19-00141-00-BR
- Let date
- Friday, November 17, 2023
- Contract
- 99713 · job page
- District
- District 9
- County
- Jackson
- Highway
- Limits
- Replace existing structure with a precast concrete box culvert with pre-cast box culvert end sections, PCC pavement, sidewalk, curb and gutter, on East College Street over Piles Fork Creek in Carbondale.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $553,288 | ||
| 2 | Sierra Bravo Contractors, LLC | $588,712 | +6.4% | |
| 3 | Samron Midwest Contracting, Inc. | $770,770 | +39.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Sierra Bravo Co… | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | X0900064 | MEMBR WTRPR SYS B STR | 229 | SQ YD | $30.02 | $53.00 | $23.50 | |
| 2 | X4240440 | PC CONC SIDEWALK 6 SP | 557 | SQ FT | $15.95 | $21.16 | $13.80 | |
| 3 | X6026050 | SANITARY MANHOLE ADJ | 1 | EACH | $1,637.55 | $1,060.00 | $300.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,420.21 | $7,950.00 | $35,510.28 | |
| 5 | Z0007126 | HANDRAIL REMOVAL | 117 | FOOT | $14.40 | $29.12 | $0.0100 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $11,440.00 | $13,250.00 | $25,000.00 | |
| 7 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $15,372.23 | $14,044.74 | $20,000.00 | |
| 8 | Z0018700 | DRAINAGE STR REMOVED | 1 | EACH | $1,408.71 | $3,274.54 | $200.00 | |
| 9 | Z0054402 | ROCK FILL - REPLACE | 207 | CU YD | $61.84 | $63.60 | $76.00 | |
| 10 | 20200100 | EARTH EXCAVATION | 5 | CU YD | $113.28 | $81.50 | $0.0100 | |
| 11 | 20201200 | REM & DISP UNS MATL | 207 | CU YD | $37.52 | $38.73 | $40.00 | |
| 12 | 20700220 | POROUS GRAN EMBANK | 379 | CU YD | $55.92 | $53.00 | $86.40 | |
| 13 | 20800150 | TRENCH BACKFILL | 7 | CU YD | $54.00 | $53.00 | $56.00 | |
| 14 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $12,100.00 | $13,250.00 | $11,110.00 | |
| 15 | 25000400 | NITROGEN FERT NUTR | 10 | POUND | $1.76 | $3.18 | $3.50 | |
| 16 | 25000500 | PHOSPHORUS FERT NUTR | 10 | POUND | $1.76 | $3.18 | $3.50 | |
| 17 | 25000600 | POTASSIUM FERT NUTR | 10 | POUND | $1.76 | $3.18 | $3.50 | |
| 18 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $8,800.00 | $11,660.00 | $1,480.00 | |
| 19 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $9.86 | $5.30 | $2.30 | |
| 20 | 28000500 | INLET & PIPE PROTECT | 4 | EACH | $301.42 | $212.00 | $185.00 | |
| 21 | 28100107 | STONE RIPRAP CL A4 | 63 | SQ YD | $88.68 | $81.67 | $105.00 | |
| 22 | 28200200 | FILTER FABRIC | 63 | SQ YD | $9.93 | $3.18 | $10.30 | |
| 23 | 31100100 | SUB GRAN MAT A | 96 | TON | $36.45 | $41.28 | $41.70 | |
| 24 | 42000401 | PCC PVT 9 JOINTED | 364 | SQ YD | $111.95 | $92.76 | $90.90 | |
| 25 | 42400100 | PC CONC SIDEWALK 4 | 682 | SQ FT | $11.76 | $11.43 | $10.95 | |
| 26 | 42400800 | DETECTABLE WARNINGS | 40 | SQ FT | $33.07 | $42.40 | $26.15 | |
| 27 | 44000100 | PAVEMENT REM | 364 | SQ YD | $21.21 | $17.22 | $14.60 | |
| 28 | 44000200 | DRIVE PAVEMENT REM | 13 | SQ YD | $87.80 | $15.67 | $2.80 | |
| 29 | 44000500 | COMB CURB GUTTER REM | 208 | FOOT | $14.36 | $9.46 | $3.80 | |
| 30 | 44000600 | SIDEWALK REM | 1,104 | SQ FT | $3.34 | $1.78 | $3.65 | |
| 31 | 50100100 | REM EXIST STRUCT | 1 | EACH | $15,685.65 | $11,807.12 | $65,000.00 | |
| 32 | 50901720 | BICYCLE RAILING | 99 | FOOT | $286.00 | $288.06 | $246.50 | |
| 33 | 51500100 | NAME PLATES | 1 | EACH | $495.00 | $795.00 | $417.00 | |
| 34 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $36,770.94 | $61,582.55 | $55,000.00 | |
| 35 | 54011009 | PCBC 10X9 | 162 | FOOT | $1,067.48 | $957.05 | $1,675.00 | |
| 36 | 54248510 | CONCRETE COLLAR | 0.5 | CU YD | $2,151.78 | $2,650.00 | $350.00 | |
| 37 | 550A0070 | STORM SEW CL A 1 15 | 3 | FOOT | $609.15 | $266.03 | $65.20 | |
| 38 | 550A0120 | STORM SEW CL A 1 24 | 24 | FOOT | $250.12 | $137.57 | $164.30 | |
| 39 | 55101200 | STORM SEWER REM 24 | 34 | FOOT | $54.29 | $23.63 | $54.20 | |
| 40 | 60219300 | MAN TA 4 DIA T11F&G | 1 | EACH | $6,785.94 | $11,092.04 | $3,000.00 | |
| 41 | 60236800 | INLETS TA T11F&G | 1 | EACH | $4,703.65 | $8,442.04 | $3,000.00 | |
| 42 | 60260100 | INLETS ADJUST | 2 | EACH | $1,715.10 | $795.00 | $675.00 | |
| 43 | 60603800 | COMB CC&G TB6.12 | 208 | FOOT | $69.83 | $56.46 | $40.70 | |
| 44 | 67100100 | MOBILIZATION | 1 | L SUM | $34,697.85 | $35,279.84 | $46,000.00 | |
| 45 | 70107025 | CHANGEABLE MESSAGE SN | 140 | CAL DA | $55.45 | $84.80 | $80.00 | |
| 46 | 78001110 | PAINT PVT MK LINE 4 | 416 | FOOT | $6.05 | $5.83 | $2.50 | |
| 47 | 78001150 | PAINT PVT MK LINE 12 | 64 | FOOT | $21.89 | $21.09 | $15.80 |