PAVT MKR | 101 | EACH | $70.00 | $73.76 | |
| 29 | 78300200 | RAISED REF PVT MK REM | 32 | EACH | $0.0100 | $20.78 | |
| 30 | 78300201 | PVT MKG REM GRINDING | 4,987 | SQ FT | $0.0100 | $0.0100 | |
| 31 | 88600100 | DET LOOP T1 | 419 | FOOT | $26.00 | $26.40 |