FAP 0348 22 BJ
- Let date
- Friday, November 17, 2023
- Contract
- 62T18 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- The scope of work consists of overlay of SN 016-2598 bridge deck overlay, parapet and railing repairs, deck scarification, pavement markings, and traffic control and protection. The project is located over UPRR in the Village of Northbrook in Cook County. Gross Length= Net Length =2658 FT (0.50 Mile).
- Classification
- Overlay of SN 016-2598 bridge deck overlay, parapet and railing repairs, deck scarification, pavement markings
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lorig Construction Company Low bidder | $1,108,628 | ||
| 2 | Martam Construction Incorporated | $1,128,917 | +1.8% | |
| 3 | Areatha Construction Co., Inc. | $1,283,172 | +15.7% | |
| 4 | Herlihy Mid-Continent Company | $1,348,000 | +21.6% | |
| 5 | Alliance Contractors, Inc. | $1,412,357 | +27.4% | |
| 6 | Rausch Infrastructure, LLC | $1,868,605 | +68.6% | |
| 7 | ERA-Valdivia Contractors, Inc. | $2,048,688 | +84.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lorig Construct… | #2 Martam Construc… | #3 Areatha Constru… | #4 Herlihy Mid-Con… | #5 Alliance Contra… | #6 Rausch Infrastr… | #7 ERA-Valdivia Co… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | K1004595 | PRUN SAFETY/EQUIP CLR | 1 | L SUM | $1,000.00 | $9,000.00 | $8,500.00 | $5,200.00 | $5,200.00 | $9,000.00 | $11,000.00 | |
| 2 | X0300062 | GRAFFITI REMOVAL | 10,500 | SQ YD | $11.25 | $1.00 | $0.0100 | $11.25 | $11.25 | $29.00 | $67.00 | |
| 3 | X0326766 | CLEAN RESEAL RLF JNT | 102 | FOOT | $85.00 | $60.00 | $47.55 | $65.00 | $25.00 | $75.00 | $65.00 | |
| 4 | X4201400 | BR APPROACH PAVT SPL | 78 | SQ YD | $350.00 | $385.00 | $459.90 | $600.00 | $295.00 | $686.00 | $125.00 | |
| 5 | X4400503 | CC&G RMVL REPL > 10FT | 379 | FOOT | $76.00 | $63.00 | $123.80 | $70.00 | $80.00 | $120.00 | $75.00 | |
| 6 | X5060700 | CLEAN/PAINT BEARINGS | 56 | EACH | $850.00 | $1,000.00 | $848.25 | $848.21 | $850.00 | $3,600.00 | $1,500.00 | |
| 7 | X6330902 | REATT GRDRL TO STRUC | 1 | EACH | $1,000.00 | $500.00 | $1,000.00 | $5,000.00 | $1,000.00 | $1,100.00 | $1,500.00 | |
| 8 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $1,400.00 | $3,200.00 | $2,500.00 | $4,430.00 | $500.00 | $5,000.00 | $2,500.00 | |
| 9 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $115,000.00 | $178,000.00 | $27,200.00 | $26,000.00 | $53,295.00 | $48,000.00 | $28,500.00 | |
| 10 | X7010410 | SPEED DISPLAY TRAILER | 4 | CAL MO | $450.00 | $660.00 | $600.00 | $450.00 | $450.00 | $643.00 | $650.00 | |
| 11 | X7830050 | RRPM REFLECTOR REMOVL | 358 | EACH | $4.00 | $7.00 | $10.00 | $14.00 | $8.00 | $18.00 | $12.00 | |
| 12 | X7830052 | RRPM REFLECTOR REPLAC | 358 | EACH | $14.00 | $20.00 | $15.00 | $14.00 | $14.00 | $16.00 | $15.00 | |
| 13 | Z0006014 | BR DK LTX C OLY 2 1/2 | 1,301 | SQ YD | $115.00 | $105.00 | $179.20 | $185.00 | $199.00 | $126.00 | $110.49 | |
| 14 | Z0012130 | BR DECK SCAR 3/4 | 1,301 | SQ YD | $60.00 | $44.00 | $100.60 | $68.00 | $92.00 | $78.00 | $85.00 | |
| 15 | Z0012754 | STR REP CON DP = < 5 | 122 | SQ FT | $225.00 | $170.00 | $186.85 | $250.00 | $150.00 | $187.00 | $300.00 | |
| 16 | Z0012755 | STR REP CON DP OVER 5 | 21 | SQ FT | $400.00 | $195.00 | $266.15 | $275.00 | $175.00 | $204.00 | $325.00 | |
| 17 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,000.00 | $8,000.00 | $2,500.00 | $15,000.00 | $2,500.00 | $10,000.00 | $17,500.00 | |
| 18 | Z0016001 | DECK SLAB REP (FD-T1) | 2 | SQ YD | $4,000.00 | $4,500.00 | $3,731.05 | $2,440.00 | $4,995.00 | $8,900.00 | $2,900.00 | |
| 19 | Z0030850 | TEMP INFO SIGNING | 64 | SQ FT | $14.00 | $30.00 | $20.00 | $14.00 | $14.00 | $23.00 | $30.00 | |
| 20 | Z0038114 | PCC SUR REM 1/4 | 258 | SQ YD | $15.00 | $16.00 | $13.85 | $7.61 | $13.85 | $3.50 | $25.00 | |
| 21 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $8,000.00 | $8,000.00 | $14,864.75 | $15,000.00 | $5,000.00 | $23,000.00 | $7,500.00 | |
| 22 | Z0064800 | SELECTIVE CLEARING | 2 | UNIT | $800.00 | $1,000.00 | $650.00 | $800.00 | $800.00 | $760.00 | $1,150.00 | |
| 23 | Z0073510 | TEMP TR SIGNAL TIMING | 1 | EACH | $3,500.00 | $4,000.00 | $1,500.00 | $3,500.00 | $3,500.00 | $4,000.00 | $4,000.00 | |
| 24 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 25 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 26 | 21101615 | TOPSOIL F & P 4 | 39 | SQ YD | $1.00 | $40.00 | $35.00 | $35.00 | $1.00 | $14.00 | $125.00 | |
| 27 | 25200110 | SODDING SALT TOLERANT | 39 | SQ YD | $175.00 | $99.00 | $90.00 | $90.00 | $175.00 | $29.00 | $150.00 | |
| 28 | 40600982 | HMA SURF REM BUTT JT | 344 | SQ YD | $26.00 | $25.00 | $24.85 | $26.00 | $24.85 | $30.00 | $35.00 | |
| 29 | 40604062 | HMA SC IL-9.5 D N70 | 63 | TON | $315.00 | $260.00 | $245.00 | $630.00 | $245.00 | $730.00 | $495.00 | |
| 30 | 40800029 | BIT MATLS TACK CT | 302 | POUND | $0.0100 | $0.1000 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 31 | 42400200 | PC CONC SIDEWALK 5 | 434 | SQ FT | $12.00 | $12.00 | $38.60 | $15.00 | $12.00 | $17.00 | $33.59 | |
| 32 | 44000100 | PAVEMENT REM | 78 | SQ YD | $70.00 | $36.00 | $62.95 | $75.00 | $160.00 | $256.00 | $55.00 | |
| 33 | 44000173 | HMA SURF REM 6 | 69 | SQ YD | $17.00 | $65.00 | $22.00 | $77.00 | $75.00 | $90.00 | $90.00 | |
| 34 | 44000500 | COMB CURB GUTTER REM | 17 | FOOT | $32.00 | $36.00 | $38.45 | $9.00 | $45.00 | $110.00 | $75.00 | |
| 35 | 44000600 | SIDEWALK REM | 434 | SQ FT | $5.00 | $3.00 | $11.45 | $2.85 | $8.25 | $12.00 | $12.17 | |
| 36 | 44003100 | MEDIAN REMOVAL | 1,290 | SQ FT | $5.00 | $5.00 | $1.00 | $3.55 | $8.25 | $25.00 | $55.00 | |
| 37 | 44004250 | PAVED SHLD REMOVAL | 6 | SQ YD | $50.00 | $36.00 | $34.30 | $34.00 | $60.00 | $430.00 | $450.00 | |
| 38 | 44200612 | CL A PATCH T3 13 | 6 | SQ YD | $439.11 | $765.00 | $1.00 | $275.00 | $1,685.00 | $1,516.00 | $550.00 | |
| 39 | 44201301 | CL C PATCH T1 6 | 7 | SQ YD | $400.00 | $455.00 | $1.00 | $475.00 | $535.00 | $1,299.00 | $450.00 | |
| 40 | 44201385 | CL C PATCH T1 13 | 1 | SQ YD | $1,000.00 | $765.00 | $1.00 | $395.00 | $1,150.00 | $5,397.00 | $1,500.00 | |
| 41 | 44213000 | PATCH REINFORCEMENT | 7 | SQ YD | $135.00 | $265.00 | $1.00 | $150.00 | $25.00 | $746.00 | $75.00 | |
| 42 | 44213200 | SAW CUTS | 130 | FOOT | $5.00 | $10.00 | $15.45 | $15.00 | $10.00 | $36.00 | $9.50 | |
| 43 | 48203021 | HMA SHOULDERS 6 | 69 | SQ YD | $150.00 | $160.00 | $145.00 | $77.30 | $145.00 | $90.00 | $185.00 | |
| 44 | 50102400 | CONC REM | 21.8 | CU YD | $2,200.00 | $1,800.00 | $1,925.50 | $2,300.00 | $4,810.00 | $2,200.00 | $2,750.00 | |
| 45 | 50157300 | PROTECTIVE SHIELD | 661 | SQ YD | $1.00 | $45.00 | $142.90 | $0.0100 | $36.00 | $102.00 | $95.00 | |
| 46 | 50300255 | CONC SUP-STR | 23.2 | CU YD | $1,600.00 | $2,200.00 | $2,527.45 | $2,820.00 | $5,785.00 | $2,500.00 | $2,267.52 | |
| 47 | 50300260 | BR DECK GROOVING | 1,335 | SQ YD | $9.00 | $8.50 | $7.90 | $8.40 | $10.25 | $9.00 | $14.00 | |
| 48 | 50300300 | PROTECTIVE COAT | 1,356 | SQ YD | $1.00 | $1.00 | $2.80 | $1.63 | $2.30 | $4.50 | $4.00 | |
| 49 | 50800205 | REINF BARS, EPOXY CTD | 2,510 | POUND | $4.00 | $3.00 | $3.05 | $4.67 | $3.65 | $3.90 | $5.75 | |
| 50 | 50800515 | BAR SPLICERS | 12 | EACH | $95.00 | $65.00 | $105.25 | $135.00 | $225.00 | $180.00 | $75.00 | |
| 51 | 52000110 | PREF JT STRIP SEAL | 202 | FOOT | $225.00 | $235.00 | $374.70 | $489.00 | $170.00 | $267.00 | $285.00 | |
| 52 | 58700300 | CONCRETE SEALER | 40 | SQ FT | $125.00 | $10.00 | $8.50 | $125.00 | $125.00 | $13.00 | $3.00 | |
| 53 | 59000200 | EPOXY CRACK INJECTION | 78 | FOOT | $100.00 | $55.00 | $75.00 | $90.00 | $150.00 | $58.00 | $75.00 | |
| 54 | 60600095 | CLASS SI CONC OUTLET | 2.5 | CU YD | $925.00 | $450.00 | $2,831.05 | $2,500.00 | $625.00 | $2,900.00 | $300.00 | |
| 55 | 60618390 | CONC MED SURF CORR | 872 | SQ FT | $12.00 | $18.00 | $15.10 | $25.00 | $24.50 | $29.00 | $45.00 | |
| 56 | 60620000 | CONC MED TSB6.24 | 418 | SQ FT | $30.00 | $22.00 | $29.05 | $35.00 | $32.50 | $40.00 | $55.00 | |
| 57 | 63000001 | SPBGR TY A 6FT POSTS | 100 | FOOT | $17.00 | $18.00 | $45.00 | $16.13 | $45.00 | $52.00 | $55.00 | |
| 58 | 63100075 | TRAF BAR TERM T5A | 1 | EACH | $1,400.00 | $1,500.00 | $1,000.00 | $1,347.14 | $1,000.00 | $1,170.00 | $1,850.00 | |
| 59 | 63200310 | GUARDRAIL REMOV | 113 | FOOT | $23.00 | $22.00 | $20.00 | $21.32 | $20.00 | $23.00 | $25.00 | |
| 60 | 63302400 | REM RE-E T B TERM T5 | 1 | EACH | $1,000.00 | $1,000.00 | $1,300.00 | $987.57 | $1,300.00 | $1,521.00 | $1,750.00 | |
| 61 | 63302700 | REM RE-E T B TERM T6 | 1 | EACH | $2,700.00 | $2,800.00 | $3,500.00 | $2,577.19 | $3,500.00 | $4,095.00 | $6,500.00 | |
| 62 | 67100100 | MOBILIZATION | 1 | L SUM | $60,000.00 | $66,000.00 | $76,640.00 | $80,485.99 | $84,000.00 | $112,000.00 | $80,000.00 | |
| 63 | 70107025 | CHANGEABLE MESSAGE SN | 336 | CAL DA | $27.00 | $33.00 | $30.00 | $27.00 | $27.00 | $35.00 | $33.00 | |
| 64 | 70300150 | SHRT TRM PAVT MK REM | 4,669 | SQ FT | $0.3000 | $0.1000 | $0.9000 | $0.4000 | $0.7500 | $0.5000 | $1.25 | |
| 65 | 70307100 | TEMP PVT MK LTR & SYM T4 TAPE | 182 | SQ FT | $3.50 | $3.50 | $5.00 | $3.50 | $3.50 | $9.30 | $3.65 | |
| 66 | 70307120 | TEMP PVT MK L4 T4 TAPE | 12,040 | FOOT | $1.15 | $1.20 | $1.30 | $1.15 | $1.15 | $1.40 | $1.25 | |
| 67 | 70307130 | TEMP PVT MK L6 T4 TAPE | 1,073 | FOOT | $1.75 | $1.50 | $1.60 | $1.75 | $1.75 | $3.50 | $1.50 | |
| 68 | 70400100 | TEMP CONC BARRIER | 763 | FOOT | $25.00 | $36.00 | $47.30 | $35.00 | $35.00 | $52.50 | $39.00 | |
| 69 | 70400200 | REL TEMP CONC BARRIER | 563 | FOOT | $3.00 | $8.00 | $12.45 | $5.00 | $10.00 | $8.70 | $9.00 | |
| 70 | 70600241 | IMP ATTN TEMP NRN TL2 | 2 | EACH | $3,500.00 | $6,000.00 | $4,000.00 | $3,500.00 | $3,500.00 | $5,616.00 | $8,500.00 | |
| 71 | 70600340 | IMP ATTN REL NRD TL2 | 2 | EACH | $750.00 | $2,000.00 | $1,500.00 | $750.00 | $750.00 | $1,638.00 | $3,500.00 | |
| 72 | 78000100 | THPL PVT MK LTR & SYM | 73 | SQ FT | $5.00 | $6.00 | $10.00 | $5.75 | $5.00 | $5.80 | $6.25 | |
| 73 | 78000200 | THPL PVT MK LINE 4 | 13,730 | FOOT | $0.7500 | $0.8000 | $0.8000 | $1.05 | $0.7500 | $0.9000 | $1.20 | |
| 74 | 78000400 | THPL PVT MK LINE 6 | 450 | FOOT | $2.00 | $2.20 | $1.20 | $1.72 | $2.00 | $1.40 | $2.00 | |
| 75 | 78004635 | PREF PL PM TD STD L 7 | 110 | FOOT | $19.00 | $20.00 | $48.00 | $25.00 | $19.00 | $35.00 | $28.00 | |
| 76 | 78009004 | MOD URETH PM LINE 4 | 802 | FOOT | $5.00 | $6.00 | $5.15 | $4.00 | $5.00 | $8.70 | $4.50 | |
| 77 | 78011040 | GRV RCSD PVT MRKG 8 | 110 | FOOT | $7.25 | $8.00 | $33.50 | $0.9500 | $7.25 | $21.00 | $1.25 | |
| 78 | 78100100 | RAISED REFL PAVT MKR | 8 | EACH | $125.00 | $135.00 | $500.00 | $225.00 | $125.00 | $684.00 | $250.00 | |
| 79 | 78100200 | TEMP RAIS REF PVT MKR | 58 | EACH | $6.00 | $16.00 | $15.00 | $6.00 | $6.00 | $16.00 | $20.00 | |
| 80 | 78200011 | BARR WALL REF TYPE C | 62 | EACH | $6.00 | $15.00 | $15.00 | $6.00 | $6.00 | $16.00 | $11.00 | |
| 81 | 78300200 | RAISED REF PVT MK REM | 16 | EACH | $25.00 | $30.00 | $15.00 | $46.00 | $25.00 | $11.00 | $55.00 | |
| 82 | 78300202 | PVT MKG REM WTR BLAST | 5,018 | SQ FT | $1.00 | $3.30 | $2.50 | $1.00 | $1.00 | $1.50 | $4.50 | |
| 83 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $13,500.00 | $15,000.00 | $13,500.00 | $13,500.00 | $13,500.00 | $15,000.00 | $15,500.00 |